HomeMy WebLinkAbout06- Golder B- Supplemental ReportGolder
Associates
March 16, 2012
Ricky Bates
Enterprise Products Company, Inc./Mid-America Pipeline Co.
1100 Louisiana Street
Houston, TX 77002
RE: SUPPLEMENTAL REPORT TO GEOTECHNICAL SITE INVESTIGATION
NORTH SIDE OF BAXTER PASS, COLORADO
FOR WESTERN EXPANSION PROJECT PHASE II
Dear Ricky:
Project No. 113-91752
1.0 SCOPE AND PURPOSE
This Supplemental Report addresses the proposed locations of HDD drill paths as presented in drawings
dated November 3, 2011, transmitted to us by Rooney Engineering on December 14, 2011. These
drawings are revised from those presented in Golder's report, Summary of Geotechnical Site
Investigation, North Side of Baxter Pass, Colorado, for Western Expansion Project Phase Il, dated
December 2011. Included herein are comments specific to the revised HDD alignments, as well as
geotechnical -related issues pertaining to the option of conventional trench construction, raised during the
conference call on December 14, 2011.
This Supplemental Report builds upon the information and conclusions presented in the site investigation
report, Summary of Geotechnical Site Investigation, North Side of Baxter Pass, Colorado, for Western
Expansion Project Phase 11, dated December 2011. The December report presented the results of site
investigation at the Woodpile Landslide and the Columbine Landslide Complex, including the findings of
the subsurface drilling, and laboratory testing of samples. Information for the proposed McAndrews HDD
was also presented in that report, but was limited to information provided by Enterprise Products
Company, showing the findings of subsurface investigation, completed in the late 1990's, related to the
existing HDD (the Brown Line). No further site investigation or testing has been done as part of this
supplemental study.
The December report includes detailed descriptions of the local geology, and conditions observed at each
of the HDD areas. This information is not repeated herein, except as appropriate to the discussion of the
revised HDD alignments. The reader is referred to the December Report for supporting details.
Much of the pipeline corridor from the summit of Baxter Pass to below McAndrews Lake traverses
landslide deposits. It is not reasonably feasible to avoid all of the potential hazard areas. The
geotechnical recommendations for the WEP2 project focus on avoiding or mitigating those areas which
have been identified as recently or historically (past 50-100 years) active.
The proposed pipeline will lie within essentially the same corridor as existing pipelines currently in
operation. As is the case for all pipelines through this area, there is the potential for re -activation of
landslide deposits, regardless of age, which could occur from a number of causes, including wetter
climate trends, unusually wet individual years, and/or disturbance by human activity. The existing
pipelines at Baxter Pass, and those in similar terrain elsewhere, are being successfully managed in
landslide areas, through various types of monitoring and appropriate mitigation response plans.
Therefore, we believe the HDDs proposed through Woodpile, Columbine, and McAndrews Lake areas,
s:\enterprise\2011 \2011 columbinesprings\wep2 supplemental report 2-2012\stamped final report 3-2012\wep2 supplemental.docx
Golder Associates Inc.
595 Double Eagle Court, Suite 1000
Reno, NV 89521 USA
Tel: (775) 828-9604 Fax: (775) 828-9645 www.golder.com
Golder Associates: Operations in Africa, Asia, Australasia, Europe, North America and South America
Golder, Golder Associates and the GA globe design are trademarks of Golder Associates Corporation
Ricky Bates March 16, 2012
Enterprise Products Co./Mid-America Pipeline 2 113-91752
combined with appropriate monitoring as discussed below, are strategies that meet or exceed current
standards of practice for constructing and operating pipelines in such terrain.
2.0 COMMENTS ON THE REVISED HDD ALIGNMENTS
The following paragraphs provide brief discussion on each of the three HDD alignments, pertinent to the
most recent revised drawings transmitted to us, dated November 3, 2011. In two locations (Columbine
slide and McAndrews Lake), special conditions related to existing landslide deposits are present at a
proposed endpoint of the HDD. In each case recommendations are given for mitigating these conditions,
without the need to revise the latest (November 3, 2011) proposed HDD plans. Certainly, relocation of
the respective end points of the proposed bores could be used as an alternative to mitigating these
locations. However, based on discussions with both Rooney Engineering and Enterprise Products,
relocation is not the preferred approach. We agree that each of these locations can be appropriately
mitigated by other means, without the need to change the present design.
2.1 Woodpile Landslide HDD
Figure 1 shows the revised proposed HDD alignment through the Woodpile landslide area, in both plan
and profile. As described in Golder's December 2011 report, most of the area crossed by this HDD is
within or underlies landslide deposits. The exception is the portion near the exit (south) end of the
proposed HDD, from about Station 9+00 to 13+36, where bedrock appears to be in place at or near the
ground surface. North of Station 9+00, the remainder of the alignment crosses landslide deposits.
