HomeMy WebLinkAboutSoils & Foundation Investigation 8.22.07T CTLITHOMPSON
SOILS AND FOUNDATION INVESTIGATION
MILLER RESIDENCE
PARCEL 3, ROE SUBDIVISION
GARFIELD COUNTY, COLORADO
Prepared For:
MR. JOHN MILLER
405 Will Avenue
Rifle, CO 81650
Project No. GS05048-120
234 Center Drive I Glenwood Springs, Colorado 81601
Telephone: 970-945-2809 Fax: 970·945-7411
August 22, 2007
1
't
. ' ·~
TABLE OF CONTENTS
SCOPE 1
SUMMARY OF CONCLUSIONS 1
SITE CONDITIONS 2
PROPOSED CONSTRUCTION 2
SUBSURFACE CONDITIONS 2
SITE EARTHWORK 3
Excavations 3
Sub-Excavations 4
Fill and Backfill 5
FOUNDATIONS 5
Friction Piers 6
Footing Foundations on Structural Fill 7
FLOOR SYSTEM AND SLAB-ON-GRADE CONSTRUCTION 8
BELOW-GRADE CONSTRUCTION 9
SURFACE DRAINAGE 11
LIMITATIONS 12
FIGURE 1-APPROXIMATE LOCATIONS OF EXPLORATORY BORINGS
FIGURE 2 -SUMMARY LOGS OF EXPLORATORY BORINGS
FIGURES 3 AND 4-SWELL-CONSOLIDATION TEST RESULTS
FIGURES 5 AND 6 -EXTERIOR FOUNDATION WALL DRAINS
TABLE I -SUMMARY OF LABORATORY TEST RESULTS
JOHN MILLER
MILLER RESIDENCE
CTLIT PROJECT NO. GS05048·120
S:IGS05041.000\12012. Reporu\GS05D41120 RI.doc
..
SCOPE
This report presents the results of our soils and foundation investigation for
the proposed Miller Residence on Parcel 3 of the Roe Subdivision in Garfield County,
Colorado. We conducted the investigation to evaluate the subsurface conditions at
the site and provide geotechnical engineering recommendations for the proposed
construction. Our report was prepared from data developed from our exploratory
borings, laboratory testing, engineering analysis, and experience with similar
conditions. This report includes a description of the subsurface conditions found in
our exploratory borings drilled at the site and presents recommendations for design
and construction of foundations, floor systems, below-grade walls, subsurface
drains, and criteria for details influenced by the subsoils. A summary of our
conclusions is presented below.
SUMMARY OF CONCLUSIONS
1. Subsurface conditions encountered in our exploratory borings
consisted of 0.5 feet of sandy clay "topsoil" underlain by sandy clay to
the maximum explored depth of 30 feet below existing ground surface.
An approximately 3 foot lense of clayey gravel was encountered in our
exploratory boring TH-2 at an approximate depth of 9 feet below
existing ground surface. Laboratory test results and our experience
indicate the sandy clay under the subject parcel possesses potential
for moderate to high amounts of expansion when wetted under
foundation loads. Free ground water was not found in our exploratory
borings during drilling operations.
2. Differential heave and associated damage to foundations and floor
slabs is likely if the proposed residence is constructed directly on the
undisturbed, natural sandy clay. We recommend constructing the
residence on a drilled pier foundation that is below the probable depth
of wetting. A less positive alternative Is to construct the residence on
footing foundations supported on a minimum 3 foot thick layer of
structural fill. Design and construction criteria for drilled piers and
footings on structural fill are presented in the report.
3. In our opinion, lower level floors In living areas of the residence should
be structurally supported by the foundation system. We recommend
sub-excavation, moisture-treatment and recompaction of soils to a
JOHN MILLER
MILLER RESIDENCE
CTLIT PROJECT NO. GS05048·120
S:IGS05D48.0001120\2. RoportslGS05048 120 R1.doc
1
, '
depth of at least 2 feet below floor slabs in unfinished areas such as
the garage.
4. Surface drainage should be designed to provide for rapid removal of
surface water away from the proposed residence. A foundation drain
should be Installed around the basement
SITE CONDITIONS
The Roe Subdivision is a development located approximately 6 miles south of
Rifle on County Road 319 in Garfield County, Colorado. Parcel 3 ls In the western part
of the subdivision. Parcel 4, which is east of Parcel 3, is developed with a slngle-
family residence and a detached garage. Ground surfaces on the parcel slope down
to the south at grades between 5 and 1 O percent Vegetation on the parcel consisted
of sage brush and pine and juniper trees.
