Emergency Response
For Pipeline Construction
May 2008
TABLE OF CONTENTS
1.0 INTRODUCTION ........................................................................................................................................ I
2.0 SPILL PREVENTION ......................................................................................................................................... 2
3.0 SPILL REPORTING PROCEDURES ....................................................................................................... 3
3 .I INTERNAL NOTIFICATION ............................................................................................................................ 3
4.0 EXTERNAL SPILL REPORTING REQUIREMENTS ........................................................................... 4
4.1 WHAT IS A REPORTABLE SPILL? ................................................................................................................ 4
4.1.1 Oil, Condensate, and Produced Water.................................... . ..... 4
4.1.2. Chemical and Refined Hydrocarbon Spill. ....... ........ .............. . ....... 4
4.1.2.1 Release into Water............... ................. ............................ ..................... ........ . ...... 5
4.1.2.2 Releases onto the Ground............................. ................ ............................ . .......... 5-
4.1.3 Cunnt!ative Releases.................................................................. . ............................................... 5
4.2 WHO IS TO REPORT?............................................... . ........................................................................... 5
4.3 WHENTOREPORTANDWHATTOREPORT? ........... . ............................................................................. 5
5.0
5.1
5.2
5.3
6.0
6. I
6.2
6.3
7.0
7. I
7.2
JNFORMA TION TO REPORT .................................................................................................................. 7
INITIAL VERBAL REPORT ............................................................................................................................ 7
FOLLOW-UP WRITTEN REPORTS .................................................................................................................. 7
VERBAL REPORTING PROCEDURES ............................................................................................................. 8
GENERAL SPILL RESPONSE PLAN .................................................................................................... 10
INITIAL COMMUNICATION AND ACTION PROCEDURES ............................................................................. I 0
SUPERVISOR'S RESPONSIBILITIES ............................................................................................................ 12
"FIRST RESPONSE" COMPANIES ................................................................................................................ 12
SPILL MANAGEMENT ........................................................................................................................... 13
SMALL VERSUS LARGE SPILLS ................................................................................................................. 13
REMEDIATION FOR LARGE SPILLS ...................... .
7.2.1 Spill Containment .................... .
7.2.1.1 Land Containment Methods ..
7.2.1.2 Containment on Waterways ..
7.2.2 Recovety .......................................... .
7.2.3 Initial Treatment ............................. .
7.2.3.1 Soils Handling ............... .
7.2.3.2 Brine Spills .......................... .
7.2.3.3 Hydrocarbon Spills ............................................ .
. ......................................................... 13
. .... 14
·································· ..... ············· ........ i4
························································· ........... 15
. ..... 16
17
. ......... 17
. .. 18
19
EnCana Spill Plan Emergency Response May 2008
Appendix A
Figures
Figure 6.1 Detail of Interceptor Trench
Figure 6.2 Trenches to Intercept Overland/Subsurface Flow
Figure 6.3 Culvert and Earth Dam Weirs
Figure 6.4 Water Bypass (Underflow) Dam
Figure 6.5 Various Means of Connecting Wood or Styrofoam Booms
Figure 6.6 Jellyroll and Sausage Roll Improvised Sorbent Barriers
Figure 6.7 Boom Angle Deployment vs. Water Velocities
Figure 6.8 Multiple Angled Booms
Figure 6.9 Possible Schemes for Boom Attachment
Figure 6.10 Snow Fence and Sorbent BatTier
EnCana Spill Plan Emergency Response May 2008
1.0 INTRODUCTION
The purpose of this document is to provide to construction, drilling, completion and production
operations personnel for EnCana Oil & Gas (USA), Inc. (EnCana) the following information as it
relates to spill incidents:
• Reporting requirements;
• Initial spill response procedures;
• How to access emergency response procedures; and
• Initial remediation techniques.
This document is intended to provide operations personnel with sufficient information so they
can readily assess a spill, know which government agency to report to, what to report, and how
to address the spill. This document only covers spills that are "manageable" with the tools and
resources that operations personnel have readily available to them. The document does not cover
urnnanageable or catastrophic spills that require specialized expertise and equipment.
Regardless of the size or type of spill, if difficulties or uncertainties arise, contact EnCana's
Parachute, Colorado Office staff for advice and assistance. Please refer to the contact
information provided in Section 2.1.
This Project Specific Spill Response Plan covers spills associated with construction, drilling,
completion and production operations and services associated with them.
A copy of this Project Specific Spill Response Plan is on file at the following locations:
EnCana Oil & Gas (USA), Inc.
Parachute, Colorado Office
EnCana Spill Plan Emergency Response May 2008
2.0 SPILL PREVENTION
Care should be taken to prevent spills, leaks and releases. Two variables must be considered if a
release occurs:
Rate of flow: Is variable, depending on size and location of the related failure. Maximum
expected potential rate of flow is not anticipated to exceed the amount of total liquid per day
transferred using the pipeline. Personnel routinely perform visual inspections of piping to detect
any failures.
Total quantity of fluid that could be discharged: Is variable, depending on the rate of flow though
the pipeline and the location of the failure. The maximum potential release would not exceed the
volume for the pipeline and tank of the fluid'being transferred.
EnCana has engineering controls and management practices in place to prevent spills. Secondary
containment is provided for oil spills at permanent facilities. For temporary surface pipelines
EnCana has designed the pipeline with block valves which isolate sections of the pipeline to
limit a release should one occur. Storage tanks are designed with isolation valves to ensure
containment.
EnCana's standard operating procedures require that any fluid transfer though temporary surface
pipelines will be manned 24-hour a day until the transfer has been completed. If a spill is
discovered then the following actions and reporting will be initiated immediately.
EnCana Spill Plan Emergency Response May 2008
2
3.0 SPILL REPORTING PROCEDURES
Spill reporting is an important part of environmental management. There can be fines and
penalties imposed upon a company for not reporting a spill if it is considered a "reportable"
occurrence under the legislation. This plan outlines when a spill is reportable, and to whom the
spill must be reported. In addition to reporting to regulators, EnCana's personnel must be
informed, and an incident/accident report completed and submitted to the EnCana's Parachute,
Colorado Office.
