HomeMy WebLinkAbout3.0 CorrespondenceDavid Pesnichak
From: Megan O'Brien <megan@thekiernancompanies.com>
Sent: Wednesday, September 16, 2015 11:32 AM
To: David Pesnichak
Cc: Davis Farrar; David H. McConaughy; Kevin Kiernan
Subject: FW: CLH - FedEx Land Use Permit Expiration
David,
You can go ahead and archive the application, we will not be requesting an extension. Thank you for checking with us
first.
Thank you,
Megan
Megan OBrien
KiernanWest, LLC
PO Box 979
Telluride, CO 81435-0979
402-201-6922 cell
For FedEx deliveries please use the following address:
118 Lost Creek Lane
Telluride, CO 81435
From: David Pesnichak [mailto:dpesnichak@garfield-county.com]
Sent: Wednesday, September 16, 2015 7:55 AM
To: 'wsconsulting@sopris.net' <wsconsulting@sopris.net>; Kevin Kiernan <kevin@thekiernancompanies.com>; David
McConaughy <dmcconaughy@garfieldhecht.com>
Subject: CLH - FedEx Land Use Permit Expiration
Hi Davis, Kevin and David,
The 1 year expiration to complete the Conditions of Approval passed yesterday (9/14) for the proposed CLH property
FedEx facility. I am assuming it is OK with you if I mark this application officially expired and archive the application. If
you would like to request an extension to comply with the Conditions of Approval, however, please let me know by the
end of day today.
Thanks,
Dave
David Pesnichak, AICP
Senior Planner
Garfield County
Community Development Department
108 8th St Suite 401
Glenwood Springs, CO 81601
(970) 945-8212
1
GLENWOOD SPRINGS OFFICE
The Denver Center
420 Seventh Street, Suite 100
Glenwood Springs, Colorado 81601
Telephone (970) 947-1936
Facsimile (970) 947-1937
GARFIELD & HECHT, P.C.
ATTORNEYS AT LAW
Since 1975
www.garfieldhecht.com
September 5, 2014
VIA US MAIL AND EMAIL
David Pesnichak, Senior Planner
Garfield County Planning Division
108 8th Street, Suie 401
Glenwood Springs, CO 81601
dpesnichak@garfield-county.com
Re: FedEx Facility
Dear David:
David McConaughy
dmcconaughy@garfieldhecht.com
Thank you for your detailed staff report and for meeting with us earlier this week
regarding the upcoming hearing with the Board of County Commissioners. As we discussed, our
client is generally okay with the proposed conditions of approval but would request that the
Board consider the following changes. Several of these requests relate to timing issues and the
fact that our client's real estate contract with the current owner is contingent upon issuance of the
land use permit. As such, for example, our client cannot grant an easement until it holds title to
the property, which will not happen until after issuance of the land use permit. Accordingly, we
have proposed making some of these conditions triggered after the land use permit when our
client will have ownership and control of the property.
Condition 7. Please revise to clarify the proposal is for operations 7 days per week, 24 hours per
day (not just Mon -Sat).
Condition 16. Please consider making this a condition of building permit, not the land use
permit.
Condition 18. Please consider making this a condition of building permit.
Condition 20. At the hearing, the applicant will address the issue of traffic impacts generally
including the proposed payment amount, which we understand is not tied to any applicable fee of
Garfield County itself. We are also uncertain whether the City would even accept a payment of
traffic fees not tied to any contract or permit from the City. Additionally, we have some concern
about constructing improvements to Airport Road that may be obliterated by the future
construction of the South Bridge and could be a waste of money and effort. Our engineer will
address this at the hearing.
Aspen • Avon • Basalt • Glenwood Springs • Rifle
® Printed on recycled paper
GARFIELD & HECHT, P.C.