PROPOSED CONSTRUCTION
Building plans were not provided to us. We understand the residence will
likely be a two-story, wood.frame building ~ith a basement and an attached garage.
Maximum foundation excavation depths of about 10 to 12 feet are expected at the
uphill side of the building. Garage floors in similar residences in the area are typically
constructed as slabs-on-grade. We expect maximum foundation wall loads of about
3,000 pounds per lineal foot offoundation wall and maximum column loads of 30 kips.
If actual construction will differ significantly from the descriptions above, we should
be informed so that we can provide geotechnical input and revise our
recommendations, if necessary.
SUBSURFACE CONDITIONS
Subsurface conditions for the Miller Residence were investigated by drilling
two exploratory borings (TH-1 and TH-2) with a track-mounted drill rig at the
approximate locations shown on Figure 1. Drilling operations were directed by our
staff engineer who logged the soils encountered in the borings and obtained samples
JOHN MILLER
MILLER RESIDENCE
CTI.IT PROJECT NO. GS05048· 120
S :IOSOI041.000112012. RtponalGS05041120 R1 .doc
2
'I ·,
for testing in our laboratory. Graphic logs of the soils found in our exploratory
borings are shown on Figure 2.
Subsurface conditions encountered in our exploratory borings consisted of
about 0.5 feet of sandy clay "topsoil" underlain by sandy clay to the maximum
explored depth of 30 feet below existing ground surface. An approximately 3 foot
lense of clayey gravel was encountered in exploratory boring TH-2 at an approximate
depth of 9 feet below existing ground surface. Results of field penetration resistance
tests and our observations during drilling indicated thatthe gravel was dense and the
clay was very stiff. Free ground water was not found in our exploratory borings
during drilling operations.
Samples obtained in the field were returned to our laboratory where field
classifications were checked and samples were selected for pertinent testing. Three
samples of the natural sandy clay were selected for one-dimensional, swell-
consolldation testing. During the test procedure the samples were loaded with 1,000
psf and then flooded. The resulting volume change (i.e., swell or consolidation} was
then measured. The clay samples tested exhibited between 0.4 to 3.3 percent swell.
The samples were then loaded back to the original volume to determine the swell
pressures. Results of swell-consolidation testing are shown on Figures 3 and 4.
Laboratory test results are summarized on Table I.
SITE EARTHWORK
Excavations
We anticipate excavations for foundations and utilities at this site can be
accomplished using conventionalt heavy-duty excavation equipment Excavation
sides will need to be sloped or braced to meet local. state and federal safety
regulations. The natural, sandy clay will likely classify as a Type 8 soil, and the gravel
as a Type C soil based on OSHA standards governing excavations. Temporary slopes
deeper than 4 feet should be no steeper than 1 to 1 (horizontal to vertical} in Type B
JOHN MILLER
Mil.I.ER RESIDENCE
CTI..jT PROJECT NO. GS05048·120
S :\GSOI0'8.C00\12012. RoportalGSOS041120 R1.doc
3
. ,
soils and 1.5 to 1 in Type C soils. Contractors should identify the soils encountered in
excavations and refer to OSHA standards to determine appropriate slopes.
Contractors are responsible for proper site excavation and the maintenance and
safety of the excavations and overall site safety.
Free ground water was not found in our exploratory borings during this
investigation. We do not anticipate excavations for foundations or utilities will
penetrate ground water. Excessive wetting of the excavation should be avoided.
Excavations should be sloped such that water from precipitation can drain to a
positive gravity outfall or to a temporary sump where water can be removed by
pumping. Ground surfaces surrounding excavations should be sloped as much as
practical to direct runoff away from the excavations.
Sub-Excavation
Laboratory test results and our experience at the site indicate the natural,
sandy clay below the subject lot possess the potential for moderate to very high
amounts of expansion when wetted. Differential heave and associated damage to
floor slabs is likely if the slabs are constructed directly on the natural clays.