3.1 INTERNAL NOTIFICATION
Field personnel are to notify the EnCana's Parachute, Colorado office staff immediately upon
locating a spill, release, or an unnatural event. The EnCana's Parachute, Colorado office staff
will notify the required local, federal and state agencies.
EnCana Oil & Gas (USA), Inc. -Parachute, Colorado Office
(970) 285-2600
Dewey Neeley-Field Construction Leader
Office: (970) 285-2632
Cell: (970) 250-9462
Bob Anderson-Construction Coordinator
Office: (970) 285-2622
Cell: (970) 366-0772
Jess Wood-Team Lead, Facilities & Construction
Office: (720) 876-5064
Cell: (303) 885-5559
Home: (303) 621-2433
Hr~r!ll (_iimrlH..:son-(rmup Lcttd. Ll-1&2) (Lttvir(Hllllt~ntal [fealth & Safety)
Ulticc: (/)II) ;)!(,.JU)\)
lc II I 3 0 l i 8 I '! ;_; 1;
! !omc: (\()_\) (;~:i(J-J -;r-;s
En Can a Emergency Spill Response Plan
3
July 2007
4.0 EXTERNAL SPILL REPORTING REQUIREMENTS
External spill reporting requirements are state and federal requirements as they relate to
"reportable" spills.
4.1 WHAT IS A REPORTABLE SPILL?
4.1.1 OIL, CONDENSATE, AND PRODUCED WATER
In Colorado, spills are under the jurisdiction of the State of Colorado Oil and Gas Conservation
Commission. Reportable spills are defined as:
• ANY spill or release that may impact waters of the State. These spills are reportable as
soon as practicable.
• Any spills in excess of20 barrels (840 US gallons) are reportable within 24 hours.
• Any spills in excess of five barrels (210 US gallons) are reportable within ten days.
In addition, the following types of spills are reportable.
Spills that may cause an adverse effect to the environment. An adverse effect is defined as
"impairment of or damage to the environment, human health, or safety or property. "
Specifically, it is considered the following:
• Spill is confirmed to have moved off-location (including vertical migration to water
table);
• Contaminants are present off-location at levels generally accepted to be problematic to
soil, groundwater, livestock, and vegetation. This includes third party impact such as
vegetation damage, and livestock impact;
• Release is into surface water or a watercourse and moves off location;
• Release or spill has potential for offsite odor complaints; and
• Potential for toxic or flammable release to air going offsite.
For assistance in determining if a release can be classified as an "adverse effect" or "potentially
hazardous to the environment", contact EnCana's Parachute, Colorado Office Staff (See contact
information provided in Section 2.1 ).
4.1.2. CHEMICAL AND REFINED HYDROCARBON SPILL
Spills of production chemicals, fuels, lubricating oils as well as other refined hydrocarbons
require reporting. Reporting of ANY AMOUNT of chemicals identified as toxic substances is
required. Most of these compounds are associated with the downstream refining end of the
petroleum industry, and are therefore not dealt with in detail in this report.
EnCana Spill Plan Emergency Response May 2008
4
4.1.2.1 Release into Water
A release of ANY AMOUNT of a chemical into surface water, a watercourse or groundwater
that can cause an adverse effect on the environment must be immediately reported. Typically
this means water found external to a containment berm. The regulations require reporting of any
amount that can cause an adverse effect. This effectively means any chemical, fuel or lubricant
used in construction; drilling, completion and production operations that are spilled into surface
water must be reported. The regulatory authority then decides if any further action is required.
4.1.2.2 Releases onto the Ground
A release of chemical or fuels onto the ground below the State of Colorado thresholds may still
be reportable. Contact the EnCana's Parachute, Colorado Office staff for specific chemical
releases.
4.1.3 CUMULATIVE RELEASES
Cumulative releases involve the slow release of material over a sufficiently long time that the
volumes eventually become significant and represent a potential risk to the environment.
Cumulative releases that typically occur at our operations are associated with load outs, tank
farms, pits, etc. and are relatively confined, therefore not causing a "significant environmental
effect". Although the reporting of cumulative releases is required if they are causing a
significant environmental effect, it should only be done in consultation with EnCana's Parachute,
Colorado Office staff.
4.2 WHO IS TO REPORT?
When an operator, maintenance person or other employee discovers a reportable spill, the area
supervisor ofEnCana's Parachute, Colorado Office staff must be notified immediately. The area
supervisor must immediately contact EnCana's Parachute, Colorado Office staff, who will
contact the appropriate government agency to report the spill (see Table I below). EnCana's
employees and contractors are not to contact regulators unless directed to do so by their manager.
4.3 WHEN TO REPORT AND WHAT TO REPORT?
A release should be reported to the appropriate government agency as soon as it is discovered or
at the first available opportunity. The requirement for reporting is both verbal and written
depending on the severity of the spill. Govemment authorities will advise if a written report is
required at the time the verbal report is provided. Reporting personnel should make a point of
inquiring about the need for a written report. The Table on page I 0 outlines the specific
information to be provided verbally and in written repmis for spills of oil, condensate and
produced water, as well as spills of chemicals and refined hydrocarbons. Verbal reports are
provided as soon as possible, written reports are provided according to the schedule required by
the government agency.
EnCana Spill Plan Emergency Rcspon)~ May 2008
5
Local Emergency Planning Commission (LEPC) is the County Sheriffs Otl!ce (Table I). When
notified of a spill, they may contact state and federal agencies, but be sure to cont!nn this,
because procedures change regularly. Written reports will be compiled and submitted by
EnCana.
