HomeMy WebLinkAboutConditions of PermitCONDITIONS OF PERMIT
BLCO-02-17-4574
Glenwood Caverns: "Mine Drop" Amusement Ride Building
1850 Transfer Trail Road — Glenwood Springs, Colorado
1) ALL WORK SHALL COMPLY WITH THE 2015 IBC, IMC, IPC, IFGC, IFC, 2009 IECC, AND IN
ACCORDANCE WITH MANUFACTURER'S INSTALLATION INSTRUCTIONS & REQUIREMENTS.
2) REFER TO PLAN ATTACHMENTS FOR GARFIELD COUNTY'S BUILDING REQUIREMENTS, PLAN
REVIEW COMMENTS AND/OR REDLINES, AND INSPECTIONS POLICY.
3) WORK SHALL COMPLY WITH ALL CONDITIONS OF THE SPECIAL -USE PERMIT AND "RURAL" ZONE
DISTRICT REGULATIONS PER GARFIELD COUNTY'S LAND USE & DEVELOPMENT CODE.
4) BUILDING APPROVED AS TYPE V -B CONSTRUCTION, FULLY FIRE-SPRINKLERED WITH THE
FOLLOWING OCCUPANCIES: ASSEMBLY (GROUP A-5), MERCANTILE (GROUP M) & STORAGE
(GROUP S-2).
5) CONTACT LOCAL FIRE DISTRICT FOR INTERNATIONAL FIRE CODE (IFC) REQUIREMENTS AND
OPERATIONAL PERMITS. PROVIDE COPY OF BUILDING PERMIT DRAWINGS TO FIRE DISTRICT
FOR REVIEW & SIGN -OFF. FIRE DISTRICT'S FINAL APPROVAL REPORT IS REQUIRED PRIOR TO
FINAL BUILDING INSPECTION & CERTIFICATE OF OCCUPANCY.
6) THE AMUSEMENT PARK RIDE SITUATED WITHIN THIS BUILDING 15 SEPARATE FROM AND
SPECIFICALLY NOT INCLUDED IN THIS BUIDING PERMIT. PER IBC, CHAPTER 17 "SPECIAL
INSPECTIONS", THE AMUSEMENT RIDE SHALL BE PERMITTED, INSPECTED & APPROVED BY THE
STATE OF COLORADO, DEPT. OF LABOR & EMPLOYMENT. PROVIDE COPY OF APPROVED DESIGN
PLANS FOR BUILDING INSPECTOR REVIEW AT TIME OF FRAME INSPECTION. FINAL
CERTIFICATION & APPROVAL BY STATE IS REQUIRED PRIOR TO FINAL BUILDING INSPECTION &
CERTIFICATE OF OCCUPANCY.
7) ON-SITE WASTEWATER TREATMENT SYSTEM (OWTS) TO COMPLY WITH ALL SETBACKS AND
OTHER REQUIREMENTS PER GARFIELD COUNTY OWTS REGULATIONS. ENGINEER SHALL
PROVIDE FINAL INSPECTION REPORT FOR SEPTIC SYSTEM PRIOR TO FINAL BUILDING
INSPECTION & CERTIFICATE OF OCCUPANCY.
8) ACCESSIBILTY REQUIREMENTS PER 2015 IBC, CHAPTER 11, AND ICC ANSI 117.1-2009. TOILET
FACILITIES SHALL COMPLY WITH ICC ANSI 117.1-2009, SECTIONS 603-609. AMUSEMENT RIDE
SHALL COMPLY WITH IBC, SECTION 1110.4.8 AND ICC ANSI 117.1-2009, SECTION 1102.
9) BUILDING MECHANICAL SYSTEMS INCLUDING: COMBUSTION AIR, DUCTWORK & VENTING
REQUIREMENTS PER INTERNATIONAL MECHANICAL CODE (IMC) AND IECC, SECTION 503.
MECHANICAL ROUGH -IN INSPECTION REQUIRED PRIOR TO FRAMING INSPECTION.
10) PLUMBING REQUIREMENTS PER INTERNATIONAL PLUMBING CODE (IPC). PLUMBING ROUGH -IN
INSPECTION REQUIRED PRIOR TO FRAME INSPECTION.
11) ELECTRICAL REQUIREMENTS, PERMITTING AND INSPECTIONS BY COLORADO STATE ELECTRICAL
BOARD. ELECTRICAL ROUGH -IN APPROVAL IS REQUIRED AT FRAME INSPECTION. ELECTRICAL
FINAL APPROVAL REQUIRED FOR FINAL BUILDING INSPECTION & CERTIFICATE OF OCCUPANCY.
12) VERIFY DIRECTIONAL EXIT SIGNS & EMERGENCY LIGHTING LOCATIONS PRIOR TO ELECTRICAL
ROUGH -IN INSPECTION.