Loading...
HomeMy WebLinkAbout1.0 Application IncompleteRECEIVED NOV 0 3 1998 The following are revised sections of the Garfield County Special Use Permit Application for the Yankee Gulch Sodium Minerals Project Product Solution and Water Return Pipelines. Additions to the application are presented in bold and underlined text. After review and approval of Garfield County, these revised sections will be incorporated into the application for formal submittal to Garfield County. From pages 5 and 6: 1.4 Hours of Operation Construction of the proposed pipelines will occur only during the daylight hours, from approximately dawn to approximately dusk over a period of four to five months along the proposed pipeline corridor. After construction_ is completed, the proposed project pipelines will operate 24 hours per day, 365 days per year, allowing for periodic maintenance and repair. 1.5 Site Access and Anticipated Vehicle Traffic American Soda is proposing no new access road construction. Access for both construction and operations will be via existing roads or on the ROW itself. Section 3.1.4 of the POD, "Construction Access Roads," identifies and describes projected access roads to the pipeline corridor during construction. Access to the proposed pipeline corridor in Garfield County will be provided primarily by County Road 215 (Parachute Creek Road), which follows Parachute Creek north from the Parachute Site. A private road provides access from the north end of County Road 215 to the base of Davis Point. Access to the northern end of the Garfield County portion of the pipeline corridor will be provided via BLM and private roads off Rio Blanco County Road 5. Commuter traffic to and from the pipeline construction project will occur primarily early in the morning at the beginning of the day and in the late afternoon at the end of the working day. In total, approximately 30 to 55 commuter round trips are anticipated per day along the Garfield County portion of the pipeline corridor. This number is based on the assumption that pipeline construction workers will carpool to the working area at the rate of two workers per passenger vehicle. It is important to note that, while the peak number of trips is estimated to be about 55 trips per day for the peak construction month, the average number of commuter round trips will be about 30 per day over the majority of the construction period. In addition, approximately 15 to 20 truck round trips per day are estimated for delivery of pipe and other equipment and supplies to the working areas along the pipeline corridor. These truck trips will most likely originate from the Parachute Site. Virtually all of these trips would utilize trucks weighing less than 80.000 pounds m aximum gross vehicle weight (20,000 pounds per axle). In accordance with Garfield County requirements. American Soda would obtain the necessary Special Transport Permits for any oversized loads, if any such trips were necessary. While requirements for access to the pipeline corridor after being placed into service are anticipated to be minimal, many of the same roads used for construction will continue to be utilized for routine periodic operations, inspections, and maintenance activities. During the operations phase of the project, the only vehicle traffic anticipated for the pipelines would be associated with infrequent groundinspections by American Soda personnel utilizing pick-up trucks or off-road vehicles. These ground inspections would occur approximately twice annually. Otherwise, there would be virtually no vehicle traffic associated with the pipelines once construction is completed. From pages 8 through 9: 7.0 IMPACT STATEMENT In accordance with Sections 5.03.07 and 5.03.08 of the Garfield County Land Use Codes, this Impact Statement is filed with Garfield County for the purpose of ... .... Copies of the Draft EIS and Final EIS were similarly provided to Garfield County for review in January and July 1999, respectively. Based on current pipeline design and installation information, American Soda has developed a pipeline construction workforce schedule that identifies likely manpower requirements on a month -by -month basis. Table 1 identifies this workforce. As described previously in Section 1.3.3, pipeline construction activities are anticipated to commence as early as January 2000 in the Parachute Valley in Garfield County, with completion of the entire pipeline expected no later than November 2000, subject to securing all requisite permits and easements. Given the typically difficult and somewhat unpredictable winter and spring field conditions in the region, full-scale construction activity would likely begin in late spring 2000, as depicted in Table 1. DRAFT Table 1 Schedule of Pipeline Construction Workforce. Pipeline March April Mev 2000 Img 2000 jinx 2000 i Au u t 5_kt. Cmc . 2000 Construction 2000 2400 240.4 2�i QQ Workforce Rio Blanco 1.1 41 11 2a 126 §3 E 12 County_ Garfield SQ 60 110 72 64 2Q 12 County Total Rio i;z 1QQ 1Q5 15.1 12.6. 122 fz n Blanco and Garfield Counties From pages 11 through 12: 5.03.07 INDUSTRIAL OPERATIONS D. Truck and Automobile Traffic Access to the proposed pipeline corridor in Garfield County is provided primarily by Garfield County Road 215 (Parachute Creek Road), which follows Parachute Creek north from the Parachute Site. A private road provides access from the north end of County Road 215 to the base of Davis Point. Access to the northern end of the Garfield County portion of the pipeline corridor will be gained via BLM and private roads off Rio Blanco County Road 5. Commuter traffic to and from the pipeline construction project will occur primarily early in the morning at the beginning of the day and in the late afternoon at the end of the working day. In total, approximately 30 to 55 commuter round trips are anticipated per day along the Garfield County portion of the pipeline corridor. This number is based on the assumption that pipeline construction workers will carpool to the working area at the rate of two workers per passenger vehicle. It is important to note that. while the peak number of trips is estimated to be about 55 round trips per day for the peak construction month, the average number of commuter round trips will be about 30 per day over the majority of the construction period. In addition. approximately 15 to 20 truck round trips per day are estimated for delivery of pipe and other equipment and supplies to the working areas along the pipeline corridor. These truck trips will most likely originate from the Parachute._ Site. During the operations phase of the project, the only vehicle traffic anticipated for the pipelines would be associated with infrequent ground inspections by American Soda personnel utilizing pick-up trucks or off-road vehicles. These ground inspections would occur approximately twice annually. Otherwise, there would be virtually no vehicle traffic associated with the pipelines once construction is completed. From pages 13 through 14: 5.03.08 INDUSTRIAL PERFORMANCE STANDARDS 1. Volume of Sound Construction of the proposed project pipeline will generate noise for a brief period of time at any given location along the corridor. After construction of the proposed project pipeline is completed, there will be no perceptible sound from the operating pipeline. 2. Vibration Generated There will be no perceptible vibrations from the construction or operation of the project pipelines. 3. Emissions Qf Smoke and Particulate Matter During construction, there will be emissions of diesel exhaust from heavy equipment and dust to some extent from earthmoving activities. These emissions will occur along the pipeline corridor, which is located in a sparsely populated portion of Garfield County. Minimal or no impacts associated with smoke and dust emissions are anticipated for residential areas of the county, such as the Town of Parachute, during construction. There will be no emission of smoke, particulate matter, or any other form of air pollutant from the operating pipeline. Pumps associated with the pipeline will be located at the Piceance and Parachute Sites and will be electrically driven. 4. Emission of Heat, Glare, Radiation, and Fumes Aside from diesel exhaust from heavy equipment during constructions there will be no generation of heat, glare, radiation, or fumes from the project pipeline. 111111111111111111111111111111111 III11I 1111111111111111 683596 10/04/2005 09 31A 61732 P649 N AL5OORF 1 of 4 R 0.00 0 0.00 GARFIELD COUNTY CO SATISFACTION OF PERMIT AND RELEASE OF SECURITY WHEREAS, American Soda, LLP ,obtained a Special Use permit from the Garfield County Board of County Commissioners authorizing certain uses on their property subject to conditions of approval contained in Resolution No. 2000-D05; and WHEREAS, as a condition of issuance of the permit, American Soda, LLP, provided security for revegetation to Garfield County in the form of a bond number 6239756. NOW, THEREFORE, at the request of American Soda, LLP, Garfield County, through the Board of County Commissioners, states as follows: 1. Garfield County acknowledges that the terms and conditions of Resolution No. 2000-005 for a Special Use Permit issued to American Soda, LLP, requiring the revegetation of portions of the property are completely fulfilled. 2. There exists no potential claims against Garfield County and SAFECO Insurance Company of America, under the terms and conditions of bond number 6239756 for any of the activities required of American Soda, LLP, under the terms of the permit referenced above. 3. Garfield County, through the Board of County Commissioners, hereby releases SAFECO Insurance Company of America from performance of its obligations under bond number . ,A6'2"t9ra„56 . "; ATTEST OF GARFIELD COUNTY, COLORADO BOARD OF COUNTY COMMISSIONERS • erk to the Board By: Date: Chai MEMO TO: BOARD OF COUNTY COMMISSIONERS FROM: MARK BEAN, DIRECTOR, BUILDING & PLANNING DATE: 9/27/05 RE: AMERICAN SODA, LLP, ACKNOWLEDGMENT OF SATISFACTION AND RELEASE OF SECURITY American Soda, LLP has tendered a request to the Building & Planning Department requesting that we acknowledge satisfactory performance under the conditions of approval contained in Resolution 2000-005 and further that we release their surety and bonding company from all obligations for revegetation provided pursuant to that permit. Steve Anthony, County Vegetation Management Director has inspected the revegetation work performed on the property, pursuant to the conditions of approval contained in Resolution No. 2000-0. It is Mr. Anthony's opinion that American Soda, LLP has satisfactorily performed all conditions of their permit and that there are no potential claims that may be asserted by Garfield County against American Soda, LLP under the tens of that permit. It is my opinion that the County Commissioners should release SAFECO Insurance Company of America, the surety company, from the terms and conditions of bond number 6239756. MEMORANDUM To: Carolyn Dahlgren Mark Bean From: Steve Anthony Re: Solvay Chemicals request for revegetation security release per BOCC Reso: 2000-005 Date: September 1, 2005 Ed Cooley of Solvay Chemicals has requested a release of the revegetation security posted in 2000 for their Special Use Permit for their pipeline for liquid sodium and water. I inspected their work with Mr. Cooley on August 22. 2005 and certify that they have met their revegetation obligations per Garfield County resolution 2000-005. It is my understanding that the County Attorney's Office in cooperation with Building and Planning will coordinate the release of the revegetation security. If you need anything further from me let me know. Bond No. 6239756 Replaces Safeco Bond #604399 LICENSE OR PERMIT BOND KNOW ALL BY THESE PRESENTS, That we, American Soda, LLP Houston Texas (City) as Principal, of 3333 Richmond Avenue (State) ,a Washington Garfield County, Colorado (Street and Number) and the SAFECO Insurance Company of America corporation, as Surety, are held and firmly bound unto , as Obligee, in the sum of Ninety Thousand and oo/ioa Dollars ($ 90,000.00 ) for which sum, well and truly to be paid, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents. Sealed with our seals, and dated this s day of November , 2003 THE CONDITION OF THIS OBLIGATION IS SUCH, That WHEREAS, the Principal has been or is about to be granted a license or permit to XidOtitigit(x( cover the reclamation costs for that section of American Soda, LLP pipeline located In Garfield County (total length approximately 19 miles/ by the Obligee. NOW, THEREFORE, if the Principal well and truly comply with applicable Iocal ordinances, and conduct business in conformity therewith, then this obligation to be void; otherwise to remain in full force and effect. PROVIDED, HOWEVER: 1. This bond shall continue in force: Until , , or until the date of expiration of any Continuation Certificate executed by the Surety OR QUntil canceled as herein provided. 