HomeMy WebLinkAbout1.31 Storm Water & Soil Management Plan 10.23.2008Site - Specific Storm -Water / Soil Management Plan
Page 1/5
Site Name: Well Pad 35 -BV
Date of Plan: October 23, 2008 Rev. 1
1. Site Activity ! Description
Background Information: Information provided in this
document is intended to supplement the existing Skinner
Ridge Storm Water Management Plan. This document
specifically addresses the requirements for the Well Pad
(WP) 35 -BV.
Site Purpose: WP 35 -BV will be used for multiple
purposes to support the natural gas field operations,
including drilling up to 22 directionally wells, primary
liquid / gas separation equipment, placement of
hydraulic fracturing equipment and associated fracturing
(frac) tanks, and ancillary equipment required to extract
raw natural gas from the wells and convey it to the to the
CPF (see Drawings PBSR-598358VW- PIP- PLN -URS-
00000- 00002 -00 and PBSR- 59835BV -C IV -S KT -URS-
00000- 00002). Well drilling and fracing and natural gas
extraction activities will be regulated by and take place
under the administration of the Colorado Oil and Gas
Conservation Equipment (COGCC). Remaining space
on the well pad will be used to locate the water
management systems, that include a water distribution
system, temporary Stage 2 water system, water
management tanks, and a water management tank
pump system.
The temporary water management systems will operate
by pumping produced water from the CPF to WP 35 -BV
where it will be stored in ten (10) 500 barrel (bbl) (21,000
gallon) frac tanks. Pumping to the frac tanks from the
CPF will occur on a batch basis. From the frac tanks,
the stored produced water will be pumped through 10
micron filters and subsequently be stored in two 500 bbl,
vertical "clean" tanks, also on a batch basis. Produced
water will be pumped from the "clean" tanks through a
four inch pipeline, approximately 5 miles, to Well 8 -1 for
injection disposal. The following details pertain to the
temporary water management systems:
• All pumps will be trailer mounted and diesel engine
powered
• The injection pumps will be equipped with high
pressure shutdown devices
• The operating status of all pumps will be monitored
in the CPF control room
• Liquid levels in the "clean" tanks will be monitored in
the CPF control room
• The volume of produced water injected into Well 8 -1
will be measured at WP 35 -BV
• The volume of injected water and casing -head
pressure will be recorded at Well 8 -1.
The area surrounding the ten frac tanks, clean tanks and
pumps will be enclosed by a small earthen containment
berm. A trench will be formed to route any spills
collected in the berm to the existing on -site, lined liquids
pit. Liquids collected in the lined pit will be removed for
disposal by vacuum truck or re- introduced into the frac
tanks for disposal.
Once the permanent water management systems are
permitted, constructed and commissioned the temporary
storage equipment (frac tanks) will be removed from WP
35 -BV.
The CPF removes the remaining water and condensate
(a blend of low- density hydrocarbons) from the extracted
natural gas (which is not removed by the on pad primary
separation equipment) prior to gas transfer into the
Program 30 -inch sales pipeline. Condensate removal is
necessary to prevent pipeline multiphase flow problems
and to collect the valuable commodity for sales (source
of propane, butane, pentane and heavier hydrocarbon
fraction). The water must be removed to prevent
corrosion and hydrate formation in the pipelines and to
prevent the multiphase flow problems.
Site Location: The proposed facility will be located
about 0.1 miles west of an existing intersection of two
ranch roads near the confluence of Clear Creek and
Tom Creek (see Maps - Figure 2). The intersection is
located about 2.5 miles north northwest of the end of
County Road (CR) 211. The site can be accessed from
Interstate 70, exit 62, by traveling north on local Road
45N. Road 45N north of De Beque, Colorado, is also
known as Roan Creek Road /Drive and CR 204 (Garfield
County). The intersection of CR 211 and CR 204 is
located about 12.5 miles north northwest of De Beque
and this facility can be accessed by continuing north on
CR 211.
Site Area /Disturbed Area: WP 35 -BV would occupy
about 3.4 acres. A general coordinate for the facility is
39 °34'19.77 "N latitude, 108 °21'0.18 "W longitude NAD
831 WGS 84. The total footprint of WP 35 -BV area will
be about 3.4 acres, which was previously disturbed
during the installation of the existing Skinner Ridge
Service Pad 598 -35 -BV (Service Pad). The new WP 35-
BV will be positioned on the existing Service Pad.
