HomeMy WebLinkAboutConditions of PermitCONDITIONS OF PERMIT BLCO-11-13-3049 EnCana/Hunter Ridge Energy LACT Bldg #1, J-25 CDP Parachute, Colorado 1) WORK PERFORMED WITHOUT PERMIT. ALL WORK MUST COMPLY WITH THE 2009 IBC AND MANUFACTURERS SPECIFICATIONS. 2) ALL WORK MUST COMPLY WITH STATE AND FEDERAL REGULATIONS. 3) ALL WORK MUST COMPLY WITH THE CONDITIONS OF THE CURRENT LAND USE PERMIT. 4) ENGINEER SHALL BE ON SITE DURING PIER, PILE, OR CAISSON INSTALLATION. PROVIDE APPROVAL REPORT AT FINAL INSPECTION. 5) ALL HIGH STRENGTH BOLTING AND FIELD WELDING REQUIRES SPECIAL INSPECTOR. PROVIDE APPROVAL REPORT AT FINAL INSPECTION 5) VERIFY STRUCTURE IS INSPECTED AND FACTORY BUILD LABEL AFFIXED. (C.D.O.H.) 7) ELECTRICAL FINAL APPROVAL IS REQUIRED FOR FINAL INSPECTION. 8) LIGHT AND VENTILATION PER 2009 IBC, CHAPTER 12. 9) LOCKS, LATCHES AND LANDINGS PER 2009 IBC, SECTION 1008. 10) GARFIELD COUNTY FINAL INSPECTION REQUIRED FOR COMPLETION APPROVAL. ir/QE- cop/