2. This bond may be canceled by the Surety by the sending of notice in writing to the Obligee, stating when, not less than thirty days thereafter, liability hereunder shall terminate as to subsequent acts or omissions of the Principal. American Soda, LLP Principal SAFEC aucee Cothp • T6 of erica Pamela Prokop j torney-in-Fact By WC-1235/EP 4/94 PAINTED IN USA SAFECO" POWER OF ATTORNEY ?CO INSURANCE COMPANY OF AMERICA +ERAL INSURANCE COMPANY OF AMERICA HOME OFFICE: SAFECO PLAZA SEATTLE, WASHINGTON 98185 No. 5713 KNOW ALL BY THESE PRESENTS: Thal SAFECO INSURANCE COMPANY OF AMERICA and GENERAL INSURANCE COMPANY OF AMERICA, each a Washington corporation, does each hereby appoint DONALD R. GIBSON, SANDRA PARKER; LISA A. WARD; WILLIAM L. POWER; MELISSA HADDICK; KIM STRAHM; Houston, Tams Its hue and lawful attorney(s)-in-fact, with full authority to execute on its behalf fidelity and surety bonds or undertakings and other documents of a similar character issued in the course of its business, and to bind the respective company thereby. IN WITNESS WHEREOF, SAFECO INSURANCE COMPANY OF AMERICA and GENERAL INSURANCE COMPANY OF AMERICA have each executed and attested these presents this 4th RA. PIERSON, SECRETARY day of June , 1999 ratidt4/144 W. RANDALL STODDARD, PRESIDENT CERTIFICATE Extract from the By -Laws of SAFECO INSURANCE COMPANY OF AMERICA and of GENERAL INSURANCE COMPANY OF AMERICA: "Article V, Section 13. - FIDELITY AND SURETY BONDS ..• the President, any Vice President, the Secretary, and any Assistant Vice President appointed for that purpose by the officer in charge of surety operations, shall each have authority to appoint individuals as attorneys -In -fad or under other appropriate titles with authority to execute on behalf of the company fidelity and surety bonds and other documents of similar character issued by the company in the course of its business... On any instrument making or evidencing such appointment, the signatures may be affixed by facsimile. On any Instrument conferring such authority or on any bond or undertaking of the company, the seal, or a facsimile thereof, may be impressed or affixed or in any other mariner reproduced; provided, however, that the seal shall not be necessary to the validity of any such Instrument or undertaking." Extract from a Resolution of the Board of Directors of SAFECO INSURANCE COMPANY OF AMERICA and of GENERAL INSURANCE COMPANY OF AMERICA adopted July 28,1970. "On any certificate executed by the Secretary or an assistant secretary of the Company setting out, (1) The provisions of Article V, Section 13 of the By -Laws, and (if) A copy of the power-of-attomey appointment, executed pursuant thereto, and (iii) Certifying that said power-of-attorney appointment Is in full force and effect, the signature of the certifying officer may be by facsimile, and the seal of the Company may be a facsimile thereat." 1, R.A. Pierson, Secretary of SAFECO INSURANCE COMPANY OF AMERICA and of GENERAL INSURANCE COMPANY OF AMERICA, do hereby certify that the foregoing extracts of the By -Laws and of a Resolution of the Board of Directors of these corporations, and of a Power of Attomey issued pursuant thereto, are true and correct, and that both the By -Laws, the Resolution and the Power of Attorney are still In full force and effect. IN WITNESS WHEREOF, I have hereunto set my hand and affixed the facsimile seal of said corporation this 14th day of February 2000 • S-0974/SAEF 7/98 RA. PIERSON, SECRETARY ® Registered trademark of SAFECO Corporation. 6/4199 PDF shall be de% eloped by American Soda in coordination with the BLM. Seed or transplant material shall be derived only from this stand of trees. Prior to disturbing any ponderosa pine. American Soda shall contact the Authorized Officer. 6. The pipeline corridor passes through a number of geographical areas that have been documented to be the locations of plant communities considered to be vulnerable or imperiled in the state of Colorado and/or throughout their ranges (Figure 3.,-2 in the Draft EIS). Potential impacts to these plant communities shall be assessed in consultation with the BLM on a site-specific basis based on final pipeline routing and specific known community site locations. Should it be necessary to disturb these communities, BLM may require the areas to be revegetated with species indigenous to the site. WILDLIFE The Wildlife Mitigation Plan as developed and approved in the FEIS shall be implemented as directed by the Authorized Officer. American Soda shall develop an educational/awareness program for employees that include information on wildlife laws, wildlife harassment and deer1vehicle collisions. The information shall be incorporated into employee orientation and training programs. 3. American Soda shall develop (I) an effective disciplinary policy for dealing with infractions of wildlife laws, including intentional harassment of wildlife, and (2) a policy prohibiting employees from carrying firearms on the job site to reduce the opportunity for illegal hunting. SPECIAL STATUS SPECIES l . Threatened and Endangered Animals In the course of Endangered Species Act consultation, American Soda offered to release, on a schedule set by the U.S. Fish and Wildlife Service (USFWS) to benefit endangered fish, any water from their Wolford Mountain contract that would not be needed by American Soda for direct replacement or exchange purposes. Implementation of this conservation measure by American Soda is considered an integral part of the Proposed Action and its successful execution is implicit under the terms of the consultation and this Record of Decision. American Soda shall provide to the BLM Authorized Officer documentation of the terms and conditions agreed to by American Soda and the USFWS concerning the disposition of the Wolford Mountain water. A-7 613000:461J00.ROD dac i c. :09912 .: ?NO. RAT '. [n order to exempt this action from the incidental take provisions of the Endangered Species Act and as prescribed by the USFWS in the Biological Opinion developed for this project, BLM and American Soda shall comply with the following reasonable and prudent measure with its implementing terms and conditions: To minimize incidental take of Colorado pikeminnow and razorback sucker, American Soda shall. upon testing or actual use of the intake structure from the Colorado River. sample for tish entering the pipeline and settling pond. At least 1 month prior to any operation of the intake, American Soda shall alert appropriate USFWS personnel so that they may provide advice on sampling procedures and/or attend sampling procedures. American Soda shall provide a report to the USFWS and BLM Authorized Officer of all species of fish trapped in the pipeline and settling pond by no later than the end of September of the year following sampling. Upon any indication from sampling that incidental take of threatened or endangered fish is occurring, American Soda shall design an entrainment preclusion device and pay for its timely installation and maintenance. If, during the course of the action covered under the Biological Opinion, levels of incidental take established in BLM's Biological Assessment are exceeded (0.05 percent of total larval and young -of -year razorback sucker and 0.08 percent of total larval and young -of -year Colorado pikeminnow produced upstream of the intake structure per year under any given flow conditions), American Soda and BLM shall coordinate the reinitiation of formal consultation to review and, where necessary, modify the reasonable and prudent measures established in the original Biological Opinion. Additionally. if circumstances change such that the effects of this project on any endangered or threatened species are altered in a manner or to an extent not considered in the Biological Opinion developed for this project (i.e., project operations change, a new species becomes listed. anticipated incidental take levels are exceeded, total average annual water depletions change). formal Section 7 consultation with the USFWS would be reinitiated by the BLM. Threatened and Endangered Plants The Biological Opinion issued by the LS. Fish and Wildlife Service supports Implementation of these stipulations to avoid adv erse effects on threatened and endangered plants. A. The BLM shall implement stipulation NSO-8 of the White River Resource Area Resource Management Plan Record of Decision (BLM 1997) and not A-8 b1000:463.44RQD dot 14:1941_ PM RP/ 4 allow surface disturbance or surface occupancy w ithin habitat occupied by the Dudley Bluffs twinpod or the Dudley Bluffs bladderpod at the Piceance Site. The BLM shall require that no surface disturbance occur within 200 feet of the outer edge of existing populations of Dudley Bluffs twinpod or the Dudley Bluffs bladderpod unless a site-specific analysis indicates that there is a low likelihood for direct or indirect impacts. American Soda shall establish these buffer zones and maintain them through fencing or signs. B. American Soda shall develop and implement a monitoring plan, approved by the BLMM. that establishes a baseline for the known populations of Dudley Bluffs twinpod or Dudley Bluffs bladderpod within the lease area, is able to detect any significant changes in these populations attributable to American Soda's operation, and ensures the adequacy of the committed mitigation. C. American Soda shall re -inventory unoccupied suitable habitat in each mine pane! prior to development of the mine panel. If new populations of the species are found, the mitigation measures established herein shall be applied. No inventory of the 0-5 year mine panel shall be required if surface disturbance begins within 3 years of the 1998 botanical survey. D. In consultation with the BLM and USFWS, restoration of unoccupied suitable habitat disturbed during well field and road construction shall be accomplished by American Soda in accordance with the Soil Conservation, Erosion and Sediment Control. Reclamation and Revegetation Plan. This plan shall be field tested to ensure that the restored habitat promotes suitability for the desired species over suitability for potentially competing species. A-9 61000:463400IROD dx IOr:01991: 5: PM) RPT 9 3. Colorado River Cutthroat Trout The following measures are considered by BLMM to be committed mitigation for the protection of Colorado River Cutthroat Trout (i.e., measures analyzed as part of the proposed action): A. The width of construction in Parachute Creek and riparian zone shall be reduced to the minimum necessary, and removal of large trees will be avoided. B. Construction across Parachute Creek shall be limited to no more than one day per crossing. C. Siltation of Parachute Creek shall be prevented by use of appropriate erosion controls during and following construction. D. American Soda shall restore the streambed, stream banks, and riparian zone of Parachute Creek in consultation with the Colorado Division of Wildlife. VISUAL RESOURCES 1. American Soda shall minimize ground disturbance to the extent possible; including areas of cut and fill. American Soda shall minimize soil sidecast on the downhill slopes of road cuts or well pad areas. At the Piceance Site, American Soda shall paint all permanent structures (i.e., on site for a period Ionger than 90 days after construction) a color agreed to by BEA to blend with the surrounding landscape. Exceptions to this requirement are small structures that are not readily visible from a distance of approximately 1/4mile such as wire and small pipe or structures that, because of OSHA requirements require safety coloration. 3. The project sites shall feature mercury vapor lighting installed to provide adequate lighting for workers in accordance with OSHA standards. Light fixtures shall include visors to reduce glare when viewed from off site. CULTURAL RESOURCES 1. American Soda shall comply with the provisions of the BLN1's Programmatic Agreement with the State Historic Preservation Officer (SHPO) and the PresidentOs Advisory Council on Historic Preservation for the protection of cultural resources or otherw ise ensure that adverse effects to historical properties are avoided in compliance with any BLN1 requirements to satisfy its Section 106 responsibi lities. A-10 69oo02463400/ROD oc r: _ i 92. : AM' ar- ?. American Soda is responsible for informing all persons associated with this project that they will be subject to prosecution for knowingly disturbing historic or archaeological sites or for collecting artifacts. 