As discussed in the SLAB-ON-GRADE section, we recommend removal {i.e.
sub-excavation), moisture-treatment and recompaction of the soils below the floor
slabs in unfinished areas such as the garage. Sub-excavation should be to a depth of
at least 2 feet below the bottom of slabs. Sub-excavation of at least 12-inches would
enhance performance of exterior slabs. Sub-excavated areas below slabs should
extend laterally at least 1.5 feet beyond the perimeter of the slabs. The bottom of the
sub-excavated area should be scarified to a depth of at least 8 inches, moisture-
treated and compacted.
We recommend re-using the excavated soils for structural fill, provided they
are free of organics, debris and rocks larger than 4 inches In diameter. If import soils
are required for use as structural fill, they should be similar to the on-site soils.
JOHN MILLER
MILLER RESIDENCE
CTLIT PROJECT NO. GS05048-120
S:IGS050...000\12012. Repe>.UIGS06048 120 R1.tlo~
4
Structural fill should be moisture-treated to between 1 percent below and 3
percent above optimum moisture content and compacted to 98 percent of standard
Proctor (ASTM D 698) maximum dry density. Additional water required to increase the
existing soil moisture content to the specified moisture content should be uniformly
mixed into the fill soil prior to compaction. We recommend a maximum loose lift
thickness of 8 inches. The actual thickness of fill lift that can be properly compacted
will depend on the type of compaction equipment In order for the procedure to
perform properly, close control of structural fill placement to specifications is
required. Our representative should be called to check processing, compaction, and
moisture content of the structural fill during placement.
Fill and Backfill
Proper placement and compaction of fill and backfill adjacent to the building is
critical to prevent infiltration of surface water and wetting of the soils below the
building. The on-site soils free of organics, debris and rocks larger than 4 inches in
diameter can be used as fill and backfill. If import soil is required for fill and backfill, it
should have similar characteristics to the on-site soils. Fill and backfill outside the
building footprint should be placed in loose lifts of B inches thick or less, moisture
treated to between 1 percent below and 3 percent above optimum moisture content
and compacted to 95 percent of standard Proctor (ASTM D 698) maximum dry density.
We recommend that density and moisture content be checked during placement.
FOUNDATIONS
The natural sandy clay below the site possess potential for moderate to high
amounts of expansion when wetted under foundation loads. Differential heave is
likely if the Miller Residence is constructed directly on the undisturbed, natural clay
soil. We recommend constructing the Miller Residence on drilled pier foundations.
Piers concentrate building deadloads and anchor the foundation below the zone of
probable moisture variation to resist potential swelling pressures from the expansive
JOHN MILLER
MILLER RESIDENCE
CTllT PROJECT NO. GSOS048·120
S;IGSOS0,9,000\12012. R1parta\GS05Da 120 R1.dac
5
soil. A high degree of care will need to be taken to prevent wetting of the soils below
the residence.
A less positive foundation alternative is to construct the building on footing
foundations, provided the soils are sub-excavated to a depth of at least 3 feet below
footings, moisture-treated, and recompacted. We recommend reuse of the on-site
soils as structural fill. Recommendations for sub-excavation and structural fill
placement were provided in the Sub-excavation section. Recommended design and
construction criteria for friction piers and footing foundations are presented below.
Friction Piers
1. Piers should be designed for a maximum allowable end pressure of
8,000 psf and skin friction of 1,000 psf. Skin friction should be
neglected for the upper 3 feet of pier below grade beams.
2. Piers should be designed for a minimum deadload pressure of 10,000
psf based on pier cross-sectional area. If this deadload cannot be
achieved through the weight of the structure, the pier length should be
Increased beyond the minimum values specified In the next paragraph.
3. Piers should have a total length of at least 20 feet. The pier length
should not exceed about 30 times the pier diameter (we assume 10-inch
piers will be used).
4. Piers should be reinforced their full length with at least 2 No. 7 (22 mm),
Grade 60 (420 Mpa) reinforcing bars (or their equivalent) to resist
tension in the event of swelling. Reinforcement should extend into
grade beams and foundation walls.
5. There should be an 8-inch (or thicker) continuous void beneath all
grade beams and foundation walls, between piers, to concentrate the
deadload of the structure onto the piers.
6. Grade beams (If any) should be well reinforced. The reinforcement
should be designed by a qualified structural engineer. Lateral earth
pressures and the effects of large openings within basement walls
should be considered.
7.