However:
• The most recent landslide activity appears to be limited to the area from about Station
5+50 to 8+80. The alignment also runs along the downslope edge of an older slide block
from about station 4+30 to 5+50, but this area is not believed to be recently active;
• The proposed HDD as shown in the drawings is to be located in bedrock below the base
of the landslide deposits at about Station 6+00, based on the findings in the borehole
(WP -1,) from the 2011 drilling investigation, which was located near Station 6+00;
■ Based on our interpretation of available surface and subsurface information, we believe
that the proposed HDD will likely be within bedrock from about Station 2+00 or 3+00 to its
south endpoint at Station 13+36.
From the entry point to about Station 2+00 to 3+00, the HDD may be within older (not recently active)
landslide deposits. Based on the findings of the drilling investigation, it is likely that these deposits
contain significant cobbles and boulders, within a predominantly clay and silt matrix. Boulders could
range up to several feet in diameter.
The bedrock expected to be encountered in the Woodpile HDD is of the Wasatch Formation from the
north end to about Station 9+00. These rocks are composed of massive mudstones, with layers of fine to
coarse-grained conglomerate sandstone which can range up to 50 feet in thickness. South from about
Station 9+00, the rock exposed at the ground surface is of the Douglas Creek Member of the Green River
Formation. These rocks are primarily composed of fine to very fine-grained sandstones, slightly
calcareous siltstones, and silty claystones, with some limestone layers. The lower part of the formation,
which is most likely to be encountered in the HDD, also contains flaky clay shales interbedded with algal
limestone beds. The HDD bore is expected to cross the contact between these rock formations
somewhere between Stations 7+50 and 12+00.
2.2 Columbine Landslide Complex HDD
Figure 2 shows the revised proposed HDD alignment through the Columbine Landslide area, showing
both plan and profile. As described in Golder's December 2011 report, most of the area crossed by this
HDD is within or underlies landslide deposits. Figure 2 shows the extent of recent or likely historic areas
of landslide and slope movements, extending from about Station 8+40 to the south end of the HDD at
s:\enterprise\2011\2011 columbinesprings\wept supplemental report 2-2012\stamped final report 3-2012\wep2 supplemental.docx
Golder
Associates
Ricky Bates March 16, 2012
Enterprise Products Co./Mid-America Pipeline 3 113-91752
Station 25+18 of the currently -proposed HDD alignment. (Note: These limits are based on the Plan View
of Figure 2. The limits of the Columbine Landslide Complex shown in the HDD Profile View of Figure 2
differs from the limits shown in the Plan View.)
It is also possible that older landslide deposits blanket the slopes from Station 0+00 to 8+40. However,
mapping by the U.S. Geological Survey (Johnson, 1985), indicates that a large portion of this area is
characterized by bedrock of the Wasatch Formation. At the depth of the HDD, based on Johnson's 1985
mapping and the findings of the 2011 drilling investigation, we believe that the HDD will penetrate bedrock
of the Wasatch Formation from about Station 0+50 to 22+00. It must be understood that this range is
merely an estimate, as no borings were drilled along the south -most 800 feet of the revised alignment.
Also, the borings drilled were along the existing pipeline right-of-way, at a distance of as much as 380 feet
from the proposed alignment, and thus may not accurately reflect conditions under the proposed
alignment itself.
The HDD is anticipated to transition from bedrock into older landslide deposits below more recently -active
landslide areas from about Station 22+00 (a rough estimate as described above) to the exit point at
Station 25+18. However, near the proposed exit point near Station 25+18, there is a small, recently
active slump on the existing right-of-way cut slope. Based on the exit point location shown in Figure 2,
the bore pit and a portion of the last 50 or so feet of the bore may be located below this feature. This
feature is interpreted to be shallow, and confined to the older cut slope. Great care needs to be taken in
this area to avoid re -activating or expanding the unstable area, particularly during work in the bore pit.
We recommend that the slope in this area should be laid back to a more stable configuration prior to
beginning work on the HDD in this area. Laying back the slope may remove most or all of this feature,
since it is relatively small.
At the north end of the bore, near the proposed entry point, borehole CS -1 encountered soils to a depth of
about 18 feet below the ground surface. Also, the upper portion of the underlying bedrock was logged as
highly weathered and sheared to a depth of about 23 feet. Based on these findings, soil, or soil -like
conditions are likely to be encountered from the entry point to about Station 0+50.
Where the HDD penetrates landslide deposits, cobble and boulders may be encountered, but are not
expected to be as frequent as observed in the Woodpile Landslide area. Otherwise, these materials are
expected to consist primarily of clays and silts of medium to very stiff consistency.
Bedrock encountered in the Columbine HDD will be of the Wasatch Formation. These rocks are
composed of massive mudstones, with layers of fine to coarse-grained conglomerate sandstone which
can range up to 50 feet in thickness. Some of the conglomerate sandstone was encountered near the
bottom of borehole CS -2, and was found to be much harder than overlying materials. This likely
represents the more resistant sandstone units which occur in the Wasatch Formation and are reported to
range up to 50 feet in thickness. Test sample results indicate the sandstones and siltstones from the
Wasatch Formation to have rock strength from Very Weak to Weak (ISRM classification). However, the
borehole logs indicate that some layers of harder rock were also encountered.