3. If previously undiscovered historic or archaeological materials are uncovered during construction. American Soda shall comply with the necessary steps to protect such materials as specified in the BLM1's Programmatic Agreement or otherwise comply with any BLM requirements governing discovery situations. OIL SHALE PROTECTION American Soda will develop and implement a plan, subject to BLM approval, to monitor operations to assure compliance with lease stipulations concerning protection of the oil shale. The plan will include sampling of the production stream for dissolved organic carbon to identify if destructive distillation of the oil shale is occurring. SUBSIDENCE MONITORING The Subsidence Monitoring Plan shall be implemented as directed by the Authorized Officer. PIPELINES AND ROADS 1. The sodium minerals pipeline and parallel return water pipeline shall be constructed, operated and maintained in accordance with the Pipeline Plan o, Development. '. Access road upgrades shall be constructed and maintained in accordance with BLM 9113 guidelines and Class C 0 Mountainous Rio Blanco County Road standards. The designated operatorlessee shall regularly maintain the road in a safe, usable condition. A regular maintenance program shall include, but not be limited to. blading, crowning, ditching, culvert installation, drainage installation, surfacing, and inspection. The designated operator lessee shall post signs, visible within line of sight, indicating the location of the underground v. ater pipelines and any cables, providing name, address. and telephone number of a responsible contact person. All pipelines adjacent to or crossing access roads shall either be buried with a minimum of 4 to 5 feet of cover in alluvial areas and a minimum of 30 inches of cover in rocky areas, or they will be otherwise protected from road maintenance and construction activity. A-1 1 5e000:463400IROD doc 991:1: PM •I:PT 9 6. Culverts and/or other measures may be necessary to control surface water runoff from the access road and adjacent areas so as not to impede natural drainage or create erosional hazards. Placement and construction is subject to direction and/or approval by the Authorized Officer. 7 A cattleguard meeting. BLM specifications shall be installed wherever an access road intersects a fenceline. The cattleguard shall be maintained and kept functional by the operator. A gate (wire, metal, etc.) shall be installed adjacent to the cattleguard for the movement of livestock from allotment to allotment. The cattleguard shall be installed at the time of construction of the well pad and access road A-12 611000240400WRDD dac IO+20/991: 52 n11-APT9 INADEQUATE SCOPING AND PUBLIC PARTICIPATION • Commentors. McGihon and Ireland contend that the BLM did nor comply with NEPA requirements for public scoping, hindered public participation and withheld pertinent information by not making the Commercial Mine Plan available for public review until March 1999. The BLM did adequately comply with the letter and spirit of the NEPA regulations regarding public scoping and participation. BLM initiated scoping in June 1998 to ensure that there was an early and open process to inform the public and agencies of the proposed project and to solicit input on identifying significant issues and alternatives to be analyzed. In accordance with the CEQ Scoping Guidance, the "Scoping Document", which was available to the public and agencies, describes the proposed action, preliminary range of alternatives and potential scope of environmental issues to be addressed. At the public meetings, the BLM presented an overview of the project and the proponent was available to answer questions on specifics of the proposed project. All comments and letters received during the public scoping period and a summary of the issues raised were presented in the "Summary of Public Scoping Meetings", which was also made available to the public. NEPA does not require that a commercial mine plan be completed prior to scoping, nor does it have to be available for public review during the preparation of the Draft EIS. The commercial mine plan was made available on March 10, 1999 and throughout the Final EIS comment period. The pertinent information on the proposed action that was presented in Chapter 2 of the Draft EIS was extracted primarily from the "Commercial Mine Plan", and was presented in plain language so that decision -makers and the public could readily understand the proposed activities and processes. The DEIS does not rely on other data in the "Commercial Mine Plan" that was not specifically disclosed in the DEIS to support its conclusions. The fact that the Mine Plan was not available for review at the BLM office during the Draft EIS comment period has riot in any way impeded the ability of the public to comment on the proposed mining operation. INADEQUATE EXAMINATION OF ALTERNATIVES • Commentors' McGihon and Dodson contend that the EIS did not examine a reasonable range of alternatives and that adequate justification was not provided for rejecting alternatives before conducting the environmental impact evaluation. As stated in the Final EIS, a reasonable range of alternatives was addressed in the EIS in accordance with NEPA. The EIS also disclosed alternatives that were considered but eliminated from detailed study as required by the Council on Environmental Quality (CEQ) regulations. The CEQ recognizes reasonable alternatives as those that are practical or feasible from a technical and economic standpoint, use common sense, and consider the purposes and needs of the proposed action. The Commentors do not identify other alternatives that the EIS should have discussed that would be considered technically or economically feasible INADEQUATE ENVIRONMENTAL ANALYSES • Air Quality: Dodson indicates that a major error may have been made in the air emission B-2 6800:2+6340YROD doc 10/11199f211 PMVRFCA estimates due to underestimating the assumed energy requirements for the proposed project. The commentor has confused the test phase air quality permit information with the commercial phase information. The referenced operating permit (No. 980PRB 197) and the cited fuel requirements of 447.461 MSCF (million standard cubic feet per year) apply to the existing test phase boiler. The test phase boiler has a heat capacity that is I0 percent of the commercial phase boilers. The estimated fuel requirement presented in Attachment A of the commercial phase Construction Permit is 3,942 MMSCF which is consistent with the commentors estimated 4,041 MMSCF. The fuel requirement used to estimate emissions in the construction permit application and used as the basis of the modeling and impact assessment is 4,444 MMSCF. Thus, the fuel requirement used for the impact assessment is actually 10 percent higher and more conservative than the commentors'estimate. • Groundwater Baseline Conditions: Several commentors (Ireland, Tobin, Dorsett, and McGihon) stated that available data were not adequate to establish baseline conditions for groundwater; therefore, the project should not go forward without additional characterization. Ireland, Tobin, Dorsett, Rothberger, and McGihon also contend that laboratory results used by the BLM to characterize baseline groundwater quality are erroneous and deficient, and BLM's reliance on these data is unacceptable. It is BLM's position that sufficient information exists with respect to groundwater to make a well -reasoned decision to permit the project. This decision is based on the following; ► Aquifer delineation (i.e., Iateral and vertical extent) and groundwater flow patterns are sufficiently characterized from the following sources of information: (1) American Soda monitoring wells and exploration boreholes; (2) historic exploration boreholes and groundwater wells in the vicinity of the project, and (3) regional U.S. Geological Survey (USGS) and U.S. Bureau of Mines published reports characterizing groundwater conditions in the Piceance Basin including the project area. From the above sources, the relationship of aquifers, aquitards and the zone proposed for solution mining is well understood. 1 Groundwater quality data presented in the Draft EIS and Final EIS for American Soda monitoring wells near the test mine site are representative of baseline conditions in the vicinity of the first 5 -year mining panel as discussed below. Groundwater samples were collected and analyzed by American Soda a number of times during 1997 and 1998 from four wells representing water quality in the alluvium, upper aquifer, lower aquifer, and the dissolution surface. Initial concerns by Tobin focused on his assertion that analytical results did not conform to groundwater quality trends noted in previous studies of the Piceance Basin (i.e., water quality appeared to be worse in the vicinity of American Soda's wells than regional data suggested it should be). American Soda subsequently contracted a known expert in groundwater conditions within the Piceance Basin, George Saulnier, a former USGS employee, to review and comment on groundwater data collected by the proponent. Dr. Saulnier prepared a report to document his findings ("Groundwater Quality in Piceance Creek Basin", G.J. Saulnier, Jr., September 1999). A copy of Dr. Saulnier's report is available for public review at the BLM White River Field Office in Meeker. He concluded that past activities in the vicinity of American Soda's project had the B-3 611:100246 40010D.+lva lag 319912 41 PMVRPTA potential to cause cross -contamination of aquifers in the area. He specifically noted activities by Shell in construction of their in-situ oil shale test cavity, the US Bureau of Mines at the Horse Draw test mine site. and improper plugging and abandonment of mineral and oil and gas exploration boreholes in the area (including borehole 20-1 on American Soda's leasehold) as likely sources of contamination. He suggested that these prior activities likely contributed to the total dissolved solids (TDS) anomalies observed in Amencan Soda groundwater monitoring wells. Conclusions in his report are supported by his presentation and interpretation of specific conductance readings taken in monitoring wells installed by American Soda for the pilot project. • Groundwater Flow Direction: Commentors' McGihon and Moran noted that the groundwaterjIow direction used by American Soda to site additional monitoring wells required by the Groundwater and Surface Water Monitoring Plan does not conform exactly to site-specific or regional flow directions, and the data collected from these wells would be of little use if the flow direction is different from that assumed. The BLM, other regulatory agencies (e.g., USEPA, Colorado Division of Minerals and Geology), and American Soda recognize that the Groundwater and Surface Water Monitoring Plan is a "living" document and revisions to the plan may be necessary as more data are gathered across the project area of approximately 4,500 acres over 30 years of operation. The Record of Decision also allows for the flexibility to change and/or revise stipulations as necessary based on monitoring results (Section VI Mitigation and Monitoring). If results from the planned wells indicate that additional wells are needed because of variations in direction of groundwater flow from that assumed, BLM will require installation of additional wells. It should be noted that American Soda plans to accomplish several objectives with installation and sampling of the planned wells. A key objective is to evaluate vertical hydraulic gradients and associated water quality at several multiple -completion sites. These data will help verify information in Saulnier's report (Saulnier 1999) suggesting the likelihood of cross -contamination from historic activities. This objective necessarily requires that slight differences in groundwater flow direction between the upper aquifer (i.e., northeasterly flow) and lower aquifer (i.e., easterly flow) systems may be a secondary consideration for some well locations. Furthermore, the BLM does not believe McGihon's assertion that data collected from the planned wells will be of limited value if the flow direction is not exactly as that assumed. Well locations were purposefully selected to account for possible variations in Flow from that assumed. Therefore, the wells are expected to provide upgradient and down gradient information relevant to at least portions of the first 5 -year mine panel if not the entire panel. • Laboratory Detection Limits: Several commentors P Moran, Tobin, Rothgerber, and Komatinsky) noted that laboratory Method Detection Limits (MDL) for many water quality parameters listed in Tables 2 and 3 of the Groundwater and Surface Water Monitoring Plan are too high to be of use when evaluating whether a given result exceeds state water quality standards. Moran presents a list of MDLs and Practical Quantitation Limits (PQLs) from a commercial laboratory, Core Laboratories, to demonstrate what he feels are reasonable limits which in many cases are tnuc/t lower than those shown in the Groundwater and Surface Water Monitoring Plan. A multi -agency meeting was held March 25, 1999, in an effort to bring all agencies into 8-4 6800tn.163-40N1RODak 1413r99i2.