TABLE 1: GOVERNMENT AGENCY EMERGENCY CONTACT LIST
FEDERAL AGENCIES
National Response Center:
http://www.nrc.uscg.mil/index.html
EPA Region VIII:
http://www.epa.gov/region8/
800-424-8802 (24 Honr)
303-312-6312
303-293-1788 (Spill Line)
800-227-8914 (24 Hour)
BLM Colorado River Valley Field Office 970-876-9000
http://www.blm.gov/co/stlen/fo/crvfo.html
BLM Grand Junction Field Office 970-244-3000
http://www. blm. gov/co/st/en/fo/gjfo.html
STATE AGENCIES
CO Oil & Gas Conservation Commission: 303-894-2100
http://oil-gas.state.co.us/ 1-888-235-1101 (Spill Line)
Colorado Department of Public
Health and Environment (CDPHE):
http :1 /vvvvw. eel p he. state. co. us/
1-877-518-5608 (24 Hour)
Colorado Division of Oil & Public Safety: 303-318-8547
http :1 I o i I. cell e .state. co. us/
Glenwood Springs Division of Wildlife 970-947-2920
(Northwest Division)
Northwest Region Service Center 970-255-6100
(Grand Junction)
COUNTY AGENCIES
Garfil'ld County LEPC
Jim Sears, Emergency Vlam1ger
EnCan<1 Emergency Spill Response Plan
l) 70-94 5-114 53
6
July 2007
5.0 INFORMATION TO REPORT
5.1 INITIAL VERBAL REPORT
Verbal reports must be provided immediately, or as soon as practicable. Reports should include:
Oil, Condensate and Produced Water
• The location and time of the release;
• The type and quantity of the material released;
• The details of any action taken so far, and the actions proposed to be taken at the site;
• A general description of the location of the release and of the immediate surrounding area;
Chemicals and Refined Hydrocarbons
• Date and time of the release, or the time period over which the release occurr.ed if known;
• The location of the release;
• The duration, frequency and rate of release if known;
• The type of chemical released and amount released, if known;
• A discussion of spill containment and recovery procedures used;
• A discussion of steps to be taken to prevent similar spills;
• The status of the remediation program (remediated, under active remediation or io be
remediated);
• The remediation plan and schedule of implementation if required; and·
• Information regarding landowner notification.
5.2 FOLLOW-UP WRITTEN REPORTS
Written reports will be provided according to the schedule required by government agency.
Colorado requires the completion of Form 19.
Oil, Condensate and Produced Water
• Date and time of the release, or the time period over which the release occurred if known;
• The location of the release;
• The duration, frequency and rate of release if known;
• The type of material released (produced water, etc.) including concentration of key
components and amount released if known;
• A discussion of spill containment and recovery procedures used;
• A discussion of steps to be taken to prevent similar spills;
• The status of the remediation program (remediated, under ~ctive remediation or to.be
remediated);
• The remediation plan and schedule of implementation if required; and information regarding
landowner notification
EnCana Spill Plan Emergency Response May 2008
7
Chemical and Refined Hydrocarbons
• A description of the circumstances leading up to the release;
• A discussion of spill containment and recovery procedures used;
• A discussion of steps to be taken to prevent similar future spills; and an outline of the
proposed spill site reclamation program
5.3 VERBAL REPORTING PROCEDURES
The foiiowing contacts must be made in the event of a reportable spiii or other emergency. Refer
to Table I for current phone numbers.
Garfield County SherifPs Department (County LEPC)
The Dispatch operator will assess the need for service and will dispatch emergency Police,
Ambulance, Fire and/or Hazardous Material Response as required.
Construction, drilling, completion and production operations personnel will contact the Garfield
County Sheriffs Department in the early stages of operation to advise them .of the start of
operation and to provide instructions to reach the operations site. The directions will be kept on
file by the Dispatch operator and utilized if required.
In the event of a spill the Garfield Sheriffs department is also the t:ounty LEPC. The LEPC
Coordinator will access the situation and activate the County Hazmat response team as required.
The Coordinator will also act as first contact advisor to initial clean .• up efforts .. The Coordinator
may also contact additional regulatory agencies as required, but be sure to ask them and
document the response.
National Response Center (NRC)
The NRC must be notified in the event of a produced \Mater spill that. could reach waters of the
US. The NRC will notify the US Coast Guard. They will contact the region in which the spill
occurs and a regional coordinator may be dispatched to the site depending on severity of the
spill. Both the EnCana's supervisor and the Garfield County LEPC Coordinator must contact the
NRC.
Environmental Protection Agency (EPA) ·
The NRC should notify the EPA regarding a spill. However, contact the EPA Region 8 Spill
Line (Table I) just to be sure.
Colorado Oil & Gas Conservation Commission
This division must be contacted in the event of any spill (regardless of size). This is the state
emergency response commission. A representative will be sent to the site if required.
EnCana Spill Plan Emergency Response May 2008
8
Bureau of Land Management (BLM):
Initial contact with BLM should be to the Glenwood Springs Energy Office, Grand Junction
Field Office & White River field Office (Table I). They will then activate the BLM spill
response plan.
EnCana Oil & Gas (USA), Inc.
The EnCana Parachute, Colorado Office staff will activate EnCana's spill response personnel if
required and dispatch an environmental/spill specialist to site if the spill severity requires it. The
Division Manager will dispatch the Area Production Supervisor to the site to manage spill
containment and clean up operations if needed. The· Area Production Supervisor will··
communicate with the Garfield County Sheriffs Department, the appropriate surface use agency
(Bureau of Land Management, Colorado Division of Wildlife) to facilitate and manage the
overall clean-up operation and ensure to that all government requirements are fulfilled.
EnCana Oil & Gas (USA), Inc. -Parachute, Colorado Office:
The EnCana Parachute, Colorado Office staff will provide spill clean up guidance and will
prepare detailed spill reports for the regulatory agencies. Enviromnental spill specialists will
coordinate with the Garfield County LEPC Coordinator to ensure that all government regulations
and requirements are met. Environmental spill specialists will work with and advise the onsite
Production Supervisor regarding remediation measures required. Spill specialists will coordinate
all post clean up sampling activity and reporting.