2.3 McAndrews Lake HDD
Figure 3 shows the revised proposed HDD alignment for the McAndrews Lake area. This area also has
landslides. No drilling investigation was performed in this area during the 2011 studies. Geotechnical
information for this HDD is being taken from six previous borings done close to the proposed alignment in
the late 1990's, to support design of the Brown Line HDD which is already in place in this same vicinity.
These borings were completed by Terracon Consultants Western, of Salt Lake City, Utah, and are
presented in drawings relevant to construction of the Brown Line HDD. These drawings are included in
Golder's December 2011 report. The drawings include rock strength test data, as well as lithologic data
for the soil and rock types encountered.
The proposed HDD is shown to lie deep within the bedrock below McAndrews Lake, and well below the
depth of landslide deposits over most of its length. The information presented in the Brown Line HDD
s:\enterprise\2011\2011 columbinesprings\wept supplemental report 2-2012\stamped final report 3-2012\wep2 supplemental.docx
�Golder
® Associates
Ricky Bates March 16, 2012
Enterprise Products Co./Mid-America Pipeline 4 113-91752
drawings does not specify the geologic formations encountered by Terracon in these borings. However,
based on the mapping by Johnson (1985) we interpret that the south portion of the proposed HDD will be
drilled in rocks of the Mesa Verde Formation, and the north portion will be drilled in rocks of the Wasatch
Formation.
Rocks of the Mesa Verde Formation consist of fine-grained sandstone, silty shale, carbonaceous shale,
and coal. Rocks of the Wasatch Formation are most often characterized as massive mudstones, with
layers of fine to coarse-grained conglomerate sandstone which can range up to 50 feet in thickness.
Based on the information shown on the Brown Line drawings, borehole B-3 encountered conglomerate
sandstone layers up to about 15 feet in thickness. The Johnson mapping (1985) shows a fault crossing
the valley just upstream of the McAndrews Lake dam, thus accounting for the offset in these formations.
Although the fault itself is not considered to be a likely concern for drilling the HDD, if continuous and of
permeable character, it could have the potential to act as a conduit for groundwater. Depending on the
relative heads of fluid in the HDD bore, the surrounding formation, and in the lake, it could cause either
losses of drill fluid, or inflow of groundwater as the bore crosses the fault, and these factors should be
considered in the design of the boring plan and mud mix. However, previous experience with drilling the
HDD close to this alignment in the late 1990's does not indicate any inflows or loss of fluid associated with
this fault. This suggests that provided the proposed HDD is drilled at a similar or greater depth, and
similar mud management practices are implemented, the fault should not act as a conduit"
Although most of the proposed HDD is anticipated to be within bedrock, valley bottom alluvial deposits,
possibly with some landslide deposits will be encountered at the entry and exit points of the HDD. At the
entry point (south end), the findings of borehole B-1 suggest that the HDD may encounter valley bottom
deposits of clay, sand, and gravel from Station 0+00 to about 3+00. However, the entry point is shown to
be on the mapped boundary of a recently -active landslide. Although the entry point is on the valley floor,
this location has the potential to be affected by future movements related to the active slide on the slope
immediately to the east. We recommend that visual monitoring of the area around and adjacent to the
pipeline alignment, and the toe and lower portion of the slide (identified in previous studies and on Figure
3 as the "Hairpin Slide") be conducted on an annual basis, and that strain gages be placed on the pipe
near the entry location to monitor for any effects on the pipe from future potential ground movements.
It is usually more expedient to install strain gages at the time of construction. However, for the near term,
it may be acceptable to watch the existing inclinometer and perform annual visual inspection in this area,
which is done as part of the monitoring program already ongoing for the other Enterprise pipelines
through this area. However, if continued movement is seen in the existing inclinometers in the Hairpin
Slide, which is upslope of the approximate entry point, or visual observations indicate possible ground
movements, we would then strongly urge the placement of appropriate instrumentation on or adjacent to
the WEP2 pipe.
At the north end (exit point) of the HDD valley bottom deposits are likely to be encountered. The borehole
B-5 is located to the east of the proposed exit point, and is on the shoulder of the valley rather than in the
valley bottom. B-5 encountered bedrock of the Wasatch Formation with no reported overburden, and
thus does not represent the conditions likely to be found in the valley floor. Boring B-4, approximately 650
feet south of the proposed HDD exit point, encountered clay soils, which likely represent valley fill
deposits and/or underlying highly weathered bedrock, to a depth of about 54 feet. Based on these
findings, we anticipate that the HDD bore could encounter soils from the exit point at Station 31+00 to as
far as Station 27+00 (approximate estimate). Although soils in this area could contain some gravel
zones, significant boulders are not likely, and the predominant soils are likely to be clays and silts.