+1 P\SYRPTA consensus on a single Groundwater and Surface Water Monitoring Plan (Plan) for the Yankee Gulch Project. Those in attendance at this meeting included representatives from American Soda. Colorado Division of Minerals and Geology (CDMG), U.S. Geological Survey, Rio Blanco County, and the U.S. Environmental Protection Agency participated via telephone. American Soda provided a draft Plan at that meeting. After the meeting another draft Plan was produced by American Soda and reviewed by the agencies. A final Plan was produced April 22, 1999, and distributed to the agencies. CDMG subsequently requested a review of Tables WQI and WQ2 from the Plan because the Method Detection Limits (MDLs) in these tables were higher than the Basic Standards for Groundwater provided in Colorado Department of Public Health and Environment, Water Quality Control Commission Rule No. 41. A new set of Tables WQI and WQ2 with MDLs at or below the Basic Standards for Groundwater was submitted to CDMG on June 3, 1999..CDMG responded with a request to change the MDLs for cadmium, copper, silver, and chloride to a value lower than the Basic Standards for Groundwater. High MDL levels in the groundwater monitoring plan were noted by commentors at EPA's July 13, 1999, public hearing held in Meeker, Colorado, for American Soda's Class 111 Underground Injection Control Permit. The EPA has not distributed responses to the comments received during this hearing. Responses and required changes will be available from the EPA before issuance of the Class III UIC permit. On June 23, 1999, the Colorado Mined Land Reclamation Board (MLRB) reviewed American Soda's application for a 112 Permit and approved the application provided certain conditions would be met prior to circulation of mining fluid. Two of these conditions, defined in the 112 Permit issued by CDMG to American Soda July 16, 1999, are applicable to the Plan. One condition required that the Plan incorporate the recommended MDLs for cadmium, copper, silver, and chloride. The other condition required a second review of the MDLs from Tables WQ1 and WQ2. CDMG and the MLRB required that the MDLs in these tables reflect the capability of the laboratory testing equipment used to analyze the samples: therefore, ensuring the testing methods used will adequately meet the Basic Standards for Groundwater. Tables WQI and WQ2 were revised to incorporate the required conditions and submitted to CDMG as a Technical Revision to the 112 Permit on September 16, 1999. The BLM wishes to point out that detection or quantitation limits actually obtained on high TDS groundwater samples could be higher than laboratory determined MDLs and PQLs. This is due to the fact that the samples may require dilution prior to analysis, and the laboratory MDLs and PQLs would need to be adjusted upward to account for sample dilution. ENVIRONMENTAL IMPACTS INADEQUATELY ANALYZED • Several comnrentors (Dodson. McGihon, Rothgerber, Ireland) contend that by not disclosing data or even a summary of the test mine operations, neither the public or the BLM could adequately assess rhe potential impacts or technical or commercial viability of the proposed commercial operation. In addition, McGihon asserts that the EIS did not disclose the intended use or potential impacts of the future use of the test mine facility during commercial operations. The construction and operation of the test mine facility are described in the test mine plan B-5 610002743+OIYRt}b ,Inc 10,1 3.991 2 41 PMURPTA ("Experimental Test Cavity Project", February 1997). The environmental effects were evaluated by the BLM in 1997 and the results presented in the "Decision Record and Environmental Assessment for American Soda Test Mine Plan" dated May 2, 1997. The test mine facility will remain in place during commercial operations and used for continuing research on operations and completion methods. These uses remain within the range of activities previously analyzed in the BLM's Environmental Assessment, and would not be different than commercial activities analyzed in the EIS for the commercial operations. As stated in the Final EIS, the BLM reviews monitoring data from the test facility and believes that the results have adequately demonstrated the technical feasibility of the proposed mining and resource recovery methods. Operation pressures and temperatures commensurate with those proposed for commercial operations have been tested and results reviewed by the BLM. No unexpected results were obtained • Commentors' McGihon, Moran and Rothgerber assert that the potential impacts to oil shale from temperatures and pressures proposed by American Soda have not been adequately evaluated. Eristing groundwater data for Total Organic Carbon from American Soda test wells compared to regional background data indicate that the American Soda test wells have already caused some breakdown of oil shale organic compounds. Commentor Miller expressed concern about the future mineability of the oil shale. The BLM believes that potential contamination of groundwater from historic operations in the vicinity of American Soda's test mine facility (Saulnier 1999) could account for higher than expected TOC values. In any event, American Soda will be required to conduct their commercial operations in conformance with the lease terms, including the protection of oil shale resources, as authorized by the BLM. As stated in the Draft and Final EIS, the proposed nahcolite mining operations will not adversely affect the future mineability of oil shale. American Soda contracted with Agapito Associates, Inc. to determine the potential impacts to the oil shale resulting from the solution mining of sodium minerals at the project site ("Evaluation of Impacts to Oil Shale Due to Solution Mining of Sodium Minerals, Yankee Gulch Sodium Minerals Project", Agapito Associates, Inc., 1999) The document is a summary of a literature search on low temperature effects on oil shale and of the pilot plant findings. The information from the pilot plant shows organic compounds are found in the recovery production fluids. The project quantified the potential hydrocarbon (VOC) emissions from the well head gas separators, stripper system, and the combustion sources (see response F4.4 of the FEIS). A copy of the Agapito report is available for public review at the BLM White River Field Office. • McGihon and Dodson assert that the EIS failed to evaluate the potential impacts of the White River Electric Association 138kv-transmission line that will traverse American Soda's lease. The "Cb to Ca" 138kv power line was originally proposed by Colorado -Ute in 1987. The purpose of the line was to connect the Meeker to Cb 138kv line owned by White River Electric Association (WREA), with the Deserado to Ca 138kv line owned by Moon Lake Electric. This would create an intertie between the transmission systems operated by Deseret Generation and B-6 6/430024634COAROD.doe 10/13,99i 2 41 FMURFI Transmission, the supplier of power to Moon Lake, and Colorado -Ute, as supplier to WREA, resulting in greater system reliability. Ultimately, the project was put on hold, and in 1992 Colorado -Ute withdrew their application stating that the project was still a part of their long- range plans. However, in 1992, Colorado -Ute filed for bankruptcy, selling local assets to Tri- State Generation. In 1996, Moon Lake determined that they no longer needed the Deserado to Ca line. WREA purchased this line, and the current proposal, as before, is to tie the lines together for greater system reliability. Based on WREA's application, it is BLM's understanding that WREA intends to pursue this proposal regardless of the Yankee Gulch Project. • McGihon questions whether the Agapito rock mechanics study was conducted using the correct projected average cavity temperature (Le., 420° F). Even though injection temperatures may be over 400°F and initially the cavity temperature could be up to 400°F, operational constraints indicate that the average cavity temperature at maturity will be close to 300°F. Therefore, the thermomechnical modeling conducted by Agapito Associates, Inc. using an average cavity temperature of 300°F is appropriate for evaluating stability. • Dodson, Ireland, McGihon, and Rothgerber contend that it is not possible to evaluate potential impacts to groundwater without knowing the constituents in the mining injection fluid, and consideration of this information as confidential by the proponent is unacceptable. The BLM reviewed data for the chemical composition of the injection fluid during the test mine phase and did not have reason to expect the presence of hazardous constituents. The whole basis for the in-situ mining process proposed by the proponent and demonstrated during the test mine phase relies on a closed -circulation system within the mine cavity. From a practical and economic standpoint as well as an environmental perspective, the proponent can not afford to and will not be allowed to operate a cavity that "leaks". The design of the solution wells including cemented steel casing strings through the upper and lower aquifers will provide the primary method of protection for groundwater resources. Any cavity showing initial signs of leakage from pressure monitoring or groundwater quality data will be immediately shutdown and mitigation measures will be implemented. • Dodson believes that potential impacts to groundwater particularly along the pipeline from potential pipeline spills were not adequately evaluated or disclosed in the EIS. He goes on to assert that NEPA requires an evaluation of potentially significant adverse environmental impacts from possible contamination due to releases from the pipeline. It appears that the Commentor is confusing disclosure and discussion of potential impacts with unavoidable adverse impacts. There is a significant difference in how NEPA deals with these two Issues. In the EIS, it is acknowledged that groundwater has the potential to be irripacted if product is spilled from the pipeline or a release occurs from a solution mine cavity. However, there is no certainty that these situations will ever occur. In fact, the operational monitoring required of the proponent is designed to prevent these scenarios from occurring, and if they occur, limit adverse impacts. It is the position of the BLM that no reasonably foreseeable, unavoidable, adverse impacts to groundwater exist under the Agency Preferred Alternative. UNCERTAINTIES B-7 660002163d06+ROD Lim I0/1399(2:1I. P.M)IRPrA • Several commentors (Nehts, Rothgerber, Ireland, Miller, and McGihon) contend that BLM should require American Soda to determine the size and shape of their test mine cavities. in their opinion, this should be done to verify that the test cavities are developing in accordance with the projected cavity size and shape at full development (Le.. a cylinder approximately 200 feet in diameter and 600 feet in height). Section 3.3 of the Subsidence Monitoring Plan (Appendix F of the Final EIS) requires American Soda to evaluate technologies to characterize solution cavity size and shape and present their findings to the BLM by June 2000. The plan goes on to discuss application of the selected technology(s) during the initial stages of commercial mining when cavities in the first mining panel have reached an anticipated radius of approximately 100 feet. After June 2000, BLM will require American Soda to test the selected technology(s) in the test mine cavity to verify that the approach will work during the commercial mine phase of the project. Field