EnCana Spill Plan Emergency Response May 2008
9
6.0 GENERAL SPILL RESPONSE PLAN
6.1 INITIAL COMMUNICATION AND ACTION PROCEDURES
Internal spill reporting procedures require completion of an EnCana's incident/accident report as
well as a spill assessment form. Information contained on this form assists operators in
providing verbal reports to government authorities. The spill assessment form also helps to
characterize the spill sufficiently that appropriate response procedures can be initiated. The
assessment form covers spills from all facilities associated with the upstream oil and gas sector
including pipelines; however the form will be completed for reportable spills only. The form is
to be completed by operators at the time the spill is discovered. It is maintained with the
operator's files with a copy forwarded to EnCana. The assessment form is not submitted to any
government agencies. A copy of the assessment form is contained on the following page.
It is important to document all phases of a spill. If an assessment form is not available,
document all information (date, time of actions, phone numbers called, contact names, etc.) on
available paper and transfer it to a proper form at a later date.
The most critical aspects of spill response are accurately locating the spill, isolating or shutting in
the source of the spill, if possible, and containing and recovering surface fluids. All of these
activities must be undertaken with due consideration for the safety of the operator, clean-up
crews and the general public. Reporting of the spill should take place once initial activities to
contain and recover the spill are underway. Reports should be submitted to the appropriate
government agencies, as well as to EnCana. The spill assessment form as well as an incident
accident report form must be completed and-retained in company files.
EnCana Spill Plan Emergency Response May 2008
10
I_
SPILL ASSESSMENT FORM
FOR NOTIFICATION PURPOSES
I. Date ___ _
2. Date ____ & Time of discovery or occurrence ______ am. pm.
3. Person who discovered spill _________________ _
4. Telephone number of person who discovered spill. _________ _
5. Location of spill (detailed) _114 _114 Sec. T R
State _________ County ----------
6. Type of material spilled: _Oil _Saltwater Oil & Saltwater
_Toxic Fluid, _Other (Specify) ----··--·------·····
7. Source of spill (Check one):
_Pipeline Failure Tank Overflow
_Treater Upset _Tank Rupture
Other Unknown
8. Quantity of material spilled _ bbls. _Unknown
9. Is the spill source stopped?_ Yes _No. If not, what remaining maximum
quantity could be spilled? __ Bbls.
10. Present weather conditions. _________________ _
II. Forecasted weather conditions: 24 hrs. 48 hrs. ------72hrs. __ _
12. Actions underway to stop/control the spill.
---------·······-········-···--···----···-------
EnCana Spill Plan Emergency Response
1!
May 2008
6.2 SUPERVISOR'S RESPONSIBILITIES
EnCana's Parachute, Colorado Office Staff can provide advice and assistance with respect to
operator responsibilities as required. Operator is responsible for the following items:
• Assessing the location and source of the spill and determining if the spill can be contained;
• Assessing the hazards associated with responding to a spill;
• Determining the extent/impact of the spill;
• Contacting and dispatching clean-up crews;
• Controlling access to the spill site;
• Coordinating the containment and recovery of surface fluids;
• Notifying company and regulatory agencies; .
• Completion of spill assessment form, and incident/accident report form;
• Ensuring topsoil is salvaged and segregated; and
• Scheduling clean-up and repairs.
6.3 "FIRST RESPONSE" COMPANIES
First response companies will provide assistance with initial containment and recovery of
product. Operators should be aware of local "first response" companies that they can call on to
assist in initial containment of the spill. Operators should ensure that a listing of First Response
companies is compiled and appended to this document. This list should also be posted in
common areas at batteries and other facility sites, Opemtors should ensure that this hst is
periodically updated so that only those companies that are current appear on the list.
Willow Creek Companies
Russell Fowles
P. 0. Box 55174
Grand Junction, CO 81505
970-256-7003 -Office
970-778-5554-Cell
Backhoe/Dirt Work/Emergency Response
Rockies Construction
970-319-3167-Bill Hoke (Parachute)·
970-769-5035-Duane Higgins
505-334-1976-New Mexico Office
Vacuum Truck
Badger Day lighting
970-309-7342-Kent Powel (Rifle)
1-877-3BADGER-USA Office
Vacuum Truck
EnCana Spill Plan Emergency Response
12
May 2008
7.0 SPILL MANAGEMENT
7.1 SMALL VERSUS LARGE SPILLS
Many spills occur that are typically very small and located within the pad area. For smaller ·
spills, the technique for spill clean-up is basically shoveling the material into a drum, labeling the
drum, and disposing of it along with other oil field waste materials as per routine disposal
methods to a landfill. Generally, Class I landfills accept this type of waste, however if the·
material is contained within drums, Class II landfills may also accept them. Other methods of
manual recovery include using cans, buckets or rakes to pick-up contaminated soils on the
surface. The important point to consider when remediating small spills is to ensure that ALL of
the affected soils have been removed or otherwise dealt with and all actions to clean-up, repair
the problem, and prevent further occurrence are well-documented. This is most easily
accomplished if the spill is dealt with immediately, thereby not allowing the spill to soak into the
ground.
The following illustrates the decision matrix for spill clean-up.
Spill greater than 2yd 3
or larger than what
can easily be cleaned
up with a shovel?
7.2 REMEDIATION FOR LARGE SPILLS
The information contained within this section is meant to provide guidance on initial
containment, recovery and treatment measures to be applied to spills, which are "manageable"
with the equipment and expertise available to the majority of EnCana's operations supervisors.
This section is not meant for larger, uncontrolled spills that will require specialized equipment
and expertise.
EnCana Spill Plan Emergency Response May 2008
13
Spills will require initial containment and treatment so as to minimize spill clean up and site
restoration work, and the potential for environmental and public health risks. This section
provides information on initial treatment to stabilize the spill and prevent the worst effects from
settling in before the site can be sampled and more specific treatments applied. Contact
EnCana's Parachute, Colorado Office staff for any additional advice or assistance that may be
required. See contact information provided in Section3.1.
7.2.1 SPILL CONTAINMENT
Containment measures may be broadly categorized into two groups: land based and water based.
The options for containment make use of a wide range of locally available materials such as
straw, chicken wire, and snow fencing as well as commercial sorbents and booms.
7.2.1.1 Land Containment Methods
It is important to note that land spills are generally much easier to deal with
than spills that have reached a waterway. Efforts should be made to prevent
or stop spilled product from entering the water.