3.0 CONVENTIONAL TRENCHING ALTERNATIVE FOR PIPELINE THROUGH
LANDSLIDE ZONES
There is a possibility that it may be preferable to use conventional trenching in place of HDD construction
of the pipeline through one or more of the landslide zones. The Woodpile Landslide has been discussed
as the most likely area to consider conventional trench construction. It is unlikely that the McAndrews
Lake area would be considered for conventional construction, but if this is needed, it would be necessary
s:\enterprise\2011\2011 columbinesprings\wept supplemental report 2-2012\stamped final report 3-2012\wep2 supplemental.docx
�Golder
® Associates
Ricky Bates March 16, 2012
Enterprise Products Co./Mid-America Pipeline 5 113-91752
to revise the proposed alignment. If conventional construction is selected for any of the landslide zones,
we recommend the following measures be used:
• The pipeline should be buried at/near the minimum depth required by the DOT. This
allows for easier excavation in the event strain relief is needed;
• The length of the open excavation during construction should be limited to about 50 feet,
or no longer than needed to place a single "joint" of pipe;
• Select backfill should be used around the pipe through areas shown within the extents of
recently or historically active landslide movements (refer to Golder 2011 report). Such
select backfill would need to be imported to the site, and should consist of free -draining
sand and/or gravel, such as a pit -run product with less than 15% fines (15% or less of
material by weight passing the #200 sieve);
• The pipe trench should include trench breakers to inhibit transport of groundwater along
the trench. Each trench breaker needs to have provision for free drainage of water
collected within the trench. Usually this is done by means of perforated drain pipe
running parallel along the base of the pipe, terminating at each trench breaker and
"daylighting" to drain at a safe location downslope. Golder can provide detail drawings
for these, should conventional construction be needed;
• Reclamation of the site over the trench should include special care with control and
diversion of surface water to avoid ponding and minimize infiltration. This applies not
only to the area immediately over the trench, but also to adjacent areas, to minimize the
potential for surface water to infiltrate into the landslide mass;
• A Monitoring Plan should be established for all segments of the pipeline that are within
the extents of recently or historically active landslide movements (refer to Golder 2011
report). We recommend that strain gages be placed on the pipe for monitoring.
Depending on the situation, inclinometers may also be recommended. Inclinometers are
already in place (one each) at the Woodpile and Columbine Landslide areas, and will be
extremely helpful to the monitoring program if they can be protected and preserved
during construction. Annual surface inspection of the alignment should also be done, to
check for apparent changes in landslide conditions within and adjacent to the right-of-
way. We anticipate that such a monitoring plan would be similar to, and be conducted in
coordination with the current monitoring program for Enterprise's existing pipelines on the
north side of Baxter Pass; and
• A Mitigation Plan should be developed, addressing procedures, equipment and materials
needed to provide strain relief, and/or repairs to the pipe in the event of landslide
disturbance. A remote and immediate means of shutting down flows and isolating the
damaged section in close proximity to Baxter Pass should be included in the pipeline
system.
4.0 SUMMARY OF RECOMMENDATIONS
As described above, we recommend mitigation measures for two locations at endpoints of the proposed
HDDs. There are also recommendations for any portions of the pipeline to be placed by conventional
construction through any of the identified recently or historically active landslide areas. These
recommendations are as follows:
1) Columbine Landslide Complex, Exit Point (south end): Great care needs to be taken to avoid re-
activating or expanding a small slump area in the existing right-of-way cut slope. We recommend
that the slope in this area be laid back to a more stable configuration prior to beginning work on
the HDD in this area.
2) McAndrews Lake, Entry Point (south end): In the longer term, it is likely that installation of strain
gages will be recommended for placement on the pipe near the entry location, to monitor for any
s:\enterprise\2011\2011 columbinesprings\wept supplemental report 2-2012\stamped final report 3-2012\wep2 supplemental.docx
Golder
Associates
Ricky Bates March 16, 2012
Enterprise Products Co./Mid-America Pipeline 6 113-91752
effects on the pipe from future potential ground movements. It is usually more expedient to install
gages at the time of construction. However, for the near term, it may be acceptable to monitor
the existing inclinometers and perform annual visual inspection, which is done as part of the
monitoring program already ongoing for the other Enterprise pipelines through this area. If
continued movement is observed in the existing inclinometers in the Hairpin Slide, which are
upslope of the HDD entry point, or visual observations indicate possible ground movements, we
would then recommend the placement of appropriate instrumentation on or adjacent to the WEP2
pipe.
3) If conventional trench construction is to be used for any of the pipeline segments through those
areas identified as recently or historically active, specific measures for both construction and
operation need to be followed, as described in more detail above in Section 3.0, including:
• Shallow burial;
• Limited length of open excavations;
• Use of select backfill;
• Appropriate treatments for ground water and surface water drainage;
• Implementation of a monitoring plan; and
• Development of an emergency mitigation plan.
We trust the information presented above meets your immediate needs. We appreciate the opportunity to
continue assisting you with the WEP2 project, and are prepared to furnish additional assistance as
needed. Please don't hesitate to call us if you have any questions.
Sincerely,
GOLDER ASSOCIATES INC.