testing results for the selected technology(s) must be reported to the BLM. The BLM will also require American Soda to revise Section 3.3 of the Subsidence Monitoring Plan to reflect the above requirements. If the size and shape of the test mine cavity is considerably different than that modeled by the proponent to evaluate subsidence, the BLM can then require additional modeling or operational changes to solution mining processes if needed prior to commercial mine startup. INADEQUATE MITIGATION • Several commentors (McGihon, Dodson, Rothgerber, Ireland) believe that the Final EIS fails to adequately specify mitigation measures and that the BLAif is substituting monitoring for effective mitigation of potential impacts. In particular, commentors Ireland, Cody, Rothgerber, Dodson and McGihon express concern that the Final EIS [e.g., Groundwater and Surface Water Monitoring Plan, and the Pipeline Spill Contingency Plan (Appendix G and E, respectively, of the Final EIS)] does not contain mitigation or remediation plans for potential impacts to groundwater. Ireland states that monitoring is not an effective substitute for a remediation plan. Rothgerber asserts that "This approach may be fairly summarized as waiting until the catastrophe happens, then deciding what to do about it." Rothgerber goes on to state that the absence of specific mitigation measures violates NEPA. It is BLM's position that mitigation measures would only be required in the EIS if reasonably foreseeable adverse impacts were identified for the Agency Preferred Alternative. For example, a Wildlife Mitigation Plan is included in the Final EIS to mitigate expected impacts to mule deer, sage grouse, migratory birds and raptors. Operational safeguards and monitoring specified in the EIS are designed to prevent adverse effects to the environment and monitor changes or trends in baseline conditions. No mitigation measures are specified for groundwater because no reasonably foreseeable, adverse impacts were identified in the EIS. BLM feels that mitigation cannot be prescribed without defining the problem through monitoring. Based on the monitoring results, BLM will be continually reviewing the potential for adverse impacts and will change and/or revise the mitigation measures and stipulations in the ROD as necessary to prevent reasonably foreseeable adverse impacts from occurring. Should a release to groundwater accidentally occur, B-8 6EO O2J6M9(1ROD.Fac Ia119942'.11 ?MI/RFT/9 assessing the risk to potential receptors is one of the first considerations. Given groundwater flow rates measured in feet per year and potential down gradient receptors distant from the project, particularly at the Piceance site, flexible site/release-specific mitigation measures would be necessary. References Cited: Agapito Associates, Inc., 1999, Evaluation of Impacts to Oil Shale Due to Solution Mining of Sodium Minerals, Yankee Gulch Sodium Minerals Project, September 8, 1999. Saulnier, G.J., 1999, Groundwater Quality in Piceance Creek Basin, Duke Engineering & Services, Austin, TX. September 7, 1999. B•9 66001:124611OOPROO Jac 1Od111991241 11.1yRP79 JOHN A. THULSON EDWARD MULHALL. JR. SCOTrBALCOMB LAWRENCE R. GREEN T[MOTHY A. THULSON LORI J. M. SATfERFIELD EDWARD e. OLszewSKI DAVID SANDOVAL DENDY M. HEISEL JEFFERSON J. CHENEY BALCOMB & GREEN, P.C. ATTORNEYS AT LAW P. O. DRAWER 790 818 COLORADO AVENUE GLENWOOD SPRINGS, COLORADO 81002 Telephone: 970.945.6546 Facsimile: 970.945.8902 January 18, 2000 Mark Bean Garfield County Building & Planning Department 109 8th Street, 3rd Floor Glenwood Springs, CO 81601 OF COUNSEL; KENNETH BALCOMB Re: Product and Water Return Pipeline Special Use Permit for American Soda, LLP Dear Mark: I enclose herewith for your reference a copy of the correspondence from Mr. John Loschke, Mayor for the Town of Parachute, to the Garfield County Commissioners dated January 7, 2000, addressing the Reimbursement Agreement between the Town of Parachute and American Soda, LLP. This letter was sent to the Board at American Soda's request for the purpose of satisfying the condition of approval incorporated by the Board on December 13, 1999, specifically, that American Soda provide written confirmation that the Reimbursement Agreement previously executed by American Soda and the Town of Parachute address all the fiscal impacts presented by the American Soda project to the Town of Parachute. I was unsure as to whether this letter was mailed directly to the Board and as such felt it appropriate to provide you a copy of the same. BALCOMB & GREEN, P.C. ATTORNEYS AT LAW Mark Bean January 18, 2000 Page 2 Should you have any questions or concerns regard ng any of the above, please feel free to contact me at your convenience. Very truly yours, BALCOMB Sr GREEN, P.C. . r� rothy '• ulson TAT:kjk Enclosure Toon of Parachute int stratron 222 Telephone: (970) 2854:e; Facsimile: (970) 285-9146 January 7, 2000 Garfield County Commissioners 109 S"' Street, Suite 300 Glenwood Springs, CO 81601 Gentlemen: The Town of Parachute recently entered into L.LP to address the possible impacts their op the ``Town. This agreement provides for the rein Town feels that the issues covered in the ec The agreement provides for the possibility ha In the event that there were additional intact renegotiate the agreement in a manner the To Sutberely, John Loschke xc. Board of Trustees CO 81635-0100 Mayor John Loschke Pot ft' Fax Nott? 7671 Data/ _ _yy 4,511 4, tater Co/Dept Co 4rvx14le y G9C� Phone 1 Prione N rax' 977 - f 7 5-1 Q (�'i z- "" a Reimbursement Agreement with American Soda, ration and the additional work force would have on ursement ofpolice officer and court staff wages The ent are the actual impacts to the Town. at this time he impacts would be greater or fess than anticipated. the Town is confident that American Soda would �n would accept 1 John A. Thulson Edward Mulhall, Jr. Scott Balcomb Lawrence R. Green Timothy A. Thulson Lori J. M. Satterfield Edward B. Olszewski David Sandoval Dendy M. Helsel Christopher L. Coyle Jefferson J. Cheney Balcomb & Green, P.C. Attorneys at Law (formerly Delaney & Balcomb, P.C.) P. 0. Drawer 790 818 Colorado Avenue Glenwood Springs, Colorado 81602 Telephone: 970.945.6546 Facsimile: 970.945.8902 October 1, 1999 Mark Bean Garfield County Building & Planning Dept. 109 8`E' Street, 3`d Floor Glenwood Springs, CO 81601 Dear Mark: Of Counsel: Kenneth Balcomb I enclose herewith for your review, (3) draft copies of the above entitled Special Use Permit application of American Soda L.L.P. ("American Soda") As you are aware, American Soda is, in conjunction with the above, presently processing an application for Fiscal Impact Mitigation under Section 5.08 of the Garfield County Zoning Resolution. American Soda expressly recognizes in this regard, that this application for Special Use Permit will not be deemed complete until such time as: 1. American Soda's application for Fiscal Impact Mitigation is fully processed by the Board under 5.08;or 2. American Soda receives permission from the Board of County Commissioners ("Board") to process its application for Fiscal Impact Mitigation jointly with its application for Special Use Permit; or 3. The Board exempts American from the remaining provisions of the Fiscal Impact Mitigation Program. Consistent with the above, American Soda further recognizes and agrees that this submission is made for the limited purpose of allowing County Staff to perform a preliminary completeness review of American Soda's application for Special Use Permit and as such does not, JOHN A THULSON EDWARD MULHALL• JR. SCOTT GALCOMB LAWRENCE R GREEN TIMOTHY A THULSON LORI J M SATTERFIELD EDWARD B OLSZEw5KI DAVID SANDOVAL D€NDY M HEISEL CHRISTOPHER L COYLE JEFFERSON J CHENEY BALCOMB & GREEN, P.C. ATTORNEYS AT LAW P. O. DRAWER 790 818 COLORADO AVENUE GLENWOOD SPRINGS, COLORADO 81602 Telephone: 970.945.6546 Facsimile: 970.945.8902 December 9, 1999 Mark Bean, Director Garfield County Building & Planning Department 109 81h Street Glenwood Springs, CO 81606 (Hand Delivered) RE: Special Use Application for Pipeline American Soda, L.L.P. Dear Mark: OF COUNSEL KENNETH BALCOMB Pursuant to our discussions I enclose herewith seven (7) copies of the Reimbursement Agreement between American Soda, L.L.P. and the Town of Parachute, Colorado executed on November 18, 1999, in conformance with paragraphs 3.B, C and D and pursuant to which American Soda will reimburse to the Town of Parachute the fiscal impact costs resulting from American Soda's proposed operations. 1 had thought that a copy of this was earlier provided to you; 1 apologize for the delay in this forwarding. TAT:sv Encs. Very truly yours, BALCOMB imothy A, Thulson RECEIVED DEC 0 9 1999 r..n:'F-1ELD court EDIT DE W T,-1 ST. - sum303 81601 LLE,�yglOE'0 SPRINGS, CO Sent By: American Soda; 970 928 9863; Nov -22-99 15:58; Page 2 REIMBURSEMENT AGREEMENT BETWEEN AMERICAN SODA LLP AND THE TOWN OF PARACHUTE, COLORADO THIS REIMBURSEMENT AGREEMENT is made and entered this lath day of November, 1999 by and between American Soda LLP and the Town of Parachute Colorado. WHEREAS, American Soda LLP, a Colorado Limited Liability Partnership ("American Soda"), is the proponent of proposed commercial nahcolite mining operations ("American Sada Project") located in western Garfield and Rio Blanco Counties. WHEREAS, the Town of Parachute, Colorado ("Town") is a Colorado municipal corporation duly formed and existing under the Colorado constitution. . WHEREAS, the major components of the American Soda Project include a commercial nahcolite mining and initial processing operation located in Rio Blanco County ("Piceance Site) and a final product processing and shipping operation located in Garfield County ("Parachute Site"). The Piceance Site is located within the U.S. Bureau of Land Management White River Resource Area approximately 22 miles west-southwest of Meeker, Colorado. The Parachute Site is located approximately 2.5 miles northwest of the town of Parachute, Colorado at the former Union Oil Company of California 011 Shale Upgrade Facility. A pair of parallel buried pipelines approximately 44 miles long will connect the Piceance and Parachute Sites. WHEREAS, American Soda has received all requisite approvals from the Board of County Commissioners for Garfield County, Colorado ("Board of Commissioners") for the construction and operation of the processing and rail shipping facilities at the Parachute Site, 'WHEREAS, American Soda has made application with the Board of Commissioners for Special Use Permit approval for the construction and operation of the buried parallel pipelines (Collectively "Pipeline Special Use Permit"). This application for Pipeline Special Use Permit is presently scheduled for consideration by the Board of Commissioners on December 13, 1999. WHEREAS, pursuant to the Fiscal Impact Mitigation Program regulations as contained within Section 5.08 of the Garfield County Zoning Resolution of 1978, the Board of Commissioners has required American Soda, as a condition to precedent to issuance of the Pipeline Special Use Permit, to jejnter into an agreement with the Town of Parachute to deal with possible additional calls for service in town and to Battlement Mesa as a part of a mutual aid agreement with the Garfield County Sheriff for police service. Board of County Commissioner Resolution entered on October 12, 1999. Reimbursement Agreement American Soda LLP/Town of Paracinde Page 1 Sent By: American Soda; 970 928 9863; Nov -22-99 15:59; Page 3/6 WHEREAS, the Board of Commissioner's hearing upon the American Soda's Pipeline Special Permit is scheduled for consideration on December 13, 1999 WHEREAS, in accordance with the mandate of the Board of Commissioners above described, American Soda and the Town desire to set forth the provisions pursuant to which American Soda will mitigate the fiscal impacts to the Town which may be created by the American Soda Project. NOW THEREFORE, for and in consideration of the mutual covenants and promises of the parties and other good and valuable consideration, the adequacy and sufficiency of which is hereby acknowledged and confessexl, American Soda and the Town, on behalf of themselves, their successors, assigns and/or transferees, agree as follows: 1999: 1. American Soda shall pay to the Town on a quarterly basis beginning October 1, a. the total quarterly cost increase, ifany, in the number of compensation hours ("Comp. Hours") earned by the Town's police officers over and above the Comp. Hours earned during the corresponding time period in the base year of 1998, computed at the applicable pay rates set forth within Exhibit A attached hereto; and b. 51432.72, which amount represents the total payroll costs instant to compensating each of the pones of Court Clerk, Assistant Court Clerk and Records Coordinator for 24 additional hours (8 hours per month), computed at the applicable pay rates set forth within Exhibit A. 2. Each quarterly payment shall be due within (30) days of the receipt by American Soda of an invoice prepared by the Town which breaks down the above described charges in a form and manner substantially equivalept to the form incorporated within Exhibit A. 3. American Soda shall cause this Agreement in its entirety to be incorporated as a condition of approval within any resolution issued by the Board of County Commissioners approving the Pipeline Special Use Permit . 