JOHN MILLER
MILLER RESIDENCE
Piers should be carefully cleaned prior to placement of concrete. We
recommend a "drill-and-pour" procedure for pier installation. Concrete
should be ready on-site and placed in the pier holes immediately after
the holes are drilled, cleaned and observed by our representative to
6
CTLIT PROJECT NO . GS05048·120
S :IGSOSCMl.000112012. RoporulGS05041120 R1,doc
avoid collecting water and possible contamination of open pier holes. If
ground water is encountered during pier installation, temporary casing,
tremie equipment, and/or pumping may be necessary for proper
cleaning, dewatering, and concrete placement. Concrete should not be
placed by free fall if there is more than 3 inches of water at the bottom
of the hole.
8. Concrete placed in pier holes should have sufficient slump to fill the
pier hole and not hang on the reinforcement or the sides of the casing
during extraction (if used). We recommend a slump in the range of 5 to
7 inches.
9. Formation of mushrooms or enlargements at the top of piers should be
avoided during pier drilling and subsequent construction operations.
10. Installation of drilled piers should be observed by a representative of
our firm to Identify the proper bearing strata.
Footing Foundations on Structural Fill
1. Footing foundations should be supported by a minimum 3Mfoot
thickness of densely compacted, structural fill. Soil loosened during
the forming process should be removed or recompacted.
2. Footings on the structural fill should be designed for a maximum soil
bearing pressure of 3,000 psf.
3. Continuous wail footings should have a minimum width of at least 16
inches. Foundations for isolated columns should have minimum
dimensions of 24 inches by 24 inches. Larger sizes may be required,
depending upon foundation loads.
4. Grade beams and foundation walls should be well reinforced, top and
bottom, to span undisclosed loose or soft soil pockets. We
recommend reinforcement sufficient to span an unsupported distance
of at least 12 feet. Reinforcement should be designed by the structural
engineer.
5. The soils under exterior footings should be protected from freezing. We
recommend the bottom of footings be constructed at a depth of at least
36 inches below finished exterior grades. The Garfield County building
department should be consulted regarding frost protection
requirements.
JOHN MILLER
MILLER RESIDENCE
CTLIT PROJECT NO. GS05048·120
S :IGSOS048.00Dl1 ~Oil. R1porta\GSIJ$04B 120R1.doc:
7
·.
FLOOR SYSTEMS AND SLAB-ON-GRADE CONSTRUCTION
Expansive natural sandy clay soils are present at or near anticipated floor
elevations. The expansive clay soil is stable at existing moisture contents, but upon
wetting will heave lightly loaded slabs. This heaving cannot be controlled by
concentrating slab loads. Some increase in moisture must be assumed because of
the impact of residential construction and associated landscaping. The best current
method to limit the potential floor heave, to our knowledge, is the construction of a
structural floor with an air space between the floor and the subgrade soils. The
required air space depends on materials used to construct the floor and local building
codes. The air space should Include at least 8 inches for potential heave of expansive
soils. The structural floor is supported by the foundation system. There are design
and construction issues associated with structural floors, such as ventilation and
increased lateral loads, which must be considered. In our opinion, structural floors
should be used in all finished living areas in the proposed Miller Residence.
Structural floors are not normally used in garage areas of similar residences In
the area. Driveways, sidewalks and exterior patio slabs are also constructed as
slabs-on-grade. Performance of slabs-on-grade on expansive soils is erratic. Various
properties of the soils and environmental conditions influence magnitude of
movement and other performance characteristics of slabs supported by expansive
soils. Increases in the moisture content in expansive soils will cause heaving and
may cause cracking of slabs-on-grade. We believe these movements are most likely
in the first 3 to 5 years following construction as the soils respond to changes in
availability of moisture.
A less positive approach would be to construct the lower level floors as slabs-
on-grade supported by a minimum 2 foot thick layer of structural fill. Guidelines for
structural fill placement provided in the Sub-Excavation section should be followed.
To enhance performance, we recommend sub-excavation, moisture~treatment,
and recompaction of the soils to a depth of at least 2 feet below floor slabs in
JOHN MILLER
MILLER RESIDENCE
CTLl'f PROJECT NO. GSOS048·120
S:\GSD5D41.0D0\120U. Reparta\GSD5D48 120 R1.cto;
8
unfinished areas such as the garage. We recommend a sub-excavation process to a
depth at least 12 inches below exterior slabs. Recommendations in the Sub-
Excavation section should be followed. The recommendations in the SURFACE
DRAINAGE section will be critical to reduce potential for wetting of the subsoils below
slabs.