-004-6/
Nancy Dessenberger Rhonda Knupp
Senior Geologist
Senior Consultant
•
•
Graeme Major, PE
Principal Geotechnical Engineer
s:\enterprise1201112011columbinespringskwep2 supplemental report 2.20121stamped final report 3-20121wep2 supplemenlal.docx
' Golder
Associates
Ricky Bates March 16, 2012
Enterprise Products Co./Mid-America Pipeline 7 113-91752
Attachments: Figures 1-3
Distribution: 1 Copy — Ricky Bates, Enterprise, Houston
1 Copy — Jill Petersen, Enterprise, Hobbs
1 Copy — Jerry Simmons, Enterprise, Fruita
1 Copy — Brad Kiser, Enterprise, Rock Springs
1 Copy — Henrick Sarkissian, Rooney Engineering, Centennial
1 Copy — Graeme Major, Golder Associates, Reno
1 Copy — Golder Associates, Reno
ND/cal
12030.doc
s:\enterprise\2011\2011 columbinesprings\wept supplemental report 2-2012\stamped final report 3-2012\wep2 supplemental.docx
�Golder
® Associates
FIGURES
.
f IMP '.
0. OFCRErk�
0.
ti
it UPPER LIMIT
' OF SLIDE TERRAIN
i H.T
.-tel tY ,-_a �
STRAIN GAGE
ARRAY
s pr�
I3 1MIUl iI J:
Id[ Qat�4�/fVl
0,4
f'ZRL9P '.
0
+
0
GAS
L t w...
r n R.
GAS
ar, e7ro.
/_1-i9�UZa7�17!]I IJq.1�171�P1I91
Aar mitr
O
GASB
PJ'PER IMIT
}7i.,,1■ TERRAIN
GAS
GAS
- 411_ c
GAS,'
I. kMe q,
6w'I7D.Y
II OLeii1c141 ,
la VaIUI:YY '11
17.���Y:YA3
NTNY
eD
1.11ATAT[y4• 110 151'= -,•
r- - 'FR
-TF
POINT OF EXIT
r - STA. 3+36
• 39'35 59392'
a i7 108; 7.503 x�
4
OLD BLOCK TOP
__—G AS
—
ABA ONED PIPELINE / WEP II SURVEY CENTERLINE
A NG` l KG
�r•
1 f
s V
,"
,;,�aac • RIGHT -0
.r
11159a:O1LIIl1
itassiciustuttio
4
ti
•
okm -t
4
.,I qac
411.
11111 .401.4
4 4
9
•4.0
r � )
TOTAL HORIZONTAL DISTANCE = 1336 FT
TOTAL PIPE LENGTH = 1365.1 FT
HDD PROFILE VIEW
D -017F SCAI F
VERTICAL : 1 "= 100'
HORIZONTAL : 1"=100'
PIPE ELEV. 7825'
BORE I OG WP -1
7892' —
Lii99AY brown -gray,
LANDSLIDE DEPOSIT)
8100 ---
8050 8050
8000
7950 - POINT OF ENTRY
- STA. 0+00 I
ELEV 7820'
863.5'— �C 0v 7900
io`eaii, C3XYEY SILI,RCtric)
a�:%sed of extremely weathered
Besa$—'ora eraYY thered CLAYEY 7850
1SILTSTONE .4th ,ome sand
ExtremeIvNE weak, Light gray,
SILTSTO
7852'—Li4ht mm vv Very weak SW�dW. SILTSTONE, with trace gravels
7848.7 — Oxitlized, Red -brown, Very,weok,
7847.7`p
Mq a sible sheemelt' warp0lane
a't5 wtlhgroeM nd
osa
51Li51UNE Weak, 5W,
78422— Oxidized, Brawn Extremely weak,
7840:—MW, s dy, Very ONE
]839.5—eyyL4f97*' Very weak, SW -MW,
]838.4'— s' y
R'Itd'CLAYSTONE Weak, SW -MW,
oo vv
cloyey 1087ONE'
7830,5—Oxidized, Reddish-brown,Weak,
782825, clayey 31LT/TONE
I82fi 5 Oxidized, 6.474h-
',SW, aoGyeyvSLTST
cIcyey 1L I7T0NE
7824.5—
n, Weak,
T
7800 —
7750 —
3-
T
3-
E
LANDSLIDE AREA
EXISTING GROUND PROFILE
42.0' TANGENT LENGT
— 8100
POINT
3EXIT
STA.
+— 8050
ELEV 7995'
�6e
L
152.9' TANGENT LENGTH
POINT OF CURVE
STA. 1+51
7700
7650
7600
70.2' CURVE LENGTH
1600' RADIUS
POINIT OF TANGENT
STA.18+15
8000
7950
FLOWLINE OF CREEK—L
PROFILE- — — — 7900
7850
- 7800
- 7750
— 7700
- 7650
I„„I„„I I I„„ ,„, ' ' 7600
—1+00 0+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+00 10+00 11+00 12+00 13+00 14+00 15+00
PROFILE
(EXISTING GROUND ALONG DRILL PATH)
NOTES
1. ALL COORDINATES SHOWN ARE GEOGRAPHIC COORDINATES, NAD83 DATUM. ALL
ELEVATIONS ARE BASED ON USGS TOPOGRAPHIC DEM - 10 METER ACCURACY.