4. This Agreement shall n9t become effective until such time as the Board of Commissioners approve, upon conditions acceptable to American Soda, the Pipeline Special Use Permit. For the purpose of implementing this provision, American Soda shall be deemed to have accepted the Board. of Commissioners approval upon the initiation by American Soda of any construction or other activities governed under the Pipeline Special Use Permit so approved. 5. Unless earlier terminate1l by mutual agreement of the parties, this Agreement shall Reimbursement Agreement American Sada UP/Town of Parachute Page 2 Sent By: American Soda; 970 928 9863; Nov -22-99 15:59; Page 4/6 terminate by its own terms upon the initiation by American Soda of commercial nahcolite mining and processing operations at the American Socia Project 6. In recognition of the underlying purpose to be served by this Agreement, if the fiscal impacts of the American Soda Project to the Town are significantly greater or less than those anticipated under this Agreement, the parties agree that they will negotiate in good faith toward the purpose ofmodifying the provisions in a manner commensurate with the fiscal impacts presented by the American Soda Project. 7. In the event of any material failure by either party hereto to comply with the terms of this Agreement, the other party shall have standing to bring suit at law or in equity to enforce compliance herewith. It is expressly agreed that any default in the provisions hereof may be specifically enforced. 8. Each party's obligations under this Agreement shall be assignable to any grantee, purchaser, transferee, or assignee of the party's interest, and shall survive nay such conveyance, purchase, transfer or assignment. Any such assignment by American Soda will not relieve it of joint and several responsibility with the assignee for compliance with the conditions of this Contract, unless release by the Town. 9. Each party shall bear its own attorney's fees incurred in the negotiation, execution, and implementation of this Agreement. However, in the event arbitration or litigation is necessary to enforce the rights of the parties to this Agreement, as between themselves, the prevailing party in, such arbitration or litigation may be entitled to reasonable attorney's fees and costs actually incurred in the discretion of the arbitrator or the Court. 10. This Agreement shall be binding upon and inure to the benefit of the parties. their successors, grantees and assigns. 11. No provision of this Agreement may be waived except by an agreement in writing signed by the waiving party. A waiver of any term or provision of this agreement, or a finding that any of the terms and conditions hereof are illegal or unenforceable shall not be construed as a waiver of any other terra or provision; the terms of this Agreement are intended to be severable.. IN WITNESS WHEREOF, the parties have executed this Agreement on the date above written. The Mayor was authorized to sign this Agreement on behalf of the Town by motion of the Board of Trustees at a regular meeting held on November 18, 1999. THE TOWN OF PARACHUTE, COLORADO Reimbursement Agreement American Soda LLPftown of Parachute Page 3 Sent By: American Soda; 970 928 9863; Reimbursement Agreement American Soda LLP/Town of Parachuk Page 4 Nov -22-99 16:00; Page 516 Hv.N4s j/` dr May AMERICAN SODA, L L.N. 9(9 ®fed `00:9G 66-ZZ-AON !8986 9Z6 OLE, :Epos u?ataauty :h8 }ua I 1— iQiflltii 4i • 1J1LJ R'rf x - . E rd; ill: y !iPE(tfiJP , ,.r.l. a ) ,z ., , -.; III. !P -;o; oegl+'..a _� M X888 i M l M 1 1r O 1111 W. f M t •W es IG ti.0 MM M'� l y1��•• V V 4 i {pL.N ��.r'.L..0 W 8888. MMNM J+� l V hi% M Q I . N V W rC F Y 11111111 f4) M t! •�� 1 r • a �•1� M 1w M g =P wiwahlz TWITit N NM 41 y Ir aq 01 yamy. _.. O� - Y i _ NM Q.. _ rP' taii .x.,:.;! �w ( .1 ^ 40.,.M 1 i I .1 i _C1_ W'w 00- {q —.4" ;411I R e g 4 c M III .111 1 •a 'n 8' Y t, ^+ I +11 t MY VJ-I t► M M X11 if e. eQ ri t1 MM ti " 'P i i '41 -0-- -q�'.. MMM ;44:1 i of M ,Y It rei +_-+ tii MNV... iJ W 41 fit Illi --mn _3` M- �D 7y r '. I_. iT7 bn ...1 .. .. J�y, M a• N ,e4."4, A. kJ P-MOQrO MSF u= MS�� O i r...! M r J M r J4 i Ir u !fa C[Fi W tet f i Mi 4r it �!' f0 _ 74,4 `w 4 1-3 h.� fn • _01 -� • •O ..4 _ ♦ WMY c"}rN. �y vIN e I. Y , .lN } i W -c�" i v.Yl QO 2000 Rtstrrt Officer Horn Comp &RetotedCocrt tier=rdto Qu urty TOTL ORker ; Room RI* TOTAL Stiff A,S Rut TOTAL. Total �SreiAgent 134.42 ofAatOen= it0 Su7mnestimmoor 14219 7rrretden f133 — 9(9 ®fed `00:9G 66-ZZ-AON !8986 9Z6 OLE, :Epos u?ataauty :h8 }ua RESOLUTION NO. 99 9 A RESOLUTION OF THE BOARD OF COUNTY COMMISSIONERS OF RIO BLANCO COUNTY CONCERNING THE APPLICATION OF AMERICAN SODA LLP FOR A MAJOR DEVELOPMENT PERMIT. WHEREAS, Rio Blanco county has received an application from American Soda LLP for a major development permit to construct and operate a nahcolite solution mine .n Rio Blanco County; and, WHEREAS, said nine is to be located in the Piceance Creek area of Rio Blanco :aunty cn BLM lands approximately 22 miles West -Southwest cf Meeker in Sections 15 through 21 and Section 29 of T1S. R97W of the 5th P.M.. Said mine is to be located on the Yankee Gulch Joint Venture Lease encompassing approximately 4,955 acres of which 1.030 acres will be. impacted under the proposed thirty-year mine development plan: and. WHEREAS, the project will consist of two sites consisting of the Piceance mining operation in Rio Blanco County and a processing plant in Garfield County in the vicinity of Parachute, Colorado with two pipelines forty-four milers in Length connecting the two sites; and, WHEREAS, the Planning Commission of Rio Blanco County conducted a public hearing with regard to said application on March 15, 1999 and recommended approval of the project eubject to a number of conditions: and, WHEREAS, the Board of County Commissioners of Rio Blanco County conducted a public hearing, pursuant to notice, on April 12th, at which time the public had an opportunity to comment on the proposed project as provided in the major development permit ordinance of Rio Blanco County. NOW, TRIREYORE, T8a BOARD OF COUNTY CONN:I99ION8RS OF RIO BLANCO COUNTY finds as follows: 11 That the principal concerns rained at the public hearing conducted before the Board of tiounty Commissioners of Rio Blanco County concerned the effect an water quality in the Piceance Creek Basin by the wells and cavities to be created by the proposed project. 2) That an independent monitoring of the effect of the proposed project cn water quality in the Piceance Creek Basin should be a requirement of the major development permit. 3) That the conditions for approval of the permit recommended by the Planning commission are appropriate and should be made a part of any major development permit issued by the County on this project. 91 That any permit issued by Rio Blanco County to the applicant should be onditioned upon the completion of the purchase of the plant, facilities. and water rights necessary to complete the portion of the project located in Garfield County, Colorado. NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS OF RIO BLANCO COUNTY that the application of American Soda LLP for a major development permit to be issued pursuant to the Rio Blanco County Major Development Permit Ordinance is approved subject to the terms and conditions set forth on Exhibit "A" attached hereto and incorporated herein by reference. PASSED, ADOPTED AND APPROVED this ...4r-4day of 1999. ATTEST; NANC R. AMI K Cie and Recorder Rio Blanco County 4 BOARD OF COUNTY COMMISSIONERS RIO BLANCO COUNTY By: 1/ E '. ILLINS a i. rim' nar-d, KIM A. COOK Commissioner DONALD L. DA IS Commissioner Page 1 EXHIBIT "A" 1) Noxious weeds as determined by Rio Blanco County's noxious weed list be adequately controlled in all disturbed areas and the entire lease site. 2) All straw, hay or mulch brought in off-site shall be certified noxious weed free. 3) All earth -moving equipment shall be washed before entering Rio Blanco County. All heavy equipment, including trucks and trailers, which have been off-road or otherwise have the potential to spread weed seeds, shall also be washed before entering Rio Blanco County. Equipment shall be washed after working in any identified noxious weed areas during construction within pipeline easements and mining areas. 4) All areas disturbed by initial construction or by maintenance within pipeline easements and mining areas will be restored to its pre - construction topography and revegetated in accordance with BLM or Soil Conservation District specifications where applicable, or, in the alternative, to the surface owner's specifications unless specifically waivered by Rio Blanco County. The Soil Conservation District and/or BLM shall be consulted regarding such revegetation. Revegetation efforts should continue until they are successful, as determined by the BLM, Soil Conservation District, or landowners, as applicable. 5) Topsoil shall be segregated to ensure its return to the top of the trench within all buried pipeline easements during construction or maintenance operations. 6) American Soda, L.L.P. shall comply with the stipulations in its Major Development Permit application and with all applicable local, state and federal requirements and will obtain all required permits. 7) Any required permits from the Bureau of Land Management for the project shall be obtained. 8) Any required permits from the Department of Army Corps of Engineers for any pipeline crossings of drainages shall be obtained. 9) American Soda, L.L.P. shall obtain the appropriate road access permits for all new access roads which connect to county and/or state roads. Page 2 EXHIBIT "A" 10) American Soda, L.L.P. shall obtain the appropriate permits for pipeline crossings or infringements onto county or state right-of-ways. 11) A tracer line or location device be placed adjacent to or in the trench of all buried nonmetallic pipelines to facilitate the location of such pipelines. 12) All buried pipelines shall be buried to a minimum depth of 48 inches within all road crossings, shoulders, or road right-of-ways and to a minimum depth of 36 inches in all other areas unless specifically waivered by Rio Blanco County. The pipelines shall be installed in a manner to prevent line floating and water migration when crossing streams, irrigation ditches, wetlands and irrigated fields. Any pipelines less than 4 feet below the bottom of an irrigation ditch shall be sleeved or otherwise protected. Documentation of sleeving or adequate depth of pipelines installed under irrigation ditches shall be kept by American Soda, L.L.P. and provided upon request. 13) Areas used for storing materials or equipment shall be located at least 50 feet from stream banks, wetlands, or irrigated fields where practical alternatives exist. 14) American Soda, L.L.P. shall be responsible for ensuring all subcontractors activities comply with the approved plans and conditions of the Major Development Permit. 15) The Rio Blanco County Sheriffs Office shall be contacted immediately during any emergency or hazardous waste spill. 16) American Soda, L.L.P. shall cooperate with other pipeline companies and the BLM within utility corridors to maintain an adequate separation between pipelines and to coordinate crossings and cathodic protection facilities where applicable. 17) All construction and operation procedures identified in and submitted with the Major Development Permit application shall be strictly followed. 18) This Major Development Permit shall expire 2 years from the date of issuance if substantial construction has not occurred. Page 3 EXHIBIT "A" 19) A truck with fire fighting capabilities shall be present when pipe cutting, welding, or other activities, which have the potential to start wildfires, are performed to minimize fire danger. 