HomeMy WebLinkAbout4.0 Resolution 99-0661111:11111111111 111111111 111111111 I 111111 11111111
546855 06/08/1999 03:41P B1133 8 M ALSDORF
1 of 3 R 0.00 D 0.00 GARFIELD NTY CO
STATE OF COLORADO
)ss
County of Garfield
•
At a regular meeting of the Board of County Commissioners for Garfield County,
Colorado, held in the Commissioners' Meeting Room, Garfield County Courthouse, in Glenwood
Springs on Monday , the 7 "' day of June A.D. 199 9 there were present:
John Martin
Walter Stowe
Larry L. McCown
Don Deford
Mildred Alsdorf
Ed Green
, Commissioner Chairman
, Commissioner
, Commissioner
, County Attorney
, Clerk of the Board
, County Administrator
when the following proceedings, among others were had and done, to -wit:
RESOLUTION NO. 9 9- 0 6 6
A RESOLUTION CONCERNED WITH PLACEMENT OF A NATURAL GAS PIPELINE
FOR THE PUBLIC SERVICE COMPANY OF COLORADO
WHEREAS, the Board of County Commissioners of Garfield County, Colorado, has
received application from Public Service Company of Colorado to allow by special use,
placement of a natural gas pipeline for the corridor as identified in the site application;
WHEREAS, the Board held a public hearing on the Ird day of May 1999_,
upon the question of whether the above-described special use permit should be granted or denied,
at which hearing the public and interested persons were given the opportunity to express their
opinions regarding the special use permit; and
WHEREAS, the Board on the basis of substantial competent evidence produced at
the aforementioned hearing, has made the following determination of fact:
1. That proper publication and public notice was provided as required by law for the
hearing before the Board of County Commissioners.
2. That the hearing before the Board of County Commissioners was extensive and
complete, that all pertinent facts, matters and issues were submitted and that all
interested parties were heard at that hearing.
111V1 111111 1111111111111111111 '11111111111111
546855 06/08/1999 03:41P B1133 9 M ALSDORF
2 of 3 R 0.00 D 0.00 GARFIELD NTY CO
f
3. That the application is in compliance with the Garfield County Zoning Resolution
of 1978, as amended.
4. For the above stated and other reasons, the proposed use is in the best interest of
the health, safety, morals, convenience, order, prosperity and welfare of the
citizens of Garfield County.
NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of
Garfield County, Colorado, that the Special Use Permit be and hereby is approved to allow for
placement of a natural gas pipeline along the corridor as identified in the application, upon the
following specific conditions:
1. That all representations of the applicant, either within the application or stated at
the meeting before the Board of County Commissioners, shall be considered
conditions of approval.
2. All construction shall be in compliance with County standards, and all road
crossing pipeline depths shall be inspected by the County Road and Bridge
Department for compliance with County standards.
3. Prior to mobilization and/or construction, the applicant shall obtain approval of all
proposed crossings of County Roads from the Garfield County Road and Bridge
Department including appropriate notification of the public as may be necessary
for road closures or other activities as required.
4. Prior to mobilization and/or construction, the applicant or the applicant's
contractor(s) shall obtain overweight vehicle permits (if applicable) from the
Garfield County Road and Bridge Department
5. The applicant shall provide a pre -mobilization and/or construction survey, listing
existing road and proposed pipeline alignment conditions to the Garfield County
Building and Planning and Road and Bridge Departments.
6. The applicant shall obtain all licences as may be required for vehicles used by the
applicant and the applicant's contractor(s) from the Garfield County Clerk and
Recorder.
7. The applicant shall abide by all stipulations as may be required for revegetation by
the County Weed & Vegetation Manager.
8. The applicant shall provide to the County within 180 days of completion of the
pipeline, a detailed survey indicating the as -built alignment of the pipeline and
proof of ownership or rights to easement for the alignment.
9. The applicant shall obtain all required permits from the County for placement
within the County right of way.
!Ir's11 Illi! 11111111111111111111111"11111546855 06/08/1999 03 41P B1130 M ALSDORF
3 of 3 R 0.00 D 0.00 GARFIELD WUNTY CO
f
10. The applicant shall provide a road bond or other surety as may be required by the
County.
Dated this 7th day of June
ATTEST;,,
1-4'1-441)/
Clerk of the Board
Upon motion duly made and seconded the foregoing Reso tion w
, A.D. 19 99 .
GARFIELD COUNTY BOARD OF
COMMISSIONERS, GARFIELD
COUN OLORADO
hairman
following vote:
COMMISSIONER CHAIRMAN JOHN F_ MARTIN / ,Aye
COMMISSIONER LARRY L. MCCOWN
dopted b
the
COMMISSIONER WALTER A. STOWE
STATE OF COLORADO
)ss
County of Garfield
, Aye
, Aye
I, , County Clerk and ex -officio Clerk of the Board of
County Commissioners in and for the County and State aforesaid do hereby certify that the
annexed and foregoing Resolution is truly copied from the Records of the Proceeding of the
Board of County Commissioners for said Garfield County, now in my office.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal of said
County, at Glenwood Springs, this day of , A D 19
County Clerk and ex -officio Clerk of the Board of County Commissioners