2. STATIONING IS BASED ON HORIZONTAL DISTANCES.
3. ROONEY ENGINEERING, INC. AND ENTERPRISE PRODUCTS ARE NOT RESPONSIBLE
FOR LOCATION OF FOREIGN UTILITIES SHOWN IN PLOT PLAN OR PROFILE. THE
INFORMATION SHOWN HEREON IS FURNISHED WITHOUT LIABILITY ON THE PART
OF ROONEY ENGINEERING, INC. AND ENTERPRISE PRODUCTS, FOR ANY DAMAGES
RESULTING FROM ERRORS OR OMISSIONS THEREIN.
4. CONTRACTOR IS RESPONSIBLE FOR LOCATING ALL UTILITIES.
5. CONTACT ONE CALL COLORADO AT 811, 3 DAYS PRIOR TO DIGGING.
MATERIAL SUMMARY
REFERENCE DRAWINGS
ITEM
DESCRIPTION QTY.
DWG
DESCRIPTION
CROSSING I FGFND
NOTES
REVISED DRILL LENGTH & PROFILE
D
ADDED BORE LOG INFORMATION
TL
KR
11-04-11
10-20-11
C
RECONFIGURED HDD ENTRY 8 EXIT LOCATIONS
KR
10-06-11
B
ADDED UTILITY INFORMATION
KR
09-15-11
A
FOR REVIEW PURPOSES ONLY
KR
08-05-11
REV
DESCRIPTION
BY
DATE
MM
ZB
ZB
ZB
ZB
APP.
ENGINEERING RECORD
DRAWN
CHECKED
CLIENT
PROJECT MGMT.
PROCESS
MECHANICAL
PIPING
STRUCTURAL
ELECTRICAL
EEnterprise Products
in'Rooney Engineering, Inc.
12201 E. Arapahoe Road, Suite C-10
Centennial, Colorado 80112
(303) 792-5911
ENTERPRISE PRODUCTS PARTNERS, L.P.
PROPOSED HDD
WOODPILE LOCATION
WESTERN EXPANSION PROJECT PHASE II
GARFIELD COUNTY, COLORADO
SCALE: NO SCALE) DRAWING: 02757-PIPL-2003 I1,1E01 E
RORF I (1Q CS -3
7636'-
7628' -
$C$ANUrcCLAY Firm,
(LANDSDDE 6EPOSIT)
Compact, Finn, Brawn,
SILTY CLAY, moist
(LANOSDDE DEPOSIT)
7618'-
00417001. tiff, Brown,
S 1
(LANDSLIDE, DEPOSIT)
7608'-
Verwvpsliff,t Reddenbrown,
SILTY CLAY, moist
7598'-
Hi9hIvv 179,0 9'114.
GLAYSTONE
7563: -an bW,tyreTDSrN6
7586'- ltyySXNDSONE
PIPE ELEV.-7575'
Gray, Very weak MW -VW,
clayay SILTSTONL
7559' -
bray, Weak, SW1,I8,
only SILTSTON
7549'-
N'S SLIQ'01+
FLOWL,k,E OF CREEK-\
•
11X911:1.1:40&
TEST BORE CS -2
• ELEV: 7563'
- LAT 39'36.21462'N
LONG. 108'57.53(70'W
-TEST BORF CS -1
ELEV.7435
LAT. 39 36 35873'N
LONG. 108'57 65312W
7 er'4 //'
o*1. o
o
+ 0,1
♦ O
�I 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
COLUMBINE
LANDSLIDE
COMPLEX
11LI:1101=
IX.IN
[9005)141:: 4.121K 111
lala.Air51
C111NRH*N611@Ce
'jLI �1.'. fYBI
I I T 4.,?III
courcnianom
innincung .
IGrY:UY4I*EL86E11� • ? - -
141W/IRi:1..1
GA
SMALL
SHALLOW
SUM
411: (1)21.147014.791:1 17A477011•111 494•414,
e
)X_6111 M:1.
RORF I OG CS -1
7435 -
SANS 9LT rJry.
7427-
0 MY C AL,Dmoi °rown,
7422- CC
946(7 CLAY, moist° tan,
7417-
'4'14
417 -
Hgh14 weathered Brown,
Cly9yt aLTTONL bedrock,
7412-w,
Highly weathered 4rown,
Clayey, SILTSTONL 540,°06
7407 W,-,eyLLEnxsemeEyv
weak,
7404-10.1W-40(LAYS90
weak,
74015 -Dark pey Exbrmely weak,
7400- MW -VW, CL 01447
7399- SANDSWWTON'EV
PIPE ELEV.-7379'
RORF I OG CR -2
7563-
Compact, 0wf Brbwn,e
SILTY et tr th
sPu ds�v& trace grav4Is,
53 5 (ILANIIAL T DEPOSIT)
053.2 = Ldorse, Orange, CLAYEY SAND,
04417041. s0i( Brown,
SILTY CLAY, with 04040
7750 -
7700 -
(1-ANDSLIDE DEPOSIT) 7650 -
7544 Compost. Very stiff. Brown with
mottled orange, SILTY CLAY with
oist
]539-(LANDSLIDds,E DEmPOSIT)
Dense,. very se,f, .TY CLAY 7600 -
mottled ode.gm'o SILTY with
337]_ (LANDSLIDE DEPOSIT) -
753']-g9Ltt SAN0, 8049. 411 e„, B°H•7050 -
SANDY CA4 droryynge,
7529-(LANDSDDLE EEPOSIT)
Compact, stiff, Brown, 7500 -
(LAND LA, POV
(LANDSLIDE DEPOSIT)
Compac1. stiff, SILTY SAND,
,tn trnv44 nvy, a1i n �y 41404E
PLANDSLIDE9DEP0S0 ed 64'4046 7450 -
7519 -
7524-
Compact,
524-
Compact, stiff, SILTY SAND
55 (LANDSLIDES DLPOSIT)efed 4404046 7400
]DM6.5 1F'R, yco6nrgolmeate SAN(6STONE 7350 -
7505.7 Gray hrown Very weak Unform,
IFR, SANDSTONE
7504.7 R6AD1 Very weak, Uniform, m,
750'IOora s9oenrEWR, MagTONEm9 -
7300
7484 -
100
Cray Medium Strang, FR,
:ands SILTSTONE
B'Ity S`AND$TONE week, FR,
PIPE ELEV.-7473.37474
Gray -brown, very weak,
7471- FR, SIrolme40Wle SANDSTONE
FR.7CO GLOd0ERA0Eeemenled,
7467.7 -
POINT OF ENTRY
STA. 0000
ELEV 7395'.