20) A water -quality monitoring plan shall be developed in cooperation with Rio Blanco County, the BLM, EPA, and other agencies, which addresses all issues to the satisfaction of Rio Blanco County. 21) A $1,500,000 performance bond be obtained for Rio Blanco County to cover road impacts during the construction of this project. 22) American Soda, L.L.P. acknowledges that County Road 83 is not winter maintained and that County Road 5, although winter maintained, does not have a 24-hour a day snow plowing effort and may be impassible to vehicles for periods of time during and after storm events. 23) American Soda, L.L.P. shall provide a plan for improvements for County Road 83 which includes all requested design and improvement changes determined to be acceptable to Rio Blanco County and consistent with agreements specified in a letter dated March 31, 1999 from American Soda, L.L.P. 24) No significant changes or additions to the submitted application shall be allowed without prior approval from Rio Blanco County or an approved amendment to the Major Development Permit. 25) Annual updates which summarize mining activities, workforce, tonnage of materials mined, etc. shall be submitted to Rio Blanco County. 26) This project shall be reviewed by the Rio Blanco County Planning Commission and Board of Commissioners at scheduled public meetings every five years to review for compliance with the approved plans and to identify potential issues with the project. 27) This Major Development Permit expires 30 -years from the date of issuance. 28) In the event of pipeline failure, produced materials shall not be trucked or otherwise transported without prior approval from Rio Blanco County. /6_ Page 4 EXHIBIT "A" 29) The approval of this Major Development Permit does not constitute or imply future approval of any pipelines, powerlines, building permits, etc. or any other associated facilities required for the operation of this project. 30) All representations of the applicant, either within the application or stated at public meetings, shall be considered conditions of approval. 31) Any data or representations submitted for this project to Rio Blanco County found to be substantially inaccurate, incorrect, or misleading shall be grounds for the revocation of this permit. 32) All pertinent data on impacts from the operation and maintenance of this project on county demographics, wildlife, air, and hydrologic environments must be submitted in an unbiased manner to the county and relevant agencies for annual review. Significant impacts should be reported immediately. 33) All present and future issues and requests of the Meeker Fire District be addressed in a manner satisfactory to Rio Blanco County. 34) This Major Development Permit approval is conditioned upon American Soda, L.L.P. satisfactorily meeting all fees and requirements to be determined by future negotiations with Rio Blanco County to satisfy Section 1200 of Rio Blanco County's Development Regulations. 35) American Soda, L.L.P. agrees to pay all taxes in a timely manner. This includes but is not limited to the use taxes due on construction materials. A use tax return shall be submitted on a monthly basis. American Soda, L.L.P. understands that they are subject to a Use Tax Audit to ensure compliance at any time. 36) American Soda, L.L.P. shall provide Rio Blanco County with solid waste estimates annually and will segregate wastes consistent with the letter dated March 31, 1999 from American Soda, L.L.P. Page 5 EXHIBIT "A" 37) Rio Blanco County will make arrangements with the U.S. Geological Survey to monitor water quality at American Soda's project site in Rio Blanco County at American Soda's expense. Any costs expended by Rio Blanco County to the Geological Survey to provide for said water quality monitoring shall be reimbursed by applicant to Rio Blanco County within thirty days after receipt of any statement from Rio Blanco County for said expenses. In the event the USGS provides an estimate of the yearly cost of said monitoring, American Soda shall deposit said amount with the Treasurer of Rio Blanco County to be used for that purpose prior to the start of construction of its project under this permit. 38) This permit is conditioned upon applicant completing its purchase of the plant facilities and water rights in Garfield County necessary to complete the Garfield County portion of the project. In the event said purchase is not completed, this permit shall be null and void. REQUEST: 1)16 1/0Q 6s/BOCC 113100 p PROJECT INFORMATION AND STAFF COMMENTS A request for review of a Special Use Permit to allow construction of pipelines for liquid sodium solutions and return water. APPLICANT] American Soda L.LP. and American Soda Pipeline Company LOCATION: A corridor starting approximately 2.5 miles north of Parachute and extending approximately 19 miles north in Garfield County along the Parachute Creek and West Parachute Creek drainage. SITE DATA: The pipeline would cover 19 miles, disturbing approximately 115 acres. ACCESS: Existing public and private roads EXISTING ZONING: Resource Lands (R/L) RELATIONSHIP TO THE COMPREHENSIVE PLAN The subject property is classified as unclassified lands in the 1984 Garfield County Comprehensive Plan. The following statements are from the Garfield County Comprehensive Plan Urban Area of Influence Policies, Comprehensive Plan Goals, Objectives and Policies applicable to this application: A. "Encourage industrial expansion where similar development already exists in appropriate areas, i.e. within or adjacent to platted industrial parks, within designated industrial zones in existing towns, or adjacent to existing similar development." B. "The County may deny development proposals on the basis of : 1.) Lack of access to the site; 2.) Inadequate road access which will create an inadequate road with large daily truck volumes; or, 3.) A road which is already at or above its design capacity and due to the terrain or geology of the area, cannot be further improved to safely accommodate additional daily traffic." 1 II. DESCRIPTION OF THE PROPOSAL A. Site & Project Description; The applicants are requesting a special use permit to allow the construction, maintenance and operation of sodium products and return water pipelines The lines will be placed adjacent to an existing natural gas pipelines in the northern portion of the Garfield County section, private land in the middle section of the Garfield County section and in an existing pipeline corridor for the initial nine(9) miles in Garfield County. Overall the pipeline is 44 miles long, with 19 miles in Garfield County and the remaining 25 miles in Rio Blanco County. The proposed pipeline begins at the American Soda processing site 2.5 miles north of Parachute. The pipelines will be placed on the west side of CR 215 for the first six (6) miles; then another 2.5 miles along the east side of CR 215; then J 0' another two miles north along the Middle Fork of Parachute Creek to the base of Davis Point; west up across Davis Point and then north along the side of the East Fork of Stewart Gulch into Rio Blanco County and continuing north to the mine site in the Piceance Basin in Rio Blanco County. The entire section of the pipelines in Garfield County are on privately owned lands. Approximately 20 miles of the pipelines in Rio Blanco County are on public lands. The pipelines will have a 12.75 inch outside diameter and 0.41 inch thick walls, except for the sections crossing Parachute Creek, which have 0.5 inch wall thickness. One of the pipelines will transport sodium carbonate solution from the nacolite and initial processing facility at the Piceance site in Rio Blanco County to the processing facility north of Parachute. The other pipeline will return recycled water from the Parachute site to the Piceance site for reuse. Large electrical turbines will provide the power necessary to create the pressure to move the solution and water along the corridor. To construct the pipeline, it will take around 125 ft. of right-of-way. Within the construction right-of-way the ditch will be 6 feet wide, with excavated ditch spoil placed in an area 29 ft. wide, ten feet for pipe storage; 40 ft. for truck and work area; and 40 ft. for a topsoil pile. Once the pipelines are installed, the permanent right-of-way will be 50 ft. in width. III. MAJOR ISSUES AND CONCERNS A. Right-of-way : The applicant has obtained the right-of-way for a portion of the corridor and entered in negotiations with the other landowners. If negotiations fail, the applicant's attorney has asserted that the company has the power of eminent domain and can acquire the necessary right-of-way through the appropriate court proceedings. 2 B. Road Crossings: County Road 215 is crossed one time by the pipelines. The applicants will need to get road cut permits from the County Road and Bridge Department, prior to construction to set any bonds, verify location of the crossing and existing road conditions. C. Regulations Pertaining to Industrial Operations. A pipeline is a Special Use in the Resource Lands zone district and is considered an industrial use.. Section 5.03 describes some basic requirements for a Special Use and 5.03.07 and 5.03.08 include a description of an impact statement and standards required as part of the SUP submittal for an industrial use. Section 5.03 of the Zoning Resolution sets forth the requirements that all special uses must meet, to wit: 1.) Utilities adequate to provide water and sanitation service based on accepted engineering standards and approved by the Environmental Health Officer shall either be in place or shall be constructed in conjunction with the proposed use; There are no utilities needed for the operation of the pipeline, except for those at the processing facility. During construction, drinking water will be brought onto the site and portable toilets will need to be brought to the site. 2.) Street improvements adequate to accommodate traffic volume generated by the proposed use and to provide safe, convenient access to the use shall either be in place or shall be constructed in conjunction with the proposed use; County Road 215 is the only public road to be used for the construction of the pipeline. The majority of the access will be via private roads along the pipeline corridor. There should be no conflicts with existing traffic, given that the majority of the traffic into the area is the applicant's traffic or the property owners. 3.) Design of the proposed use is organized to minimize impact on and from adjacent uses of land through installation of screen fences or landscape materials on the periphery of the Iot and by location of intensively utilized areas, access points, lighting and signs in such a manner as to protect established neighborhood character; All impacts to adjacent uses of land will be minimal and temporary during construction. Long term impacts should be nonexistent after the revegetation is completed and well established. 3 Section 5.03.07 requires that the impact statement shall show that the use shall be designed and operated in compliance with all applicable laws and regulations of the County, State and Federal Governments, and will not have a significant adverse effect upon: 1.) Existing lawful use of water through depletion or pollution of surface runoff, stream flow or ground water; Water for the project will come from the alluvial wells in Parachute Creek or from the water withdrawal facility on the Colorado River south of the Town of Parachute. Water will be used initially to hydrostatically test the pipeline. The amount of water in each line will be 1,560,000 gallons or a total of 3,120,000 gallons. The initial hydrostatic test will result in the release of the entire amount of water into Parachute Creek. Once the pipeline is in operation, there is minimal water loss due to the reuse of the water internally within the looped system. 2.) Use of adjacent land through the generation of vapor, dust, smoke, noise, glare or vibration, or other emanations; During construction there will a limited amount of emanations such as dust and noise on the site, but not to adjoining properties. After completion of the pipeline and the establishment of the revegetation program, there should be virtually no impacts on adjacent property. 