Loading...
HomeMy WebLinkAbout4.0 ConditionsREAL ESTATE INVESTMENT The Board of County Commissioners Garfield County Glenwood Springs, Co. 81601 Re: Panorama Ranches Gentlemen: CEMSE DaJOLLEY I r YELASQUEZ_.... JUL24 1978 y ttpY^ y� FILE_ __ _ 3E-t3EN.73E3Ft. Et 30 Ack 3La 19E' x BOX /1082/ 303/927-3942 BASALT, COLORADO 81621 July 19, 1978 as This letter respectfully requests that the time for submission of the Final Plat for Panorama Ranches be extended for six months beyond its present due date of September 6, 1978, for the reasons set forth below. As you are aware, Preliminary Plat approval was granted subject to the adjudication of adequate water by the District Water Court. Immediately following Preliminary Plat approval, Ora McVey of Mountain Drilling Company was contacted to drill the required wells. He believed he could get a rig on the site by mid-November but it was late January before he was able to do so. McVey encountered only a small quantity of water after drilling to 376 feet. The well was cased and cemented. Meanwhile, we had contracted with X -L Drilling Company to drill a second well. That company began drilling January 24, 1978, and abandoned the hole nine days later after drilling 480 feet. They cased the hole to 320 feet and pronounced it a dry hole. We then selected a third site and contracted with McLeur Drilling Co. of Montrose, hiring a cat to clear a road through the deep February snows and make a well site. McLeur didn't show up to drill. We renewed the contract with McLeur April 19, 1978, and he moved a rig to the site. Two months later, after sporadic ineffectual effort, he abandoned the hole at 100 feet depth. McVey, meanwhile, said he believed the X -L hole had water but opined that they had "dog -legged" the hole and couldn't case it for that reason. He went in with a cable tool in late June, drilled inside the X -L casing, straightened out the hole, cased it and produced what appears to be a good well. It was tested at 10 gallons per minute with a two -horse pump and Glenwood Pump Company has installed a three -horsepower pump and is scheduled a 24-hour 25 -gallons per minute test. • Page Two If Glenwood Pump proves a sufficient quantity of water, we then must bring in hydrologist to supervise an uninterrupted 10 -day test to satisfy the requirements of the State Water Resources Division. Following that, we must go to trial in the District Water Court to prove that we are not injuring previously adjudicated water rights in Cattle Creek. In addition to a great deal of time and travail, we have expended $38,614.51 in our quest for water. It appears highly unlikely at this time that we will be able to fulfill the requirements for Final Plat submission by September 6, 1978, due to reasons beyond our control as set forth above and, thus, we ask that you give favorable consideration to this request for additional. time. Respectfully, ›A.;--74 John Wix, President General Partner Colorado Country Panorama Estates cc: All Partners Edward Weakly, Hydrologist -Ri\ • JUPr,IIIi, i. STEEL TANKS STRUCTURAL STEEL PLATE FABRICATION REINFORCING BAR Glacier Terliamis Co. 0252 167 Road Glenwood Springs, Colo. 81601 Dear Mr. Terliamis, • (i f7licaLYLy .Co. AI 0.1 Code 303---242-4015 1101 Third Ave. GRAND JUNCTION. COLORADO 81501 No \I .17 1q7 11 November 7, 1 'H GARFIEL CEP,cc v i11 1 r Y Re: Your Order for the O.1MG A.W.W.A. Tank for Missouri Heights East of Carbondale, CO The shell, bottom and roof material for the above referenced project, are now scheduled to be produced by the steel mill, the week of Novem- ber 6, 1977, that is, sometime between the 6th and the 12th of November. If the above schedule is upheld, we should be able to deliver all the component parts for this field erected tank sometime the week of Novem- ber 22, 1977. All but the shell, bottom and roof plates are in production at this time. FRM/jk Sincerely, GRAND JUNCTION STEEL FABRICATING CO. F.R. MITCHELL Production Coordinator 1. ‘'V l l.lh I