Because the area needed for WP 35 -BV and the water
management systems was previously developed
(graded, etc.) heavy equipment use will be limited to
building foundations and installing and connecting the
water distribution systems, tanks, filters, and pumping
components. This heavy equipment may include but not
be limited to trucks and flat -bed trailers; dump trucks;
loaders; bull dozers; backhoes; graders; scrapers;
rollers; water suppression tank trucks; and cranes. This
equipment may be operated 24 -hours per day, 7 days a
week.
General Topography: The WP 35 -BV site lies in the
Douglas - Plateau area. it consists of narrow foothills
valleys, high rolling plateaus dissected by steep
canyons, narrow mountain valleys, and high mountains.
The area of exploration and production is mostly
rangeland, with the primary limitations for grazing being
steep slopes, short growing season, rockiness, and
limited water.
Geology: The underlying rocks are relatively late
geologic age, mostly from the Cretaceous or Tertiary
periods. They range from hundreds to thousands of feet
in thickness and are generally tilted and unfolded. The
formations commonly extend of broad areas.
Site - Specific Storm -Water / Soil Management Plan
Page 2/5
Site Name: Well Pad 35 -BV
Date of Plan: October 23, 2008 Rev. 1
Property elevations vary from 5,800 ft (valley floor) to
8,500 ft (Roan Plateau). The Roan Plateau extends
north into Rio Blanco County, and surrounds the Skinner
Ridge development site. The Roan Plateau consists of
the generally stable Green River Formation.
Site Soils / Slopes: The dominant soil type is Cumulic
Haploborolls, a soil series that is placed in the hydrologic
soil group B. Cumulic Haploborolls soils having a
moderate infiltration rate when thoroughly wet and
consist chiefly of moderately deep or deep, moderately
well drained to well drained soils with moderately fine to
moderately coarse texture. These are alluvial soils with a
moderate rate of water transmission. WP 35 -BV area
slopes range from to 1 to 4 percent.
Information published by the National Resource
Conservation Service (NRCS) describes the area soils
as deep, well to poorly drained, formed in alluvium
dominated mostly by the Green River and Wasatch
shale formations. The NRCS information details a
surface layer of dark grayish brown gravelly sandy clay
loam about eight inches thick, followed by about 12-
inches of grayish brown very channery sandy clay loam.
The subsoil is grayish brown clay loam about eight
inches thick The upper part of the substratum is light
brownish gray very gravelly loamy sand about 16 inches
thick, while the lower part of the substratum to a depth of
greater than 60 inches is a yellow very gravelly sand. In
some areas the surface layer is loam or silty clay loam.
Permeability is moderate to moderately slow. And runoff
is generally slow; the hazard of water erosion is slight.
These soils are subject to brief periods of flooding as a
result of snowmelt and intense thunderstorms in the
spring and summer.
Preliminary geotechnical information indicate that the
site is covered with about one foot of topsoil (that will be
stockpiled) with about 10 feet of underlying medium to
stiff clay with shale fragments (Unified Soil Classification
System soil classification CL / SH).
The erodability of the soil based upon Revised Universal
Soil Loss Equation Version 2 (RUSLE2) is 0.17 for the Kf
(the susceptibility of the surface horizon to sheet and rill
erosion by water) and 3 for the T factor (the estimate of
the maximum average annual rate of soil erosion by
wind and /or water that can occur without affecting crop
productivity over a sustained period (rate is in tons per
acre per year).
Receiving Waters and Hydrology: Storm -water runoff
from construction activities will potentially flow south -
southwest towards Tom Creek, a tributary to Clear
Creek and / or Clear Creek, Segment 14b of the Lower
Colorado Sub -basin and Basin (Regulation 37,
Standards for the Lower Colorado River Basin). Clear
Creek is a tributary of Roan Creek, which ultimately
flows to the Colorado River.
The saturated zone in portions of the area is about 54
inches depth to water, primarily due to the close
proximity to Tom Creek and Clear Creek.
Existing Vegetation: Site is currently vegetated with
grasslands used for cattle grazing. Western Wheatgrass
(Pascopyrum smithii), Basin Wildrye (Leymus cinereus),
and Basin Big Sagebrush (Artemisia tridentate) are
common in this area, which is bordered on the north,
east and south by riparian woodlands. Dominant
observed trees in the area were Boxelders (Acer
negundo L.), and the introduced and naturalized New
Mexico Locust (Robinia neomexicana).