223.4' CURVE LENGTH
1600' RADIUS
ELEV 7435'
BORE CS -1
DEPTH: 36'
ELEV 73991.1
EXISTING GROUND PROFILE
POINT OF TANGENT
STA. 2+42
FLOWLINE OF CREEK
PROFILE - - -
335.1' CURVE LENGTH. _.
1600' RADIUS.-- --.-
-POINT OF.CURVE (VERTICAL)
STA. 0+20
20' TANGENT LENGTH
I I '
0+00 1+00
2+00
TOTAL HORIZONTAL DISTANCE = 2299FT
TOTAL PIPE LENGTH = 2334.2 FT
COLORADO 811
ELEV 7377'
469.1' TANGENT LENGTH
3+00 4+00 5+00
6+00 7+00
`POINT OF CURVE (VERTICAL)
STA. 7+12
,I
8+00 9+00 10+00
-I I
ACTIVE LANDSLIDE AREA
COLUMBINE LANDSLIDE COMPLEX
ELEV 7563' L L
BORE CS -2
DEPTH: 95.3'
- ELEV 7467.7
POINT OF TANGENT
STA. 10+44
11+00 12+00
HDD PROFILE VIEW
D-SI7F SCAT F
VERTICAL : 1"= 100'
HORIZONTAL : 1 "=100'
13+00
1
ELEV 7636'
BORE CS -3--►
DEPTH: 87'
EV 7549'
1506.7 TANGENT LENGTH
14+00 15+00 16+00 17+00
NOTES 1'
FLOWLINE OF CREEK
PROFILE
18+00
19+00
20+00
ALL COORDINATES SHOWN ARE GEOGRAPHIC COORDINATES, NAD83 DATUM. ALL
ELEVATIONS ARE BASED ON USGS TOPOGRAPHIC DEM - 10 METER ACCURACY.
2. STATIONING IS BASED ON HORIZONTAL DISTANCES.
3. ROONEY ENGINEERING, FOR LOCATION OF FOREIGN ANDNC. ENTERPRISEPRODUCTS RESPONSIBLE
IGN UTILITIESSHOWN INPLOT PLAN OR PROFILE. THE
INFORMATION SHOWN HEREON IS FURNISHED WITHOUT LIABILITY ON THE PART
OF ROONEY ENGINEERING, INC. AND ENTERPRISE PRODUCTS, FOR ANY DAMAGES
RESULTING FROM ERRORS OR OMISSIONS THEREIN.
4. CONTRACTOR 15 RESPONSIBLE FOR LOCATING ALL UTILITIES.
5. CONTACT ONE CALL COLORADO AT 811, 3 DAYS PRIOR TO DIGGING.
21+00
22+00
23+00
POINT
25 OF+18 EXIT
S.
ELEV 7725'
24+00
25+00
'
7750
12'
7700
- 7650
- 7600
- 7550
- 7500
- - 7450
- 7400
- 7350
7300
26+00
MATERIAL SUMMARY
REFERENCE DRAWINGS
ITEM
DESCRIPTION
QTY.
DWG
DESCRIPTION
CROSSING I FGFND
NOTES
C
REVISED DRILL PATH & PROFILE
TL
-03-1
MM
B
ADDED BORE LOG INFORMATION
KR
0-20-1
ZB
A
FOR REVIEW PURPOSES ONLY
KR
0-06-
ZB
REV
DESCRIPTION
BY
DATE
APP.
ENGINEERING RECORD
DRAWN
CHECKED
CLIENT
PROJECT MGMT.
PROCESS
MECHANICAL
PIPING
STRUCTURAL
ELECTRICAL
EEnterprise Products
Rooney Englapahoneering, Inc.
e Road, Suite C-10
�j,12201 E. AA
Centennial, Colorado 80112
(303) 792-5911
ENTERPRISE PRODUCTS PARTNERS, L.P.