Land containment of spills can be achieved by using minor earthworks such as trenches and
earth dams or dykes. In the winter,· snow ·can be used for a similar purpose. Snow is also a
suitable sorbent material for spills other than salt spills. Salt will melt the snow and result in
fmther spread of salt contamination.
Trenches
Trenches can be used to intercept and hold all types of fluids; however trench construction is
practical only in the summer. Figures 6.1 and 6.2 (Appendix A) provide details of an interceptor
trench and methods of using trenches to intercept overland and subsurface flo.w.
Trench construction should include the. use. of a plastic liner. This prevents downward migration
into subsurface soils and potentially groundwater. Relatively shallow trenches may be
strategically placed down slope of a spill to intercept surface and subsurface spilled materials.
This method is effective in preventing subsurface contamination of water and eventual discharge
to streams and other water bodies. Equipment required to build a trench includes:
• Backhoe, loader, bulldozer;
• Shovels, picks; and
• Plastic liners.
EnCana Spill Plan Emergency Response May 2008
14
Dams and Dykes
Earth and snow dams may be constructed across ditches or low areas to contain a spill and stop
its flow. The entire flow of the spilled material and any surface drainage may be contained.
Construction materials include earth, wood, sandbags, and snow. The dam or dyke should be
lined with plastic sheeting to make it impermeable to the spilled product. In the winter, water
may be sprayed on the snow dams or dykes to create ice. Dams should be of sufficient size to
contain the entire spill volume; insufficient capacity may result in overtopping and/or failure.
7.2.1.2 Containment on Watenvays
Water contaimnent measures generally include the·use of booms or barriers. However, dams and
weirs may also be used for ditches with flowing water and for smaller streams. Figure 6.3
illustrates the use of dams and weirs. These methods are typically used when~ it is. necessary to
allow the water to flow, while retaining lighter than water liquids such as petroleum products that
separate readily from water.
Water bypass or underflow dams may also be constructed on small, slow-flowing streams.
Water bypass involves first constructing an earthen dyke to stop the flow of water, and then
inserting a pipe below the level of the spiiled material and discharging the water on the other side
of the dyke. (Figure 6.4). It is important to note that the discharge end of the pipe should not be
inclined above the level of the dyke or overtopping and failure will result.
Weirs made from plywood, lumber and sheet metal may also be used in ditches with tlowing
water and may be placed to completely or partially block culvert openings. These barriers may
be suspended from stakes on either side of the culvert openings and raised or lowered -to maintain
the desired water level while retaining the oil.
Recovery of material collected behind dams and weirs may be made with the use of sorbents,
skimmers or by direct suction.
Other water containment measures include the use of booms or baniers. These· methods are
typically limited to the contaimnent and recovery of materials that will readily separate from and
float on water. The type and size of a boom will depend on the specific location and the
conditions within which the boom will be used. The general principles for using a boom are:
• To contain a spill of floating liquid or debris;
• To deflect or divert material to a defined area so that it may be recovered; and
• To protect sensitive areas from contamination.
EnCana Spill Plan Emergency Response May 2008
15
There are many common items that can be used as improvised booms. These include:
•
•
•
•
•
•
•
Railroad ties;
Telephone or power poles;
Trees;
Lumber;
Inflated fire hose;
Styrofoam;
Ct..:~l,~-'"'"Cor +:nt..:-~ -"' ~nd sorbent mater1'als (rolle.-1 ;ntn" oo.wono ohono\ lllVJ'\.Vll VVU .l.lk)lUU!:) 111...-L Ul u J J. v u .:l(.U..lU(..I.fS'-' JHU.J-''-'J•
It is important that buoyant material be used within the boom; otherwise it will become water
logged and sink after several hours. Rope_ or wire can be used to hold the boom sections in
place. Natural sorbents include straw and evergreen boughs. Commercial sorbents have greater
capacity to absorb oil and other petroleum products; they last longer, and can be reused. Foam
sections have good sorbent capacity and excellent buoyancy. Figures 6.5 and 6.6 illustrate
methods of connecting booms together and construction of a "jellyroll" or "sausage roll" using
improvised sorbent barriers.
Proper boom deployment is a critical consideration. The angle of the boom relative to the flow
direction must be related to water flow velocity in order to achieve effective containment (Fignre
6.7). Several booms arranged in parallel may be necessary to contain the entire product. These
should be spaced to allow for particles, which may escape the first boom, float to the surface, and
be contained by the next boom. In addition, the use of several booms permits the removal of a
boom for cleaning. Figures 6. 7 to 6.9 illustrate ... boom deployment methods. The chart at the
bottom of Figure 6.7 illustrates the proper angle to deploy the boom based on water velocity.
The higher the stream velocity, the more perpendicular the boom will be with respect to the
crossing. In the example shown in the illustration, proper bloom deployment is at an angle of 24 °
for a stream flow velocity of 17 5 feet/minute.
Fixed baniers can be used in streams with soft bed& where stakes can be .. driven. A snow fence
barrier may be installed to span the width of a stream less than 1 m deep and may be anchored at
both ends with steel or wooden stakes. Stakes are driven into the stream bottom at 3 to 6 foot
intervals. Straw bales or commercial sorbents are placed on the upstream side. The banier
should be angled against the current for collection of product along the shore. Multiple snow
fence barriers can be used to provide backup against potential losses from upstream barriers. Net
or chicken wire barriers can be constructed for !he same purpose. Figure 6. J 0. iJ.lustmtes a typical
snow fence barrier.
7.2.2 RECOVERY
Recovery effmts must be undertaken as soon as it is practical and safe to do so. Focus on rapid
recovery of spilled materials is required to reduce and/or eliminate any poremial· dangers or
hazards to the environment. Recovery methods generally include suction, mechanical removal
and use of sorbent materials.
