HomeMy WebLinkAboutEmail CorrespondenceJim Wilson
From: Brad Keller [BKeller@fciol.com]
Sent: Friday, January 24, 2014 9:57 AM
To: • Andy Schwalier; Matt Provost; Jim Wilson
Cc: Doug Swann; Steve Jones; Darrin Case
Subject: 10-12-031 - Clinic West - Permit Closeout
Attachments: Back Flow Preventer Certifications.pdf; Boiler Inspection Certificates.pdf; Chlorine Bacteria
Water Test.pdf; Electrical Coordination Study.PDF; Fire Flush Tests.pdf; PR-007.pdf; RFI -143
Fireplace Combustion Air.pdf
Andy,
As a follow up to our conversations, and some of the conversations had between Jim and Doug on site, I offer the
following regarding closeout of the Permit for the Clinic West Project at 201 Sipprelle in Battlement Mesa, Colorado:
1. Regarding re -vegetation, due to the cold winter conditions, we will resume landscape operations in the spring,
as soon as weather permits. To date, we have installed most of the irrigation system, graded and added topsoil
and placed landscape boulders. Work in the spring will include finalizing the irrigation system, touching up final
grading and placing plantings, turf and mulch. Until the work is complete, FCI will keep the Storm Water Permit
open with the State, and will keep BMP's in place and monitor.
2. Regarding systems, as of this writing, all systems in the facility are complete and operational. We have received
final Boiler inspections, Final Elevator Inspections, Generator Start up, Mechanical Systems Start ups etc... Over
the next month, we will be balancing the system and the owner will be utilizing a private, 3`d party to verify this
process. If so desired, we can produce copies of these reports to the county, albeit we don't usually get these
requests from Building Officials, as it is not part of the IBC.
3. Finally, I have attached copies of the following:
a. Electrical Coordination study from Eaton
b. Fire Flush Inspection
c. State Boiler Inspections
d. Backflow Preventer Tests
e. Bacteria / Water Tests
f. RFI regarding Combustion Air
g. PR regarding change to Fire Lite
I want to thank you guys for all the help you've provided over the duration of this project, and look forward to a smooth
close out. If there are any additional concerns please feel free to contact me directly.
Regards.
Bradford M. Keller
Project Manager
P. (970) 434-9093 / F. (970) 434-7583
C. (970)260-5130
FCI
Constructer Inc.
1
Jim Wilson
From: Brad Keller [BKeller@fciol.com]
Sent: Wednesday, January 29, 2014 7:53 AM
To: Andy Schwaller; Matt Provost; Jim Wilson
Cc: Doug Swann; Darrin Case; Steve Jones
Subject: FW: 2246-001 Battlement Mesa MOB
Attachments: 2246-001-isp-01-28-14.pdf
Gentlemen,
believe Landmark will be getting you an original Mylar, but in the meantime, I thought I'd forward for your use.
Regards.
Bradford M. Keller
Project Manager
P. (970) 434-9093 / F. (970) 434-7583
C. (970)260-5130
-PCI
Conitni tati,tam
From: Doug Swann
Sent: Tuesday, January 28, 2014 4:17 PM
To: Brad Keller
Cc: Darrin Case
Subject: FW: 2246-001 Battlement Mesa MOB
FYI
From: Jeff Gustafson[mailto:jeffg@Mandmark-co.com]
Sent: Tuesday, January 28, 2014 3:37 PM
To: Doug Swann; Steve Jones
Subject: 2246-001 Battlement Mesa MOB
Gentlemen:
Here is the Improvement Survey Plat. My plan is to get a mylar to the county and have it filed. They will then scan it and
I can have them send me a copy with the filing information on it. I can then forward you a record copy as well as any
number of hard copies.
Please let me know if you have any questions or comments so I can address them and revise the survey before filing if
necessary.
Thanks,
Jeff
Jeff Gustafson, P.L.S. 1 Landmark Consultants, Inc
p: 970-871-9494 ext 4
m: 970-819-4762
e: jeffg a(�landmark-co.com
Jim Wilson
From: Brad Keller [BKeller@fciol.com]
Sent: Thursday, January 30, 2014 4:29 PM
To: Andy Schwaller; Matt Provost; Jim Wilson
Cc: Doug Swann; Darrin Case; Steve Jones
Subject: FW: Battlement medical center
Gentlemen,
This is what we received from GarCo road and bridge. Let me know if this is sufficient.
Regards.
Bradford M. Keller
Project Manager
P. (970) 434-9093 / F. (970) 434-7583
C. (970)260-5130
• FC
c-0n.lcuctazL,lae
From: Dan Goin [mailto:dgoin@garfield-county.com]
Sent: Thursday, January 30, 2014 3:42 PM
To: Doug Swann
Cc: Rayjean Kramer
Subject: Battlement medical center
Doug,
After inspection of the driveway at the medical center it passed inspection per the permit requirements, and u are
agreed to remove the construction driveway repair any curb damage and finish pouring sidewalk where this driveway is.
If u need anything else or have any questions please call.
Thanks
Dan
1
Jim Wilson
From: Rob Ferguson [opschief@gvfpd.org]
Sent: Tuesday, January 28, 2014 3:43 PM
To: Jim Wilson
Subject: Battlement Mesa MOB
Jim,
The Final Fire Inspection is complete at 201 Sipprelle Dr., Parachute, CO. The Fire District has no objections
allowing the building to be approved for occupancy from this fire side. Please let me know if you have any other
questions.
Rob Ferguson
Deputy Fire Chief
Grand Valley Fire Protection District
0124 Stone Quarry Road
Parachute, CO 81635
Office 970-285-9119
Fax 970-285-9748
opschief@gyfod.org