Loading...
HomeMy WebLinkAbout1.08 Project facilitiesProject Facilities PROJECT FACILITY: The project consist of permanent facilities as well as temporary project facilities that will be necessary only during construction of the project. A 55 foot wide work Right -of -Way will be required on BLM hind during construction of which 30 feet will be maintained as a permanent pipeline ROW. On private Iand a 55 foot wide work Right -of -Way will be required during construction, of which 30 feet will be maintained as a permanent pipeline ROW. Other permanent facilities will be multiple above ground valve sets where laterals from individual wells tie into the trunk line. There will be two temporary staging areas. The staging areas will be property owned by EnCana Oil & Gas in Section 36 and Section 21. There will be no other additional work space areas required along the ROW.