EnCana Spill Plan Emergency Response May 2008
16
Suction
Direct suction includes the use of vacuum trucks or portable pumps. Large capacity wet service
shop vacs may also be used if there is an available power source nearby. Suction screens may
be required to prevent hose plugging by floating debris and to prevent pump damage. Care
should be taken to reduce the uptake of water in order to minimize the amount of material, which
requires disposal, and prevent mixing of oil and water.
Manual and Mechanical Recovery
Manual and mechanical recovery, discussed previously, is an effective option for the removal of
small spills. Manual recovery using hand tools (shovels, buckets, rakes, cans) is also effective in
removing spills from areas that are inaccessible to larger equipment. Though labor intensive and
time consuming, manual recovery is often the only method of recovery available and in some
cases is the preferred method as it causes the least amount of damage to an area.
Mechanical recovery using heavy equipment is an option typically-reserved for larger spills.
Details with respect to the use of heavy equipment are provided in local area emergency
response plans.
Use ofSorbent Material
Sorbents are materials that soak up oil or other product. They are commonly used for final clean·
up and recovery of small amounts of product or to remove product in places that are inaccessible
by other means of recovery. They are effective in.recovering thin as well as thick layers of
product; however large volumes of sorbent material may be required for thick deposits.
7 .2.3 INITIAL TREATMENT
Initial treatments are designed to prevent the worst effects of a spill from "settling in" before the
site can be sampled and more specific treatments completed. The purpose ofinitial treatment is
to "buy time" to allow for more extensive sampling and analytical programs to be completed and
to optimize treatment programs. Initial treatments are especially important on salt spills, as these
initial remediation measures will greatly assist in deterring or slowing the soil "salinization"
process. These treatments should proceed within 24'to 48 hours of the spifl, before the spill dries
out or receives much rain. If there has been considerable rain resulting in soft soils, chemicals
may have to be hand broadcast or sprayed fromoffsite to prevent vehicles from rutling the soil.
7.2.3.1 Soils Handling
Soil handling must be minimized to the extent possible during wet soil conditions. Typically if
there is a potential to create ruts that are greater than 3 inches deep, equipment should be kept off
the soils and the spill should be accessed on foot and manually dealt with as explained in
Section 7.2.2. However, under an emergency situation this may not always be feasible and it may
be necessary to strip the topsoil ahead of the machinery when accessing the site to prevent
compaction and destruction of the soil structure. In particular, soils must be handled carefully
during excavations. The following measures should be taken when excavating soils:
EnCana Spill Plan Emergency Response May2008
!7
• Strip the topsoil away from the area where you intend to excavate. Stockpile the topsoil
away from the area where you plan to stockpile the spoil materials to avoid mixing the two
together. When it is time to fill the hole, fill it first with the spoil materials, leaving a low
"roach" or mound to account for settling. Respread the topsoil evenly on top of the mound
being sure to completely cover the excavated area. It is particularly important during winter
excavations to not replace the topsoil until the spoil pile has settled; and
• If the topsoil was contaminated during the spill, treat the topsoil according to the
specifications listed below for brine and hydrocarbon spills.
7.2.3.2 Brine Spills
For the purposes of this document, brine is defined as:
• Water with over 10 000 mg/1 (ppm) of total dissolved solids (TDS); OR
• Emulsions containing over 20% brine (emulsions with less than 20% brine can be treated as -a
hydrocarbon spill since the oil component will be sufficiently high that it is treatable as
such); OR
• Previous spills have caused "bare spots" on the ground where vegetation either does not
grow, grows slowly, or is characterized by plants that appear different from the sunmmding
area.
Information on the composition and general chemistry of fluids characterizing the field areas
may be obtained from fluid sample analysis reports (CORE labs etc.), and should be reviewed by
operators to determine the potential for a spill to result in impacts to soils or vegetation and the
need to initiate immediate response.
Initial treatment for brine spills typically involves the addition of a calcium product to be applied
and incorporated into the soil within the first 24 to 48 hours of clean up prior to flushing with
fresh water. Operators should be aware of product suppliers in their areas, and have a listing
posted or readily available at facilities. Accepted treatment chemicals include gypsum (calcium
sulphate) and various formulations of calcium nitrate (liquid or granular fertilizer 15.5-0-0;
Saline Soil Saver (SSS); and LCA-U). Generally calcium nitrates. are prefened because of better
solubility, but are prone to surface washes and may contaminate nearby water sources.
Conversely, gypsum's low solubility characteristics make it unsuitable for most sites except wet
areas. Other chemicals that have been used successfully on brine spills include calcium chloride
(CaCb ), and magnesium sulphate (MgS04 ). The following options are provided for initial
remediation of brine-contaminate.d. soils ..
EnCana Spill Plan Emergency Response May 2008
18
Option 1:
Site Conditions:
Ground is not frozen, and can be cultivated or soaked with water to incorporate the fertilizer.
There are no water sources (shallow wells, sloughs, dugouts, ponds) near the spill site, and soils
are average in terms of moisture levels (mesic sites). Note: Calcium nitrate should never be used
in situations where site run-off could cause it to contaminate sources of drinking water for
human, livestock, or wildlife consumption.
Application: 2.2 lbs. calcium nitrate per I 0 yards 2 .
Procedure:
Spread the fertilizer on the spill site (by hand if the soils are wet). Cultivate or water the soil well
so that the fertilizer is incorporated. Soak the soil until puddles form. Let puddles soak in, and
then soak the soil some more. Soak the soil as often as possible over the next few days.
Calcium nitrate/polymer/flocculant formulations may also be used and are prefened when the
ground is not frozen or over saturated so that the treatment soaks in immediately. These
formulations are commercially available under the trade names Saline Soil Saver (SSS) and
LCA-II.
Application: Dilute 0.8 US gallons of SSS or 0.5 US gallons of LCA-II with 6.2 US gailons of
fresh water and apply 500 US and apply to I 0 square yards. Be sure to protect the concentrate
from freezing.
Option 2:
Site Conditions:
The ground is frozen and there will likely be runoff in the spring;. OR the. site is near water,
thereby precluding the use of calcium nitrate.
