Loading...
HomeMy WebLinkAbout1.14 Section 4-108Source Gas SECTION 4 -108 VACATION OF A COUNTY ROAD OR PUBLIC RIGHTS OF WAY. This project will not be vacating a public or county road or right -of -way. The Spring Valley Compressor Station (SVCS) can be accessed by taking 1 -70 to Exit 116 (Glenwood, CO) to CO- 82E south towards Aspen. The SVCS is located off of County Road 115 on a private access. The closest intersection to the SVCS is County Road 119 and County Road 115, which is approximately 0.9 miles to the northwest of the turnoff onto the private drive leading to the SVCS. The private drive is located on the south side of County Road 115. The closest major intersection is Spring Valley Road and Highway 82 approximately 5.3 miles to the southwest. The site is located in the SE '/a NW ' /a, Section 34, T6S, R88W, 6th Principal Meridian. The access off of County Road 115 will be upgraded and has been discussed with Garfield County Road and Bridge (see e-mails included). SVCS — Location & Extent Ashlee Lane From: Ashlee Lane Sent: Thursday, May 30, 2013 11:15 AM To: Ashlee Lane Subject: FW: Planning Meeting Handout Follow Up Flag: Follow up Flag Status: Flagged From: Green, Donald fmailto :Donald.Green @sourcegas.com] Sent: Monday, March 04, 2013 1:57 PM To: Ashlee Lane Cc: Dick, Cliff Subject: RE: Planning Meeting Handout Ashlee, I met with Mike Prehm with Garfield County Road and Bridge today. Garfield County is ok with our driveway access plan as long as we follow the guidelines outlined in the Garfield County Drive way permit. Mike was going to contact Molly and relay the same message to her. Thanks Donald Green Project Manager 970 -618 -1521 970- 928 -0418 Donald.green @sourcegas.com 1 Ashlee Lane From: Ashlee Lane Sent: Thursday, May 30, 2013 11 :18 AM To: Ashlee Lane Subject: FW: New Compressor Station Site Access Follow Up Flag: Follow up Flag Status: Flagged Original Message From: Green, Donald jmailto :Donald.Grcen(rasourcegas.comj Sent: Monday, March 04, 2013 2:16 PM To: Ashlee Lane Subject: FW: New Compressor Station Site Access Just an FYI on the road Access. See Below. Donald Green Project Manager 970 - 618 -1521 970 -928 -0418 Donald.grcen(d), sourccgas.com Original Message From: Michael Prehm jmailto:ninrchnu'o garlield- county.comy Sent: Monday, March 04, 2013 2:14 PM To: Molly Orkild - Larson Cc: Green, Donald Subject: New Compressor Station Site Access Hi Molly, I met with Source Gas (Don) today at the new location along County Road 115. He showed me were the new driveway access would be located. We went over the requirements for a driveway permit. With the drawings you sent me and what Don explained to me, this location would be a good spot to access their new site. let me know if I can help you on anything. Mike 1 Ashlee Lane From: Green, Donald <Donald.Green @sourcegas.com> Sent: Thursday, June 20, 2013 5:15 PM To: Ashiee Lane Subject: Fwd: Sourcegas Access Road design question Just an FYI to the access road Sent from my iWhone Donald green Project manager Sourcegas 618 -1521 Begin forwarded message: From: Michael Prehm <mprehm kgarficld- county.eom <mailto:mprchm garfcld- county.com» Date: June 20, 2013, 4:34:08 PM MDT To: "Green, Donald" <Donald.Grecn @sourcegas. com <mailto:Donald.Grccn &source as.com» Subject: RE: Sourcegas Access Road design question Donald, Thanks for running this by me. While under construction this would be fine. I would like to see it brought back to the original design after. It is important that vehicles are 90 degrees to the roadway so that they have a clear view both directions. Mike Road & Bridge Foreman / Glenwood District From: Green, Donald [Donald. Green @sourcegas.com< mailto :Donald.Grcen @sourcegas.coin >] Sent: Thursday, June 20, 2013 2:01 PM To: Michael Prehm Subject: Sourcegas Access Road design question Mike, Here is the Drawing for the entry way off of County road 115. Can you please review and give me a call if you have any questions. Thanks i Donald Green Project Manager 970- 618 -1521 970 - 928 -0418 Donald.grccnOisourccgas. coin< mailto :Donald.grccn(sourccgas.com> 2 • f • it .0.. Legend zi■NER County Roads Proposed Access Proposed Compressor Site Township Section QtrSection till S 0 250 500 1,000 Feet Author: jharris Date: 6/21/2013 Spring Valley Compressor Station Proposed Site Access Source Gas DISCLAIMER : This Geographic Information System (GIS) and its components are designed as a source of reference for answering inquiries, for planning and for modeling. GIS is not Intended, nor does it replace legal description information in the chain of title and other information contained in official government records such as the County Clerk and Recorders office or the courts. In addition. the representations of locations in this GIS cannot be substituted for actual legal surveys.