02-MAPL-WEP-II-ConstructionSchedule-Garco
rt7tiAi VAL kah CONSiR MaNa eM ENT, E 1038 Canary Rd 323 R111E, CO 81650 Mid-America Pipeline Company, LLC Western Expansion Project II- Development Plan Review for Right -of -Way Application Construction Schedule -Garfield County 1. Mobilization- 2 weeks 2. Locate Lines- 1 week 3. Clear & Grade right-of-way- 2 weeks 4. Ditch- 2 weeks 5. String Pipe- 1 week 6. Horizontal Directional Drilling- 2.5 weeks 7. Bend Pipe- 1 week 8. Lay & Weld pipe- 2 weeks 9. Coat field joints- 1 week 10. Lower in pipe- 2 weeks 11. Tie-ins- 1 week 12. Pad & Backfill- 3 weeks 13. Test, Dewater and Dry Pipeline- 5 weeks 14. Cleanup- 1 week 15. Demobilize- 2 weeks Estimated length of work: approximately 6 months. Revegetation and reclamation efforts will be conducted as weather conditions allow. Page 1 of 1