Application: II lbs. gypsum per I 0 yards 2 •
Procedure:
Spread the granular gypsum on site (by hand if soils are wet). If the ground is not frozen, and
cultivation of the soils is possible (the affected site is not a bog or muskeg) cultivate as soon as
soils are dry enough to permit cultivation, then soak the soil until puddles form. Only soak the
site once immediately prior to incorporation as the chloride salinity will aid in increasing .. the
solubility of the gypsum.
7.2.3.3 Hydrocarbon Spills
Soil contaminated by hydrocarbons must be removed from the spill site and removed to an
approved landfill.
EnCana Spill Plan Emergency Response May 2008
19
EnCana Spill Plan Emergency Response
Appendix A
Figures
20
May 2008
'·.
··-
·· ... -.
EnCana Spill Plan Emergency Response May2008
21
---~.
-._ ---.. --. \ --.. ··~ ... :·:·i
.• , .. ,,r ---.... _
,_
---·-.
h:,_;•-n. !~ !
·; n· -H .:.~·-.. ·,, , • :. ~·~~·t t ~\>' r .1 rd •\tl'h~>; =·,L. ,. -:-h.w
EnCana Spill Plan Emergency Response May 2008
22
. ·'
..... -.-·
EnCana Spill Plan Emergency Response
·· ..
..
'
1· ':!.-11·' • •...
23
···r· .t._
···-·J
..·
,.
'Ti
-"--.J,
· ....
May 2008
.. ------·-~ ---~ ..
?AitJ
/
·,,
.. --. :::;,.:.~·--:....~;/-\'· '· . -~~' -----__ _..-
\•i~UI:"I! -ti. ~
f1 .11~ r :~~ :1.:.~.,: i_l·, ~~f:7.-..l'.,,l l.':m1
EnCana Spill Plan Emergency Response May 2008
24
·,1. •) ~"'. ' .,....,,~" f '· t.l-
... : ,.· 1: ·.u· ~ l• •,
. ," ;.-;·
.. ..:.··
/ -~.;.·:
··~ .. • , --r' • _: ... ·.-
··'····· \· .~·
,; _-.-A
·' .·· .,, ··~. · . /-·····
--:.: .. -~--~._....
., ~ .,
·-·-·. •, 'i.
EnCana Spill Plan Emergency Response
25
•.'.•
.. · _ .. ·
':· )' r;.•
·"'··
> '' ~ .~ ...
·--_ _,.,
-~ .··
.·••·
!''• ·~·1->
~ . ; . ' .,
May 2008
/
./
/
/
H~.m·J~ 6.,·~·
--~·,R·\ .. :->
Jd!))dt ;tlt'l '·:b.t·;,l:_:f~ J•.U hnmn·. ;;..--d ;. .. •rhrlit E.tni.-,-~.
EnCana Spill Plan Emergency Response
26
May 2008
I((! :··
•3 I = :~ I ~!
!.;
c. :.':·.~~ •· I;, ~ "' l.
' .. I
.: .. : :· I ;--
•::·
Y.' .. I _,
., ~:.I) : ~= !
r
I
I
' '• ' ' ' \
\ \
·-.
!·1_;1 T•'o7
-------~--~
l
I
~
·-;l
'!
i
J
!
' ' ,
' .I
•I•'
!l~o~ n \t~~··k l't.:oli.t~·tn.Ji ,·. '.\.li:f!l ~"'~''·1
EnCana Spill Plan Emergency Response
27
';)
''· >.;;,
" •.'1
'·'• ~:
::-...
·-::·
·~. •·
May 2008
EnCana Spill Plan Emergency Response
A:::_--::)vER 1 ----v-····--;:y~----,
. .
'
' / -"'-..:_ --
h~'-'J\I·,It!'{
28
May 2008
--...
··.
·-.;;.._ .... -··
·· ... ·---. -·-.
·. __ _
.•
/
·· .
···-. -·~~
...
EnCana Spill Plan Emergency Response
~. ·."•'.
• 1',
May 2008
29
... . -·· .. -· ·-....... ..
. --:·-:.~---~~-.·...:·-.--· -...
' , ..
. .. ,-~ .. ,
EnCana Spill Plan Emergency Response
-:-·•· ..... ~itC,.:(
-~---~--._ . .--·-
1-_: ...
F~~-U .. ~J-H
."'_"i ... , .. -: -,(t. ~n.-1 .:'•:rbd·-~ /); r'l"il.!
May 2008
30
1.0 CONSTRUCTION METHODS
1.1 PLAN OF DEVELOPMENT
EnCana has developed a Plan of Development, which describes construction methods and
measures to be taken by EnCana during construction, operation, and maintenance of the
project. The Plan of Development is provided to project personnel, to establish guidelines for
construction and operation of the project and to address mitigation.
1.1.1 Construction Sequence
The following section provides a description of each phase of standard construction during the
project. The following operations are typical during a construction project.
1.1.1.1 Engineering Surveys
The construction right-of-way will be marked prior to construction with laths and/or flagging.
Laths/flagging will be maintained throughout construction and will not be removed until after
reclamation activities have been completed.
1.1.1.2 Clearing, Grading, and Topsoiling
Clearing, topsoiling, and grading will be limited to the minimum area required for safe and
efficient construction.
Available topsoil, up to a depth of six inches, will be segregated from the trench line only. Where
grading is required, topsoil will be stripped from the entire portion of the right-of-way. Topsoil will
be removed and stockpiled, and the right-of-way will be graded only to the extent necessary to
create safe and efficient pipeline installation conditions.
1.1.1.3 Trenching
The ditch will be excavated and sloped in accordance with OSHA specifications. The cover from
top of pipe to ground level will be a minimum of 48 inches. Where rock is encountered, tractor-
mounted mechanical rippers or rock trenching equipment may be used to facilitate excavation.
The bottom of the trench line will remain free of rocks and debris to allow for a solid surface to
install the pipe.
The trench will be excavated and subsoil material stockpiled at the edge of the workspace.
Based on field conditions, gaps will be made in subsoil stockpiles to avoid ponding or excessive
diversion of natural runoff during storm events.
