HomeMy WebLinkAboutCorrespondenceAndy Schwaller
From: Tamra Allen
Sent: Monday, March 14, 2016 2:28 PM
To: Andy Schwaller
Subject: RE: Public Service Rifle Ute Substation Grading Permit
I did visit with Jennifer and they are fine from our end to proceed.
Thank you for checking.
Tamra
Sent front my Vernon Wireley, 40 LTE sinarinhone
Original message
From: Andy Schwaller <aschwaller@garfield-county.com>
Date: 3/14/2016 9:24 AM (GMT -08:00)
To: Tamra Allen <tallen@garfield-county.com>
Subject: Public Service Rifle Ute Substation Grading Permit
Tamra,
I believe you might have spoken with Jennifer Keys with Wright Water Engineers regarding this project. They have
applied for a grading permit to change the access road; repair, replace and add some substation equipment foundation
support; and relocate utilities on their 230kv portion of the yard. It does not appear there are any new buildings or an
enlargement of what is out there now.
I did not want to release the grading permit without getting a pass from Planning on the work by Public Services. Let me
know what you think.
Thanks,
Andy