HomeMy WebLinkAboutWelding Inspection ReportsWest Slope Testing & Inspection LLC 3177 Glendam Dr. Grand Junction, CO 81504 Phone:970-434-6988 Cell: 970-260-2844 Dates:.2-14-17 & 2-I6-I 7 Inspection Report Project: Trail Ridge Employee Housing Facility Mancamp Building Building Permit No: BLC0-12-I6-4534 Contractor that Performed Work: Mantex Welding Report#l Page 1of1 Inspection of shop fabrication or field work at job site: Field @ HB Rentals Report: Visually inspected field welding at tie down cable pipe sleeves to skid frames. The welding inspected above appeared to be in general conformance with the quality requirements of the AWS DI.I Structural Welding Code, and appeared to meet/exceed the length requirements as outlined below. Note; per Phil Vaughan's conversation with the structural engineering firm Oddo Engineering I" of acceptable quality weld at each side of the pipe sleeve was adequate for the design loads anticipated. To the best of my knowledge this completes the special inspections of the welding at the die down cable pipe sleeves. Inspectorff echnician: Douglas E Young • + Douglas E Young CWI 96070131 QC1 EXP . 71112017 West Slope Testing & Inspection LLC 3177 Glendam Dr. Grand Junction, CO 81504 Phone:970-434-6988 Cell: 970-260-2844 Dates: 2-14-17 & 2-16-17 Inspection Report Report#l Page 1of1 Project: Trail Ridge Employee Housing Facility Refri/freeze Building Building Permit No: BLC0-12-16-4536 Contractor that Performed Work: Mantex Welding Inspection of shop fabrication or field work at job site: Field @ HB Rentals Report: Visually inspected field welding at tie down cable pipe sleeves to skid frames. The welding inspected above appeared to be in general conformance with the quality requirements of the A WS D 1.1 Structural Welding Code, and appeared to meet/exceed the length requirements as outlined below. Note; per Phil Vaughan's conversation with the structural engineering firm Oddo Engineering l 11 of acceptable quality weld at each side of the pipe sleeve was adequate for the design loads anticipated. To the best of my knowledge this completes the special inspections of the welding at the die down cable pipe .sleeves. Dougla E Young CWI 96070131 OC1 EXP. 71112017 West Slope Testing & Inspection LLC 3177 Glendam Dr. Grand Junction, CO 815 04 Phone:970-434-6988 Cell: 970-260-2844 Dates:.2-14-17 & 2-16-17 Inspection Report Report#} Page 1 of I Project: Trail Ridge Employee Housing Facility Potable Water Skid Building Permit No: None Contractor that Performed Work: Mantex Welding Inspection of shop fabrication or field work at job site: Fiel d @ HB Rentals Report: Visually inspected field welding at tie down cable pipe sleeves to skid frame. The welding inspected above appeared to be in general conformance with the quality requirements of the A WS D 1.1 Structural Welding Code, and appeared to meet/exceed the length requirements as outlined below. Note; per Phil Vaughan's conversation with the structural engineering firm Oddo Engineering l" of acceptable quality weld at each side of the pipe sleeve was adequate for the design loads anticipated. To the best of my knowledge this completes the special inspections of the welding at the die down cable pipe sleeves. Douglas E Young CWI 96070131 QC1 EXP. 7/1/2017 West Slope Testing & Inspection LLC 3177 Glendam Dr. Grand Junction, CO 81504 Phone: 970-434-6988 Cell: 970-260-2844 . Inspection Report Dates:. 2-14-17 & 2-16-17 Project: Trail Ridge Employee Housing Facility Sewer Skid Building Permit No: None Contractor that Performed Work: Mantex Welding Report#l Page 1of1 Inspection of shop fabrication or field work at job site: Field @HB Rentals Report: Visually inspected field welding at tie down cable pipe sleeves to skid frame. The welding inspected above appeared to be in general conformance with the quality requirements of the A WS D 1.1 Structural Welding Code, and appeared to meet/exceed the length requirements as outlined below. Note; per Phil Vaughan's conversation with the structural engineering firm Oddo Engineering 1" of acceptable quality weld at each side of the pipe sleeve was adequate for the design loads anticipated. To the best of my knowledge this completes the special inspections of the welding at the die down cable pipe sleeves. Douglas E Young CWI 96070131 QC1 EXP. 71112017