1.1.1.4 Pipe Installation
Pipe installation will include stringing, bending for horizontal or vertical angles in the alignment,
welding the pipe segments together, coating the bare areas of each joint of pipe at the welds to
prevent corrosion, and then lowering-in and padding as described in greater detail below.
Stringing
Pipe will be hauled by truck to the pipeline right-of-way. Each joint of pipe will be unloaded and
placed parallel to the ditch. Each section of pipe will be stacked on timber skids to stabilize the
pipe until welding is completed. This is done to minimize handling of the pipe and prevent
damage to the pipe coating.
Bending
After the joints of pipe are strung along the ditch, individual joints of pipe will be bent to
accommodate horizontal and vertical changes in direction. Field bends will be made utilizing a
1
Bending (continued)
hydraulically operated bending machine. Where the deflection angle of a bend might cause
minor wrinkling or buckling of the pipe on a field-bent pipe, manufactured heat induction bends
will be installed when applicable.
Welding
After the pipe joints are bent, the pipe will be welded together in conformance with the various
welding standards.
Welding Inspection
Welds will be visually inspected by a qualified inspector. Any defects will be repaired or cut out
as required under the specified regulations and standards. Welds may also be non-
destructively examined.
Coating
To prevent corrosion, the pipe will be externally coated with fusion bonded epoxy coating prior
to delivery. After welding, field joints will be coated with fusion bond epoxy coating, tape and
primer, or shrink sleeves. Before the pipe is lowered into the ditch, the pipeline coating will be
visually inspected and tested with an electronic detector, and any exposed steel on the pipe will
be repaired.
Lowering-in and Padding
Once the pipe coating operation has been completed, the pipe will be lowered into the ditch one
section at a time. Padding or placement of sand bag "pillows" every few feet along the bottom of
the trench line are installed before the pipe section is lowered-in, depending on the bottom
surface of the trench. Side-boom tractors will be used to simultaneously lift the pipe, position it
over the ditch, and lower it in place. Inspection will be conducted to verify that minimum cover is
provided; the trench bottom is free of rocks, debris, etc.; external pipe coating is not damaged;
and the pipe is properly fitted and installed into the ditch. Specialized padding machines will be
used to sift soil fines from the excavated subsoil to provide rock-free pipeline padding material.
The purpose of the "pillows", described above, is to bed the entire circumference of the pipe in
soil fines In rocky areas, imported select padding material or a rock shield will be used to
protect the pipe. Topsoil will not be used to pad the pipe.
1.1.1.5 Backfilling
Backfilling will begin after a section of the pipe has been successfully placed in the ditch and
final inspection has been completed. Backfilling will be conducted using a bulldozer, rotary
auger backfill, padding machine or other suitable equipment. Backfilling the trench will use the
subsoil previously excavated from the trench. Backfill will be graded and compacted, where
necessary, for ground stability, by being tamped or walked in with a wheeled or track vehicle.
Compaction will be performed to the extent that there are no voids in the trench. Any excavated
materials or materials unfit for backfill will be utilized or properly disposed of in conformance
with applicable laws or regulations. Topsoil will not be used to backfill the trench.
1.1.1.6 Cleanup
Cleanup activities will be initiated as soon as practicable after backfilling activities have been
completed. All construction-related debris will be removed and disposed of at an approved
disposal area. The right-of-way will be graded as near as possible to the pre-construction
contours and natural runoff and drainage patterns will be restored. The right-of-way will be left in
a roughened condition to provide micro-climates for plant development and collection of
stormwater runoff.
2
1.1.1.7 Hydrotstatic Strength Testing
This pipeline will be hydrostatically strength tested to establish the maximum allowable
operating pressure of the pipeline and ensure the integrity of the pipe before putting the pipe
into service. The pipe will be tested at a pressure of 125% of the MAOP for a period of eight
hours. In this case, the pipe will be held at a pressure of 1850 psig to establish the pre-
determined MAOP of 1480 psig.
2.0 POST-CONSTRUCTION ACTIVITIES
2.1 MAINTENANCE AND OPERATION
EnCana will maintain the right-of-way for the life of the project. Maintenance will include
repairing soil erosion and reseeding as necessary. The right-of-way will be considered
satisfactorily reclaimed by the Garfield County Vegetation Management personnel when soil
erosion has been stabilized and a vegetative cover at least equal to that present prior to
disturbance and a plant species composition at least as desirable as that present to the
disturbance is established. Establishment of all the species in the seed mixture will be
considered as meeting the composition/desirable species criteria.
EnCana's gathering system is operated using best management practices to meet or exceed
natural gas industry standards. Company personnel monitor and control the gathering system
24/7 to detect any abnormal conditions of the system. Supervisors and field personnel will also
monitor and control the system by driving throughout the project area inspecting facilities on a
periodic basis. Disposal of any liquid and solid waste generated during maintenance and
operation of the pipeline will be done at an approved facility in an environmentally sound and
approved manner.
Encana meets or exceeds the natural gas industry's best practices for installing pipelines. We
utilize such standards as the American Petroleum Institute (API), American Society of
Mechanical Engineers (ASME), National Association of Corrosion Engineers (NACE), American
Society for Testing and Materials (ASTM), National Fire Protection Association (NFPA),
American National Standards Institute (ANSI), Title 49 Code of Federal Regulations Part 192
and National Electric Code (NEG), where applicable. All material used on Encana's pipelines
and construction practices comply with one or more of these standards and/or regulations. We
also have proprietary internal Construction Specifications, Welding Procedures (in accordance
with API-1104, twentieth edition, and ASME 831.8-2007), and Standard Operating Procedures
that dictate how we install, operate, and maintain these assets.
Encana specifies that their pipe purchases meet or exceed ANSIIAPI-5L, Specification for Line
Pipe, latest edition. This document is reviewed, reaffirmed, and revised every five years. This
specification covers the manufacturing of line pipe and the traceability of each pipe joint from
ingot to transportation.
Encana keeps records of the Material Test Reports of the pipeline components, non-destructive
examination records, and strength test records for the life of the pipeline to ensure the integrity
of each pipeline.