PROPOSED HDD
COLUMBINE SPRINGS LOCATION
OPTION 3
WESTERN EXPANSION PROJECT PHASE II
GARFIELD COUNTY, COLORADO
SCALE: NO SCALE 1 DRAWING: 02757-PIPL-2002 )REV: C
UI477: IIIU8115111:44119
TEMPORARY
-WORKSPACE _ ____
-• '1OI-T FEXIT - -
1C1Yf:k"' ' .4'N
�LIHiGF:Yi.Y:II.Y:I1FkL�W - -
• MI•124J1.9'1
WPM KIM
.1111 i.i5:IId.YAIIW
•UNIND8188: 88iC➢IPI
PLAN & P-IOTd`VIEW
TOTAL HORIZONTAL DISTANCE = 3100 FT
TOTAL PIPE LENGTH = 3114.7 FT
HDD PROFILE VIEW
I1-SI7F SCAI F
VERTICAL : V= 50'
HORIZONTAL : 1,200'
811
NOTES
1 COORDINATES
GEOGRAPHIC O
ARE BASED ON USGS TOPOGRAPHIC DEM - 10 METER ACCURACY. ELEVATIONS
2. STATIONING IS BASED ON HORIZONTAL DISTANCES.
3. ROONEY ENGINEERING, INC. AND ENTERPRISE PRODUCTS ARE NOT RESPONSIBLE
FOR LOCATION OF FOREIGN UTILITIES SHOWN IN PLOT PLAN OR PROFILE. THE
INFORMATION SHOWN HEREON IS FURNISHED WITHOUT LIABILITY ON THE PART
OF ROONEY ENGINEERING, INC. AND ENTERPRISE PRODUCTS, FOR ANY DAMAGES
RESULTING FROM ERRORS OR OMISSIONS THEREIN.
4. CONTRACTOR IS RESPONSIBLE FOR LOCATING ALL UTILITIES.
5. CONTACT ONE CALL COLORADO AT 811, 3 DAYS PRIOR TO DIGGING.
7200
7160
7120
7080
7040
SEE NOTE 6
POINT OF EXIT
ELEV 6995.86'
CLAYSTONE
7000
SILTSTONE/SANDSTO E
SILTSTONE/ LAY TONE_.
CLAY
ELEV:
7000' SILTSTONE/CLAYSTONE
— SANDSTONE
145.8' TANGENT LENGTH SILTSTONE/CLAYSTONE
223.4' CURVE LENGTH SANDSTONE
600' RADIUS
SILTSTONE
SANDSTONE SILTSTONE/CLAYSTONE
SANDSTONE
6960
z
6920 O
690 I l { I I I I I I I I I I I I I I I I I I I I I I I I I 69
33+00 32+00 31+00 30+00 29+00 28+00 27+00 26+00 25+00 24+00 23+00 22+00 21+00 20+00 19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00 3+00 2+00 1+00 0+00 -1+00 -2+00
CLAY
McANDREWS LAKE
EDGE OF WATER
SANDSTONE ----GRAVEL/COBBLES
GRAVEITOSI LES SANDSTONE
GRAVEL/COBBLES
CONGLOMERATE
LAKE BOTTOM
INTERBEDDED LAYERS
OF CLAYSTONE,
SANDSTONE,
SILTSTONE, &
SILTSTONE/CLAYSTONE
INTERBEDDED LAYERS OF SILTSTONE,
CLAYSTONE & SANDSTONE
CONGLOMERATE
INTERBEDDED LAYERS OF SILTSTONE,
CLAYSTONE & SANDSTONE
1723.8' TANGENT LENGTH
cD
0_
m
SEE NOTE 6
POINT OF ENTRY
GROUND PROFILE ELEV 7113.25'
ELEV:7120'
CLAY
SAND/CLAY
SAND/GRASVELAND
-
742.5' TANGENT LENGTH
279.2' CURVE LENGTH
1600' RADIUS
INTERBEDDED LAYERS OF
CLAYSTONE, SANDSTONE,
SILTSTONE, 8 SILTSTONE/CLAYSTONE
7200
7160
6960
6920
PROFILE VIEW
DESCRIPTION
QTY.
DWG
DESCRIPTION
CROSSING I FGFND
NOTES
UPDATED ROW
KM
mraa�
®
®
09-26-
DESCRIPTION
09-06
DATE
MM
ZB
ZB
ZB
ZB
APP
ENGINEERING RECORD
DRAWN
131
CHECKED
CLIENT
PROJECT MGMT.
PROCESS
MECHANICAL
PIPING
STRUCTURAL
ELECTRICAL
&C
EEnterprise Products
Rooney Englapahoneering, Inc.
e Road, Suite C-10
�j,12201 E. AA
Centennial, Colorado 80112
(303) 792-5911
ENTERPRISE PRODUCTS PARTNERS, L.P.
PROPOSED HDD
McANDREWS LAKE LOCATION
WESTERN EXPANSION PROJECT PHASE II
GARFIELD COUNTY, COLORADO
SCALE: NO SCALE
DRAWING: 02797-PIPL-2001
MEI