We recommend the following precautions for slab-on-grade construction at
this site. These precautions will not prevent movement from occurring; rather. they
tend to reduce damage if slab movement occurs.
1. We recommend against placing a sand or gravel layer below slabs.
Provision of a sand or gravel layer below slabs increases the possibility
of a single source of water wetting the entire area supporting the slab.
2. Slabs should be separated from exterior walls and interior bearing
members with slip joints which allow free vertical movement of the
slabs.
3. Underslab plumbing should be pressure tested before the slab is
constructed. Plumbing and utilities which pass through slabs should
be isolated from the slab with sleeves and be constructed with flexible
connections to slab supported appliances. Heating and air
conditioning systems supported by slabs should be provided with
flexible connections capable of at least 2 inches of vertical movement
so that slab movement is not transmitted to the duct work.
4. Exterior patio and porch slabs should be isolated from the residence.
These slabs should be well-reinforced to function as independent units.
Movements of these slabs should not be transmitted to the residence
foundation.
5. Frequent control joints should be provided, in accordance with
American Concrete Institute (ACI} recommendations, to reduce
problems associated with shrinkage and curling. Our experience
indicates panels which are approximately square generally perform
better than rectangular areas.
BELOW~GRADE CONSTRUCTION
Foundation walls which extend below-grade should be designed for lateral
earth pressures where backfill is not present to about the same extent on both sides
JOHN MILLER
MILLER RESIDENCE
CTLIT PROJECT NO. GS05048-120
5:1G5D5D41.DOD\12Dl2. R•pons\GS05D4112D R1.doc
9
_..
of the wall. Many factors affect the values of the design lateral earth pressure. These
factors include, but are not limited to, the type, compaction, slope and drainage of the
backfill, and the rigidity of the wall against rotation and deflection. For a very rigid
wall where negligible or very little deflection will occur, an "at-restu lateral earth
pressure should be used In design. For walls which can deflect or rotate 0.5 to 1
percent of wall height (depending upon the backfill types}, lower,.active" lateral earth
pressures are appropriate. Our experience indicates typical below-grade walls in
residences deflect or rotate slightly under normal design loads, and that this
deflection results in satisfactory wall performance. Thus, the earth pressures on the
walls will likely be between the "active" and "at-rest" conditions.
If on-site soils or similar soils are used as backfill, we recommend design of
below-grade walls using an equivalent fluid density of at least 50 pcf for this site.
This equivalent density does not include allowances for sloping backfill, surcharges
or hydrostatic pressures. Backfill placed adjacent to foundation wall exteriors should
be placed and compacted as outlined in the Fill and Backfill section.
Water from precipitation, snow melt and surface irrigation of lawns and
landscaping frequently flows through relatively permeable backfill placed adjacent to
a residence and collects on the surface ofrelatively undisturbed soils atthe bottom of
the excavation. This can cause wetting of soils below the building, hydrostatic
pressure on below-grade walls, and moist conditions in below-grade areas after
construction. To mitigate these concerns, we recommend provision of a foundation
drain around the residence. The drain should consist of a 4-inch diameter, slotted
PVC pipe encased in free draining gravel. The drain should lead to a positive gravity
outfall or a sump pit where water can be removed by pumping. Typical foundation
drain details are shown on Figures 5 and 6.
Ventilation is important to maintain acceptable humidity levels in crawl spaces.
The mechanical systems designer should consider the humidity and temperature of
air, and air flow volumes, during design of crawl space ventilation systems. We
JOHN MILLER
MILLER RESIDENCE
CTLIT PROJECT NO. GS05048·120
S:\GS05041.000\1ZOl2. Raporta1GS050'4a 1ZD Rt.doc
10
believe it is appropriate to install a ventilation system that is controlled by a
humidistat.
SURFACE DRAINAGE
Surface drainage is critical to the performance of foundations, floor slabs and
concrete flatwork. We recommend the following precautions be observed during
construction and maintained at all times after the Miller Residence is completed:
1. The ground surface surrounding the exterior of the residence should
be sloped to drain away from the building in all directions. We
recommend providing a slope of at least 6 inches in the first 5 feet
around the building in landscaped areas.
