HomeMy WebLinkAboutGround Engineering Report 11.01.16I
I BR DU ND
ENGINEERING
Mr. Thomas A. Cook
Tectonic Management Group, Inc.
6695 W 48 1h Avenue
Wheat Ridge, CO 80033
Attn: Mr. Cook ,
November 1, 2016
Subject Summary of Materials Testing Services and
Special Inspection Services, Atlantic Aviation FBO
Addition -Garfield County Airport, Garfield County ,
Colorado
Ground Engineering Job Number: 16-6503
This letter summarizes the special inspection and materials testing services GROUND Engineering
Consultants , Inc. (GROUND) performed during construction of the Atlantic Aviation FBO Addition -Garfield
County Airport Project located in Rifle, Colorado. The special inspection and materials testing services were
performed at times and locations scheduled by the Contractor and/or Subcontractors between October 28th ,
2015 and August 181h, 2016.
During construction, representatives of our office were present on a part time basis to periodically observe the
open hole excavations and structural fills placed for foundations and structural walls . Exterior site
improvements , including sidewalk subgrades, pavement subgrades and aggregate base course were also
periodically tested during placement operations. Nuclear-moisture density testing was periodically performed
on the processed soils at times and locations scheduled .
Representatives of our office observed reinforcing steel placement and performed periodic testing on the
structural concrete placed for the foundation footings, walls and slab on grades at times and locations
scheduled. We also performed periodic testing of site concrete placed for sidewalk, curb and gutter.
Structural steel welded and/or bolted connections were periodically observed during field construction of
structural elements by a certified welding inspector (CWI) at times and locations scheduled .
Based on our review of the test results the field observations to date, it is our opinion that the materials tested
or observed as noted above were in general accordance with project plans, specifications , approval from the
design team, and/or applicable RFl 's.
The observations and materials testing as indicated above were performed as scheduled to provide data to
the Owner, Contractor and Subcontractors to assist them in evaluating the general compliance of the
materials and/or work with the contract documents at the times of our observation and testing . We did not
supervise, direct nor have any control over any of the Contractor's or Subcontractor's work. We were not
responsible for the Contractor's or Subcontractor's scheduling of our services , means , methods, procedures,
techniques, or sequences of construction, nor responsible for ensuring that any Contractor or Subcontractor
performed or completed the work in accordance with the contract documents or construction industry
standards .
GYPSUM OFFICE PO Box 46 ~ I 101 A Ai rpark Drive, Unit 9 I Gypsum, CO 8163 7 I (970) 524·0720 I www.groun de ng .com
ENGLEWOOD I COMME RCE CITY I LOVELAND I GRANBY I GYP SUM
·~I
Atl:1ntlc Aviation • FBO Addition -Garfield County Airport -Final Summary
Garfield County, Colorado
If you have any questions concerning this letter, please contact our office.
Sincerely,
GROUND Engineering Consultants, Inc.
Chris Hutto, C.E.T. Reviewed by Carl Henderson, P.E.
Job No. 16-6503 GROUND Engineering Consultants, Inc. Page 2 of 2
Client Mr Thomas A Cook
liiRDUllD Tectonic Managemenl Group, Inc
6695 W 48111 Avenue
Wheal Ridge, CO 80033
ENGINEERING
lnsp. Type: Frame
Atlantic Aviation -FBO Addition -Rifle
J o b NO ' 16·6503
Date: June 8 2016
Third Party Cover Report
As scheduled, a representative arrived to perform special inspection services. The following is a
summary of the services provided on this date.
Whi'e on site , we performed a preliminary observatioo of the structural wood framing for the FBO Addition main level within
gndhnes J 0 -K.0/80·18.0 Frami ng was observed for stud size and spacing, hardware anchor bolt r.:onnections shear walls for
hold downs boundary studs , and sheathing, window and door types, headers. king/jamb studs. and materials. The following is a
list of items that were observed to be out of conformance w1lh project documents
-114 "x3"x3" plate washers were not installed at shear wall anchor bolt connections to wall bottom plates .
-Some built up columns were not nailed in 4" OC staggered pattern as specified in Typical Details
• Simpson A35 Clips not installed above shear wall top plates
• Nail spacing at shear wall panel edges was greater than specified in some areas .
Rich Reeser with Blue Valley Carpentry was notified of discrepancies and wifl make necessary repairs prior to our next visit Al
the time of observation, other installed items appeared to be in general conformance wilh project documents
'''UPDATE ...
10-31 -2016 ·This report was preliminary pnor lo the City of Rine inspection It is our understanding lhal the noted items above
were corrected/completed and final inspeclions were performed by Structural Engineer and Cily of Rifle and there are no
outstanding discrepancies to date
Total number of pages included in this report : 1
Have outstanding discrepancies been reported this date? Yes
Field Representative : Shane Sorensen