3.) Wildlife and domestic animals through creation of hazardous attractions, alteration and existing native vegetation; There will the temporary displacement of wildlife during the construction of the pipeline. The mule deer population will be one of the affected species, but the construction is proposed to be during the seasons of the year that will be the least disrupting to the deer population. Some raptor and waterfowl habitat may be disturbed during construction. Special precautions will be taken if any raptor nests are identified during construction that are also active nesting sites. The procedures are identified in the application. There is also the potential to impact waterfowl nesting sites, but it should be minimal given the limited number of water crossings. Impacts to fish should be minimal given the limited stream size. 4.) Truck and automobile traffic to and from such uses shall not create hazards or nuisances to areas elsewhere in the County; As noted previously, access to the site is via CR 215 and private roads up to Davis Point. Access to the northern portion of the site is via BLM and private roads off of Rio Blanco CR 5. The application projects between 30 to 55 commuter trips per day and 15 to 20 truck trips to take material to the site. During the operation of the pipeline there would be twice annual inspections of the pipeline corridor. Overall, the traffic impacts to any other areas of the County are negligent and very minimal to CR 215. 5.) Sufficient distances shall separate such use from abutting property which might otherwise be damaged by operations of the proposed uses; The pipeline is being built on property that the applicant will have or have acquired a legal right to place it. All construction activity will be on the same property and there should be no impacts to abutting property during operation. 6.) Mitigation measures proposed for all of the foregoing impacts identified and for the standards identified in Section 5.03.08 of the Zoning Resolution. There are various mitigation measures proposed for the pipeline project. There are design features including extra thick walls for areas under creeks; steel sleeves around the pipeline in areas under county roads; posting of markers and waming signs along the corridor; and a four valve set along the corridor to allow for the closure of the pipeline in the event of a break. There will be technologically advanced metering and alarm system to monitor the pipeline for leaks and failures. A Spill Response plan has been prepared to set up containment and response measures in the event of a failure. 7.) A plan for site rehabilitation must be approved by the County Commissioners before a permit for conditional or special use will be issued; The application has a complete revegetation plan included in the application. The revegetation plan states that "certified weed free seed will be used whenever possible, and, in all cases, seed will be free of primary noxious weeds." The County has always required that all seed be certified weed free seed. The term "whenever possible" is to wide open from staffs point of view. 8.) The County Commissioners may require security before a permit for special or conditional use is issued, if required. The applicant shall furnish evidence of a bank commitment of credit, bond, certified check or other security deemed acceptable by the County Commissioners in the amount calculated by the County Commissioners to secure the execution of the site rehabilitation plan in workmanlike manner and in accordance with the specifications and construction schedule established or approved by the County Commissioners. Such commitments, bonds or check shall be payable to and held by the County Commissioners; Staff would suggest that the applicant's place a bond or letter of credit with the County for the cost of revegetation of the pipeline within Garfield County. An estimate of the cost of the revegetation plan needs to be submitted to the County and reviewed by the County Pest and Weed Director. The applicant should then be required to certify the revegetation being completed and the establishment of the plant materials. Section 5.03.08 requires that all industrial operations in the County shall comply with applicable County, State, and Federal regulations regulating water, air and noise pollution and shall not be conducted in a manner constituting a public nuisance or hazard. Operations shall be conducted in such a manner as to minimize heat, dust, smoke, vibration, glare and odor and all other undesirable environmental effects beyond the boundaries of the property in which such uses are located, in accord with the following standards; 1.) Volume of sound generated shall comply with the standards set forth in the Colorado Revised Statutes at the time any new application is made. The volume of sound generated by the construction will not exceed the limitations for industrial activities established by the State Statutes, given the remote location of the pipeline construction and the very limited amount of land uses that could be affected. 2) Vibration generated: every use shall be so operated that the ground vibration inherently and recurrently generated is not perceptible, without instruments, at any point of any boundary line of the property on which the use is located; All of the operational characteristics will not result in any vibration beyond the property boundaries given the pipelines will be located on the same property that adjoins the right-of-way. 3) Emissions of smoke and particulate matter: every use shall be operated so as to comply with all Federal, State and County air quality laws, regulations and standards; The only emanations of smoke or particulate matter that could occur would be during construction. Once the pipelines are placed, there should be no emanations form the pipelines since they will be underground. 4) Emission of heat, glare, radiation and fumes: every use shall be so operated that it does not emit heat, glare, radiation or fumes which substantially interfere with the existing use of adjoining property or which constitutes a public nuisance or hazard. Flaring of gases, aircraft warning signals, reflective painting of storage tanks, or other such operations which may be required by law as safety or air pollution control measures shall be exempted from this provision; The pipelines will not emit any heat, glare, radiation or fumes once the project is completed. During construction of the pipeline, there may be minimal emission of heat, glare and fumes as a part of the installation of the pipelines. 5.) Water pollution: in a case in which potential hazards exist, it shall be necessary to install safeguards designed to comply with the Regulations of the Environmental Protection Agency before operations of the facilities may begin. The water involved with the pipeline is not subject to any EPA regulations. D. Fiscal Impact Mitigation: Section 5.08 of the Garfield County Zoning Resolution requires any project that will employee 200 or more people at any one time during construction or operation to defined as a major project subject to the County Fiscal Impact Mitigation program. The applicants went through the pre - application process and were exempted from the fiscal impact regulations by Resolution No. 99-113, subject to meeting certain conditions of approval. Included in the application is an analysis of the available housing for the non -local construction workers and an analysis of local work force. (See Resolution pgs. /a ) The applicants have surveyed the available housing and based upon the projections in the report feel that the Parachute and Battlement Mesa areas can accommodate the non -local work force for the Parachute end of the applicant's project based on the survey and experience to date with housing employees. Additionally, they propose to have a newsletter developed for orientation of new workers that will have a current listing of available housing and it will be updated on a regular basis. Resolution No. 99-1 13 also required that the applicants enter into certain agreements with the Town of Parachute and the City of Rifle for additional service as a part of a mutual aid agreement. There is also supposed to be a plan for minimizing traffic in the Town of Parachute included with the application. There are no agreement from Rifle or a plan for minimizing traffic in the Town of Parachute included with the application. 7 E. Rio Blanco County SUP: Rio Blanco County has approved a Special Use permit for the mine and initial processing facility and the pipelines. (See Resolutions pgs. grn. 1;1— IV. 1 - IV. SUGGESTED FINDINGS 1. That proper posting and public notice was provided as required for the hearing before the Board of County Commissioners. 2. That the hearing before the Board of County Commissioners was extensive and complete, that all pertinent facts, matters and issues were submitted and that all interested parties were heard at that meeting. 3. That for the above stated and other reasons, the proposed Special Use Permit is in the best interest of the health, safety, morals, convenience, order, prosperity and welfare of the citizens of Garfield County. 4. That the application is in conformance with the Garfield County Zoning Resolution of 1978, as amended. V. RECOMMENDATION Staff recommends APPROVAL, with the following conditions of approval: 1. That all representations of the applicant, either within the application or stated at the hearing before the Board of County Commissioners, shall be considered conditions of approval. 2. All construction shall be in compliance with the application as submitted. 3. Prior to mobilization and/or construction, the applicant shall obtain approval of all proposed crossings of County Roads from the Garfield County Road and Bridge Department including appropriate notification of the public as may be necessary for road closures or other activities as required. 4. Prior to mobilization and/or construction, the applicant or the applicant's contractor(s) shall obtain overweight vehicle permits from the Garfield County Road and Bridge Department 5. The applicant shall obtain all Iicences as may be required for vehicles used by the applicant and the applicant's contractor(s) from the Garfield County Clerk and Recorder. 8 6. A copy of the Emergency Preparedness Plan shall be maintained in the Garfield County Emergency Preparedness Office and any revisions submitted as they are made in the future to ensure the plan is current. 7. Any violation of the terms, interpretations or agreements made or represented to Garfield County by the applicant pertaining to or included in this special use permit, shall be considered a breach of the terms of conditions and the applicant shall cease and desist all construction activities and forfeit any and all bond / monies as may be applicable to the County. . _ `^`' 641 �/1 8. All revegetation will be done with certified weed free seed/The applicant will be responsible for the removal of noxious weeds from the pipeline right-of-way for the life of the project. 9. An estimate of the cost of revegetation will be submitted to the County Pest and Weed Director for approval. A bond or letter of credit will be placed with the County in an amount determined to be adequate by the Pest and Weed Director for the cost of revegetation. The security will be released when a statement from a qualified specialist is received that certifies the reestablishment of the vegetation in accordance with the plan and the County Pest and Weed Director concurs with the statement. 10. The applicant shall maintain a current listing of available housing for non -local workers and present it to them at orientation or to the subcontractors management as they come into the area. 11. Prior to the issuance of the Special Use permit, the applicants shall submit a copy of the agreement with the City of Rifle to deal with possible additional calls for service, as a part of a mutual aid agreement with the Garfield County Sheriff for police service. r' to .� W/ ' �dZtJ Q� ,wit tric. 12. Thatplan for minimizing traffic to the Town of Parachute be submitted to the F� / County prior to the issuance of the Special Use permit. 13. That the applicant submit monthly housing and employment monitoring reports to the County. If the total workforce exceeds the employment workforce projected as apart of the application by ten percent (10%) or greater, the applicant is required to notify the Board of the effects of the increased work force and additional measures needed to accommodate the work force. 14. Any violation of or revocation of the Special Use permit issued by Rio Blanco County will result in a cease and desist of operations in Garfield County.