David Pesnichek
Garfield County Planning Division
September 5, 2014
Page 2 of 3
Nevertheless, if the City is willing to commit to constructing and completing the
improvements to Airport Road and Airport Center Road prior to the expected time that the
project would be ready for issuance of a Certificate of Occupancy, then the Applicant would
agree to pay the requested traffic fee amount of $585,000 to the City, We propose revising the
condition as follows:
The Applicant shall either contribute $585,000 to the City of Glenwood Springs
for road improvements or come to an agreement with the City for specific
improvements to be made to Airport Road and Airport Center Road to address the
anticipated traffic impacts of the project. If the Applicant and the City are unable
to reach an agreement, then the Applieant shall submit proof that the $585,000
has been deposited into an escrow account, which shall he released to the City
upon completion by the City of the proposed improvements to \irport Road and
Airport Center Road as identified by the City in its written comment letter. If the
City fails or refuses to complete such improvements prior to the time that the
Applicant would otherwise be entitled to issuance of Certificate of Occupancy but
for fulfillment of this condition, or by May 1, 2015, whichever first occurs, then
the Applicant shall be entitled to complete the remaining improvements itself and
apply the escrow funds towards such costs. If as of March 15, 2015, the City has
refused to accept the payment or to authorize or peribrm any construction work
on Airport Road and Airport Center Road as provided herein, then the Applicant
shall be relieved of this condition.
Condition 21. The applicant is committed to facilitating construction of the South Bridge
because it will benefit the project. however, there are challenges associated with the uncertain
plans and location of the proposed bridge. Additionally, if this condition is to be included then
we would like to see an alternative similar to the wording of Condition 20. As written in the
initial staff report, the condition could be read to grant the City unilateral discretion to approve or
not approve (or perhaps not even to consider) any agreement with the applicant. This would
effectively cede the County's land use authority to the City by granting it a veto power on the
project.
At the hearing, the Applicant's engineer will present testimony and evidence to show that the
$585,000 contribution referenced above (Condition 20) far exceeds the proportionateshare of
traffic impacts caused by the project to Airport Road and Airport Center Road. To offset that
contribution, therefore, the Applicant requests reimbursement of the fair market value of the
dedication parcel at such time as it may be needed for the bridge.
We propose the following:
1111145
The Applicant shall meet with the City to develop a plan to determine a specific
location and amount of land. to dedicate for the South Ridge landing, if any. This
dedication plan and agreement ,i'al. be in pluc beton issuanm..,e of any building
permit. Should the City determine that a dedication is ;7kot necessary, a letter from
the City stating such shall be provided to the County, and this condition shall .not
® Printed on recycled paper
GARFIELD & HECHT, P.C.
David Pesnichek
Garfield County Planning Division
September 5, 2014
Page 3 of 3
apply. If the City does not provide such a letter, and if the City and the Applicant
do not reach a mutually -acceptable agreement by October 17, 2014, then the
Applicant shall instead grant the County a 1 0 -year option to acquire the
dedication parcel at a location to be determined on the southern tip of the parcel,
with a right of way not to exceed 55 feet in width. The Applicant shall be entitled
to reasonable compensation for the actual fair market value of the dedication
parcel at the time of its conveyance to the County or the City, as applicable,
which shall include the costs of relocating or replacing any utilities or other
improvements that would interfere with the bridge project. If the parties cannot
agree on the amount of compensation informally, then the procedures set forth in
C.R.S. § 38-1-121 shall apply. The form of the option agreement shall be subject
to review and approval by the Comity Attorney prior to issuance of building
permit.
Condition 23. Please revise the final sentence of this condition as follows:
The easement document shall be prepared and submitted prior to issuance of the
Land Use Change Permit for approval by the County Attorney and shall be
recorded after transfer of the Property to KW Glenwood Springs, LLC and prior
to the issuance of a certificate of occupancy.
We need to consult with the current landowner and may have additional suggestions or
requests at the time of the hearing. If you have any questions in the meantime, please do not
hesitate to contact me. Thank you.
Very truly yours,
'HT, P.C.
_oac ug y
cc: Kelly Cave, Fsq. (e-mail only kcave@garfield-county.com)
Frank Hutfless, Esq. (e-mail only thutfless@garfield-county.com
DHM/kjt
1111145