2. Backfill adjacent to foundation wall exteriors should be placed and
compacted as described in the Fill and Backfill section. Increasing the
moisture content of backfill soil after placement often results in
additional settlement of the backfill. This settlement is most common
adjacent to north facing walls.
3. The residence should be provided with gutters and downspouts. Roof
downspouts and drains should discharge well beyond the limits of all
backfill. Splash blocks and downspout extensions should be provided
at all discharge points. Water from roof and surface runoff should not
be introduced to the foundation drain system.
4. Landscaping should be carefully designed to mm1m1ze irrigation.
Plants used near foundation walls should be limited to those with low
moisture requirements; irrigated grass or other landscaping requiring
comparatively large amounts of irrigation should not be located within
5 feet of the foundation. Sprinklers should be at least 5 feet from
building foundations and directed away from the building. Irrigation
should be limited to the minimum amount sufficient to maintain
vegetation; the application of additional water will increase the
likelihood of slab and foundation movements.
5. Impervious plastic membranes should not be used to cover the ground
surface immediately surrounding the residence. These membranes
tend to trap moisture and prevent normal evaporation from occurring.
Geotextile fabrics can be used to control weed growth and allow some
evaporation to occur.
JOHN MILLER
MILLER RESIDENCE
CTLIT PROJECT NO. GSD5048·120
S:\GS05048.000\120U. Repons\GS05048 120 RI.doc
11
LIMITATIONS
Our exploratory borings were located to obtain a reasonably accurate picture
of the subsurface. Variations in the subsurface conditions not Indicated by our
exploratory borings will occur. A representative of our firm should observe the sub-
excavation process and installation of drilled piers.
This investigation was conducted in a manner consistent with that level of care
and skill ordinarily exercised by geotechnical engineers currently practicing under
similar conditions in the locality of this project. No warranty, express or implied, is
made. If we can be of further service or if you have questions regarding this report,
please call.
CTL I THOMPSON, INC.
Edward R. White, E.I.
Staff Engineer
Reviewed by:
John Mechling, P.E.
Branch Manager
ERW:JM:cd
(5 copies sent)
JOHN MILlER
MILLER RESIDENCE
CTLIT PROJECT NO. GS05048-120
S:IGS05041.QDlll1 iDli. R•pon.IGS0504& 120 R1.doc
12
;
6CAI.£: , •• 200'
JannMI ... --Protect No. GS05048-1:ZO
''I ~ -
I I ~ARCEL 1
70.00IJ Gi;;nlll
I 1 · '\ lVC:,. -~ -l-. . ~-· """'-' -~
I
l '·· r.1·&t1· ' ' . I: °:."7 //·""] -. : . * -· , .. _,,,. ,,,.,,, ... ,"
--c::-·~~--<~· -...--:::--f ~-;_:...~:--<> -· --• ·-' :-.::-1,>;.<:•:1 . ..-· •••. -• ' .. C.! ' . · .... \. ". ,,,
.:. ~: .--,.;.)N-L"\C:. -·-• ·~\ • n·11<;,1: .... ,.;!'' .m -' I ' t >'· t.P!ILU ~<.!..l.ICl.llf M-
ropOS•d o.., IT•"':"'-1~'
u.~·, .. ·r~ ... 111k!:
Cl"A.tr"P• 1
'' 'S ::..t-u
fZ
T'.
,,.
~~
;)o -(",
Ul D ..... -~ ,.,
~
~1
4'J
E
ill -
':
1!:.J..:
,~=·
u AA..-.. ::AP
'.
, '~. j i
.l ...
.1,~···
' ..
·~ .~
' ' '·:·· .. . -... .
:r,
,. . .. >·~
··~/' ~·
~·,.,
• , "' •• p I ?.
PARCEL l
IJAt()g
.'\ '. '\ . '
Bulldlng Sit•
.IO.IAL.ARtA
i 39.51 J OC"t'e!I
(4'..,,.t.Ml~
·.-.r.u.1<'~ 1.1 .. "1'.:t ~: !Jn~ rr• '' lil~Jt.(Tt:'i 1.1t ':."' C.'-.! •. rt.t(NI
PARCEL 4'
10~~ ~ ~if~
... ~h, .. ~ .... ~. ~~--'° -~~...._~~.·;, ':v~.;
'•"""' ·,· _ _, .~
.