Observed noxious weeds in the area include Bull Thistle
(Cirsium vulgare), Common Mullein (Verbascum
thapsus), Downy Brome or Cheatgrass (Bromus
techtorum), Musk Thistle (Carduus nunfans),
Houndstongue (Cynoglossum offcinale), and Tamarisk
(Tamarix ramosissima). Tamarisk sp. is primarily
confined to the Clear Creek channel. Weed control will
be part of the ongoing site reclamation plan.
Description of Construction Activity: Because the
area that will be used as WP 35 -BV was previously
disturbed during the installation of the existing Skinner
Ridge Service Pad 598 -35 -BV (Service Pad)
construction activities at site will be limited, but may
involve grubbing, removal and stockpiling of topsoil,
followed by cut and fill operations necessary to construct
and install the needed facilities. Details of the pad
construction can be found on Drawings PBSR-
598358VW- PIP -PLN -URS- 00000 - 00002 -00 and PBSR-
59835BV-C IV-SKT- URS - 00000 - 00002). Prior to any
earth moving, erosion control BMPs will be installed to
minimize site erosion and sedimentation.
BMPs will be installed and maintained throughout the
initial, interim, and final grading stages. Initial and
interim grading activities will include the construction of
the facility. Final grading will be completed after the
completion of the installations to adequately address site
drainage issues. The interior of the site may include
graveled roads / parking areas and re- vegetated areas.
Upon completion of facility, final stormwater controls will
be installed and maintained throughout the life of the
project.
Soil Management: Topsoil is an extremely valuable
resource necessary for re- vegetation activities that are
mandated by several regulatory agencies (CDPHE,
COGCC, Garfield County). Because topsoil formation is
a very slow process [ranges from <0.25 mm per year for
cold, dry climates (similar to Colorado) to >1.5 mm per
year in humid, warm climates], every effort shall be
made to conserve existing topsoil by careful excavation
and placement in a dedicated topsoil stockpile located
east of the primary facility. Additional information
concerning soil management is provided in URS /
Chevron Specification for Site Preparation / Stabilization,
Soil Management, Earthwork, and Backfill.
Potential Sources of Storm -Water Pollution:
• Sediment from disturbed areas and /or construction
stockpile
• Oil products associated with construction vehicles
(e.g., refueling operations, engine oil leaks, etc.)
• Vehicle washing for weed control
• Trash and sanitary facilities
Possible storm -water impacts related to these sources
are summarized on page 3.
Proposed Construction Sequence: (6/2009 thru —
9/2009)
• Stake site and clear vegetation
• Remove and stockpile topsoil
Site - Specific Storm -Water / Soil Management Plan
Page 3/5
Site Name: Well Pad 35 -BV
Date of Plan: October 23, 2008 Rev. 1
• Install initial storm -water controls (including
stockpile)
■ Grading: general excavation and fill, berm floodplain
construction, soil compaction, grading of access and
interior roads
• Construction of spill containment berm
• Excavation of building / enclosure foundations
• Installation of building / enclosure foundations
• Construct / install buildings
• Final grading of all site features
• Stabilization / re- vegetation of interior non -road
areas
• Install permanent storm -water controls
• Erect fencing
2. Site Map and Erosion Control — SEE GEOTECHNICAL ENGINEERING GROUP, INC. (GEG) DRAWINGS FOR THE 35 -BV
ACCESS ROAD STORM WATER MANAGEMENT PLAN AND STORM WATER MANAGEMENT PLAN WELL PAD 598- 35 -BV.
DETAILS OF THE SITE STORM -WATER CONTROLS (BEST MANAGEMENT PRACTICES (BMPs) ARE PROVIDED ON THE GEG
DRAWING STORM WATER MANAGEMENT PLAN WELL PAD SKR 578 -35 -BV BMPs.
Information included on Erosion Control Plan Drawing:
• Construction site boundary
• Soil disturbance areas
■ Surface waters
• Existing and new access roads
• Locations of construction & permanent erosion controls (BMPs)
3. Storm -Water Management Controls -- NOTE: ALL BMPs ARE SUBJECT TO MODIFICATION AS REQUIRED BY SITE -
CONDITIONS. SITE SPECIFIC SWMP AND ASSOCIATED EROSION CONTROL DRAWING(S) WILL BE MODIFIED TO REFLECT FIELD
CONFIGURATION AS SOON AS MODIFICATION IS COMPLETED. BMP INSTALLATION NARRATIVE PROVIDED AS BMP GUIDE
ATTACHMENT TO THE MASTER PLAN. BMP'S ARE SHOWN ON GEG DRAWING STORM WATER MANAGEMENT PLAN WELL
PAD SKR 578 -35 -BV BMP.