"'':~. · .. ·. , ... i~·5: .-l
. ,... --. .. -• • r/I: ~.lHt.'oi: • •::.:i:~ ....... t)lt .. 4'1
P•~-t:v r "'T ·'-t:r " "'· r .:·;;.-~~
. •_'.:-.. :.~\·-.. ::. . ..
~) \' ... '"· '-
""""''t:• ..... lO:(
~·?r~:r·n:.
\.~' .......... \:. ,,,~ .... ,. ,·--:'.,J e .. ~~~~
s.
seg-~·50"\
~ ...
~
~
°' ~
T
Approximate
Location of
Exploratory
Borings
Fig.
TH-1 TH-2 LEGEND: ¥
0 ~ = 0 --, § Sandy, clay •top1011•, organics,
mollt, brown.
~ Clay, eandy, very stiff, moist, brown,
5 "~27/12 ~~ 5 -3 tan. (CL)
t3 Gravel, clayey, den .. , molat, tan.
(GC)
_J
10 [; .... tfW-1"2/12 10 p Drive sample. The symbol 27/12
Indicate• that 27 blow• of a 140
pound hamm•r falllng 30 Inch••
r. 'j-J 39/ 12 ~ +J2a/12 .. ~I
we,.. ,..qulr.d to dme a 2,5 Inch
15 O.D. Callfomla aamplar 12 lnchH.
S' HO TES:
20 ~ ~47/12 ~1 20 ..:Ji 1. Exploratory bor1ng1 we,.. drllltd on
Augult 2, 2007 with 4-lnch
dlamater, eond-ltem ouger and a
traok-mauntad drlll rig. Exploratory
boring• we,.. bockftued lmmtdlattly
25 ~A ~22/12 25 -I affar drilling op1raffona .,,..
completed.
2. Locations of exploratory borings
shown on Rgu,.. 1 a,.. approximate.
30 ~23/12 30 ...:i 3. Ha free ground water was found In
our exploratory boring• at the time
of drllllng.
... Th111 exploratory boring• are
1ubject to th• explonatlona,
35 35 _. llmltatlona and conclualan1 aa
contalnad In thl1 report.
SUMMARY LOGS OF EXPLORATORY BORINGS
Project No. GS050"8-120 J1i. 2
...
•
II
5
3
2
0
-1
·2
·3
EXPANSION UNDER CONSTANT
PRESSURE DUE TO WETTING
~------------------------------------------------------------------~ 0.1
APPLIED PRESSURE -KSF
Sample of CLAY, SANDY (CL)
From TH-1 AT 4 FEET
JOHN MILLER
MILLER RESIDENCE
PROJECT NO. GS05048-120
10
J:ILAB. TEMPLA T1!51To be Releaud\SWEU.-Wllh Prueurea2..sla
10
ORY UNIT WEIGHT=
MOISTURE CONTENT::
100
98 PCF
10.3 %
Swell Consolidation
Test Results
FIG.3
..
J
3...-~~------------------------------------~---------------------
1 EXPANSION UNDER CONSTANT _---+--11 _PRESSURE DUE TO WETIING
,_1JU I I I I I 111_""
~1 _1 I l_L ___ --------·:-:---1 -1--:--
2
z 0 a en z < Q. 1 x w
~
z ·2 a
, Li . I -r-11 r"I
en
ti) w
0:: .3
Q.
:::E
0
0
0 1 1 0
APPLIED PRESSURE • KSF
sample of CLAY, SANDY (CL)
From TH-1 AT 14 FEET
I I
I
10
ORY UNIT WEIGHT•
MOISTURE CONTENT•
100
112 PCF
6.0 %
------------EXPANSION UNDER CONSTANT
c::::: -PRESSURE DUE TO WETIING
z 0 o.-__ _
en z < Q. >< -1
w
z 0 ·2
Ui
ti)
w
0:: Q. -3
:::E
0
0
~-----------------------------------------------------------------01 1 0
APPLIED PRESSURE -KSF
Sample of CLAY, SANDY (CL)
From TH-2 AT 14 FEET
JOHN MILLER
MILLER RESIDENCE
PROJECT NO. GS05048-t20
J :\LAD. TEMPl..ATES\To be AolHMll\SWEl.L-Wllh P-.urn2.llla
10
ORY UNIT WEIGHT=
MOISTURE CONTENT•
10 0
120 PCF
135 %
Swell Consolidation
Test Results
FIG .4
{
SLOPE
PER REPORT
..............•.. ................. ................. ··············•·· ................. ................. .................. ................. .................
NOTE:
DRAIN SHOULD BE AT LEAST 4 INCHES
BELOW BOTTOM OF FOOTING AT 11-IE
HIGHEST POINT AND SLOPE DOWNWARD
TO A POSITIVE GRAVITY Oun.ET OR TO
A SUMP WHERE WATER CAN BE
REMOVED BY PUMPING.
ml'ACllDN PER REPCIRI) ·:~·:·:::··-::·:.-:-::·:~
COVER GRAVEL wmf
FlLlER FABRIC.
ENCASE PIPE JN WASHED CONCRETE
AGGREGATE (ASlM C3J, NO. 57 OR
NO. 67). EXTEND GRAVEL TO TOP
OF VOID.
4-INCH DIAMETER PERFORATED DRAJN
PIPE. 11-IE PIPE SHOULD BE PLACED
IN A lRENCH Wmt A SLOPE RANGING
BETWEEN 1/8 INCH AND 1/4 INCH
DROP PER FOOT OF DRAIN.
Project No. GS05048-120
--nt~1 ~--BELOW GRADE WALL
REINFORCING STEEL PER
STRUCTURAL DRAWINGS
PROVIDE POSITIVE SUP JOINT
BElWEEN SL.AB AND WALL
FLOOR SL.AB
._ __ DRIUED PIER
PROVIDE PVC SHEETING
GLUED TO FOUNDATION
WALL TO REDUCE MOISTURE
PENETRATION
Exterior
Foundation
Wall Drain
Fig. 5
•'
SLOPE
PER REPORT
I
" BACKFILL~ (COUPOSmON AND
COMPACTION PER REPORTJ
BELOW GRADE WALL
COVER GRAVEL Wmt
ALTER FABRIC
ENCASE PIPE IN WASHED CONCRETE
AGGREGATE (ASTM C33, NO. 57 OR
NO. 67). EXTEND GRAVEL TO TOP
OF VOID.
PROVIDE PVC SHEETING
GLUED TO FOUNDATION
WALL TO REDUCE MOISTURE
PENETRATION.
Project No. GS05048-120
................. ................ , ................. ................. ................. ....••........... ................. ................. ................. •..•............. ................. ................. ................. ................. ................. .................
NOTE:
DRAIN SHOULD BE AT LEAST 4 INCHES
BELOW 801TOM OF VOID AT THE HIGHEST
POINT AND SLOPE DOWNWARD TO A
POSmvE GRAVllY OUTLET OR TO A SUMP
WHERE WAlER CAN BE REMOVED BV
PUMPING.
STRUCTURALLY SUPPORTED
FLOOR SYSTEM
CRAWL
SPACE '""
OR \
VOID
REINFORCING STEEL PER
STRUCTURAL DRAWINGS
VOID
•----DRIUED PIER
4-INCH DIAMETER PERFORATED DRAIN
PIPE. THE PIPE SHOULD BE PLACED
IN A TRENCH WITH A SLOPE RANGING
BETWEEN 1/8-INCH AND 1/4-INCH
DROP PER FOOT OF DRAIN.
Exterior
Foundation
Wall Drain
Flg.6
MOISTURE DRY
DEPTH CONTENT DENSITY
LOT CFEET) (%) (PCF)
TH-1 4 10.3 98
TH-1 14 6 .0 112
TH-2 9 7 .3 114
TH-2 14 13.5 120
TABLE I
SUMMARY OF LABORATORY TESTING
PROJECT NO. GS05048-120
A TIER BERG LIMITS SWELL TEST RESULTS" PASSING
LIQUID PLASTICITY SWELL NO. 200
LIMIT INDEX SWELL PRESSURE SIEVE
(%) (%) (%) CPSF) (%)
0 .5
0.4
16
3.3
SOLUBLE
SULFATES
(o/o)
•SWELL MEASURED WITH 1000 PSF APPLIED PRESSURE, OR ESTIMATED IN-SITU OVERBURDEN PRESSURE.
NEGATIVE VALUE INDICATES COMPRESSION.
....
~
DESCRIPTION
CLAY, SANDY (CL)
CLAY, SANDY lCL)
GRAVEL, CLAYEY <GC)
CLAY, SANDY <CL)
Page 1 of 1