Source
Occurrence
Potential Storm
Water Impact
Distance to
Surface Water
Potential
Runoff
Concentration
BMPS (')
Sediment
transport
from
construction
activities
Precipitation
events / wind
events
High (w /o BMPs)
—Low (with well
maintained
BMPs)
.4-- 2D to 1,000+
feet
High (without
BMPs) — Low
(with BMPs)
• Straw wattles
• Straw bales
• Erosion control blankets
• Silt fencing, as needed
• Check dams
• Ri•ra•
Oil products
associated
with
condensate
transport and
construction
vehicles (2)
Dependent on
vehicle
maintenance
Dependent on
fluid source
(e.g., high for
vehicle refueling;
low for minor
crankcase
20 to 1,000+
feet
Dependent of
fluid source —
majority typically
contained in
soils
Inspect site for possible leakage
• Provide designated overnight
parking area for construction
vehicles — check daily for leakage
• Scheduled vehicle maintenance
teaka.e
Vehicle
washing for
weed control
(not required
after {3) er
Limited to
when
construction
vehicles leave
the area
Low — water and
sediment from
this process
contained by
lined basin
9,000+ feet
Low — limited
quantities /
controlled by
lined basin
Plastic lined basin with straw wattle
berm or equivalent
Trash and
facilities
(biocide and
domestic
wastewater)
Primarily
associated
with wind
events or
sanitary
facilities
servicing
activities
Low if inspection
process properly
implemented
y 20 to 1,000+
feet
Low — limited
fluid volume
typically
associated with
sanitary facilities
• Bear -proof trash receptacle with
weekly pickup (minimum) or
restrict food consumption to
separate location (e.g., temporary
office)
fice)
• Keep site clear of general
construction trash — verify during
weekly inspections
Sanitary Sanity facilities Stake down to
prevent tipping during wind events
1 instruct vendor to minimize spills
& leaks during servicing / service
free uentl
) See Erosion Control Details on GEG Drawing Storm Water Management Plan Well Pad SKR 578 -35 -BV BMP.
Site - Specific Storm -Water / Soil Management Plan
Page 4/5
Site Name: Well Pad 35 -BV
Date of Plan: October 23, 2008 Rev. 1
Controls and response actions covered in site Spill Prevention, Control, and Countermeasures (SPCC) Plan.
(3) Per Garfield County guidance (October 26, 2007 meeting with Steve Anthony, Garfield County Vegetation Manager).
4. Operational Stabilization / Reclamation
Operational Stabilization: Once construction is
completed, exterior berms and other disturbed areas will
be re- vegetated with the Seed Mix for Sites below 7,000
ft, using application rates and plant species designated
in the URS / Chevron Specification for the Re- Vegetation
of Disturbed Areas, document number: PBSR- ALL -CIV-
SPC- URS - 00000- 00004 -00. Any adjacent areas
disturbed by construction traffic will be re- vegetated at
this time. Final stabilization will be complete when areas
have returned to 70- percent of the original vegetation
cover. The gravel access roads (installed per
construction drawings / specifications) will provide final
stabilization in these areas but will be monitored to
determine if maintenance operations are required.
Noxious weed control will be continued on an as needed
basis.
Reclamation: The site will be reclaimed after the end of
its operational life in accordance with Garfield County
land use requirements. Reclamation activities will
include: removing pipelines, gravel from roads and
access pads; re- grading the site to the original contours
(approximate); replacing topsoil; revegetation with
appropriate seed mix; and installing and maintaining any
required storm -water controls until final stabilization is
achieved.
Site inspections will be conducted in accordance with the
Master SWMP (documented by Master Inspection
Form).
5. Inspection / Maintenance
Site - specific areas requiring inspection:
• Site perimeter and nearby areas (e.g., adjacent stream channel — for possible trash)
• Disturbed / re- vegetated areas
■ Soil stockpiles
• Vehicle wash area
• Trash container / sanitary facilities
■ BMPs
Site- Specific Storm -Water / Soil Management Plan
Page 5/5
Site Name: Well Pad 35 -BV
Date of Plan: October 23, 2008 Rev. 1
6. Site Specific SWMP Revisions
Description of revision
Initiated /approved by:
Date
Note: Insert additional sheets as needed.
7. Site- Specific SWMP Administrator (only required if different from Site Administrator)
Signature:
Title:
Printed Name: Date: