HomeMy WebLinkAboutDrilled Pier Recommendations 03.16.2017H-PI<UMAR
5020 County Road 154
Glenwood Springs, CO 81601
Phone: (970) 945-7988
Fax: (970) 945-8454
Email: hpkglenwood@kumarusa.com
Office Locations: Parker, Glenwood Springs, and Silverthorne, Colorado
March 16, 2017
Karon and Steve Smith 4pip
3909 South Eagle Street ��
Aurora, Colorado 80014 �1
karon@karonsmith.com
karonsmith.com
Project No. 16-7-577
Subject: Drilled Pier Recommendations, Proposed Residence, Lot 53, Heron Crossing at
Ironbridge, Blue Heron Drive, Garfield County, Colorado
Dear Karon and Steve:
As requested by RM Construction, we are providing drilled pier recommendations for foundation
support at the subject site. We previously conducted a subsoil study for design of foundations at
the site and presented our findings in a report dated December 2, 2016, Project No. 16-7-577.
The residence is proposed to be single -story above crawlspace with slab -on -grade garage and
located in the upper, back part of the lot. The recommended settlement precaution with spread
footings was to place at least 3 feet of compacted soil below the footings. As an alternative to
spread footings, a drilled pier foundation which extends down into the underlying dense, gravel
and cobble soil could be used with low settlement potential.
Drilled Pier Alternative: Considering the subsoil conditions encountered in the exploratory
borings on the lot and the nature of the proposed construction, straight -shaft piers drilled into the
underlying gravel and cobble soils can be used for building support. The design and construction
criteria presented below should be observed for a straight -shaft drilled pier foundation system.
1) The piers should be designed for an allowable end bearing pressure of 10,000 psf
and a skin friction of 1,000 psf for that portion of the pier embedded in gravel.
Pier penetration through the upper silt and clay soils should be neglected in the
skin friction calculations.
2) All piers should have a minimum total embedment length of 10 feet and a
minimum penetration into the gravel of 1 foot. The gravel and cobble soils will
tend to cave and penetration into the bearing soils should be limited to about 2
feet.
3) The pier holes should be properly cleaned prior to placement of concrete. The
natural silt and clay soils are stiff which indicates that casing of the holes should
not be required. Some caving and difficult drilling may be experienced in the
bearing soils due to cobbles and possible boulders. Placing concrete in the pier
hole the same day as drilling is recommended.
Karon and Steve Smith
March 16, 2017
Page 2
4) The pier drilling contractor should mobilize equipment of sufficient size to
achieve the design pier sizes and depths. We recommend a minimum pier
diameter of 12 inches.
5) Grade beams and pier caps should have a minimum depth of 3 feet for frost cover
and void form below them is not needed.
6) Free water was not encountered in the borings made at the site and dewatering
should not be needed.
7) A representative of the geotechnical engineer should observe pier drilling
operations on a full -tune basis.
If you have any questions or need further assistance, please call our office.
Sincerely,
H -P = KU MAR
Steven L. Pawlak,
SLP/ksw
cc: RM Construction — (blake)buildwitlum.com)
H -P ; KUMAR
Project No. 16-7-570
H-PKUMAR
Geotechnical Engineering l Engineering Geology
Materials Testing j Environmental
5020 County Road 154
Glenwood Springs, CO 81601
Phone: (970) 945-7988
Fax: (970) 945-8454
Email: hpkglenwood@kumarusa.com
Office Locations: Parker, Glenwood Springs, and Silverthome, Colorado
SUBSOIL STUDY
FOR FOUNDATION DESIGN
PROPOSED RESIDENCE
LOT 53, HERON CROSSING AT IRONBRIDGE
BLUE HERON DRIVE
GARFIELD COUNTY, COLORADO
PROJECT NO. 16-7-577
DECEMBER 2, 2016
PREPARED FOR:
KARON AND STEVE SMITH
3909 SOUTH EAGLE STREET
AURORA, COLORADO 80014
karon@karonsmith.com
TABLE OF CONTENTS
PURPOSE AND SCOPE OF STUDY - 1 -
PROPOSED CONSTRUCTION - 1 -
SITE CONDITIONS - 2 -
SUBSIDENCE POTENTIAL - 2 -
FIELD EXPLORATION - 2 -
SUBSURFACE CONDITIONS - 3 -
FOUNDATION BEARING CONDITIONS - 3 -
DESIGN RECOMMENDATIONS - 4 -
FOUNDATIONS - 4 -
FLOOR SLABS - 5 -
UNDERDRAIN SYSTEM - 6 -
SURFACE DRAINAGE - 6 -
LIMITATIONS - 7 -
FIGURE 1 - LOCATION OF EXPLORATORY BORINGS
FIGURE 2 - LOGS OF EXPLORATORY BORINGS
FIGURES 3 and 4 - SWELL -CONSOLIDATION TEST RESULTS
TABLE 1- SUMMARY OF LABORATORY TEST RESULTS
H-1 KUMAR
Project No. 10-7-577
PURPOSE AND SCOPE OF STUDY
This report presents the results of a subsoil study for a proposed residence to be located on Lot
53, Heron Crossing at Ironbridge, Blue Heron Drive, Garfield County, Colorado. The project
site is shown on Figure 1. The purpose of the study was to develop recommendations for the
foundation design. The study was conducted in accordance with our agreement for geotechnical
engineering services to Karon and Steve Smith dated November 8, 2016. Hepworth-Pawlak
Geotechnical (now H-P/Kumar) previously conducted a preliminary geotechnical study in the
Heron Crossing at Ironbridge development and presented the findings in a report dated February
28, 2014, Job No. 113 471A.
A field exploration program consisting of exploratory borings was conducted to obtain
information on the subsurface conditions. Samples of the subsoils obtained during the field
exploration were tested in the laboratory to determine their classification, compressibility or
swell and other engineering characteristics. The results of the field exploration and laboratory
testing were analyzed to develop recommendations for foundation types, depths and allowable
pressures for the proposed building foundation. This report summarizes the data obtained during
this study and presents our conclusions, design recommendations and other geotechnical
engineering considerations based on the proposed construction and the subsurface conditions
encountered.
PROPOSED CONSTRUCTION
The proposed residence will be a single -story wood frame structure with an attached garage
located on the lot as shown on Figure 1. Ground floor will be structural above crawlspace in the
living area and slab -on -grade in the garage. Grading for the structure is assumed to be relatively
minor with cut depths of about 2 to 4 feet. We assume relatively light foundation loadings,
typical of the proposed type of construction.
If building loadings, location or grading plans change significantly from those described above,
we should be notified to re-evaluate the recommendations contained in this report.
KUMAR
Project No, 167-577
-2 -
SITE CONDITIONS
The lot was vacant and appeared to have been stripped of vegetation and topsoil at the time of
our site visit. The ground surface is relatively flat with a gentle slope down to the north with
roughly two feet of elevation difference across the building area.
SUBSIDENCE POTENTIAL
Bedrock of the Pennsylvanian age Eagle Valley Evaporite underlies the Ironbridge development.
These rocks are a sequence of gypsiferous shale, fine-grained sandstone and siltstone with some
massive beds of gypsum and limestone. There is a possibility that massive gypsum deposits
associated with the Eagle Valley Evaporite underlie portions of the lot. Dissolution of the
gypsum under certain conditions can cause sinkholes to develop and can produce areas of
localized subsidence. A sinkhole opened in the cart storage parking lot located east of the Pro
Shop and south of the Heron Crossing at Ironbridge development in January 2005. Irregular
bedrock conditions have been identified in the affordable housing area located to the south of
Heron Crossing at Ironbridge. Subsurface exploration performed in the area of the proposed
residence on Lot 53 did not encounter voids which could indicate past ground subsidence,
however, the exploratory borings were relatively shallow, for foundation design only. In our
opinion, the risk of future ground subsidence on Lot 53 in Heron Crossing at Ironbridge
throughout the service life of the proposed residence is low and similar to other areas of the
Roaring Fork River valley where there have not been indications of ground subsidence, but the
owner should be made aware of the potential for sinkhole development. If further investigation
of possible cavities in the bedrock below the site is desired, we should be contacted.
FIELD EXPLORATION
The field exploration for the project was conducted on November 15, 2016. Two exploratory
borings were drilled at the locations shown on Figure 1 to evaluate the subsurface conditions.
The borings were advanced with 4 -inch diameter continuous flight augers powered by a truck-
mounted CME -45B drill rig. The borings were logged by a representative of H-P/Kumar.
H -I: KUMAR
Project No. 16.7-577
-3 -
Samples of the subsoils were taken with 1% and 2 inch I.D. spoon samplers. The samplers were
driven into the subsoils at various depths with blows from a 140 pound hammer falling 30
inches. This test is similar to the standard penetration test described by ASTM Method D-1586.
The penetration resistance values are an indication of the relative density or consistency of the
subsoils. Depths at which the samples were taken and the penetration resistance values are
shown on the Logs of Exploratory Borings, Figure 2. The samples were returned to our
laboratory for review by the project engineer and testing.
SUBSURFACE CONDITIONS
Graphic logs of the subsurface conditions encountered at the site are shown on Figure 2. The
subsoils consist of about 13 to 15 feet of stiff, sandy silt and clay overlying dense, silty sandy
gravel and cobbles with boulders. Drilling in the coarse granular soils with auger equipment was
difficult due to the cobbles and boulders and practical auger drilling refusal was encountered in
the deposit.
Laboratory testing performed on samples obtained from the borings included natural moisture
content and density, and finer than sand size gradation analyses. Results of swell -consolidation
testing performed on relatively undisturbed drive samples of the upper fine-grained soils,
presented on Figures 3 and 4, indicate low compressibility under light loading with a low
collapse potential (settlement under constant load) when wetted and moderate compressibility
under additional loading after wetting. The laboratory testing is summarized in Table 1.
The soils were slightly moist and no free water was encountered in the borings at the time of
drilling.
FOUNDATION BEARING CONDITIONS
The silt and clay soils encountered at expected foundation level tend to settle when they become
wetted. A shallow foundation placed on the upper natural silt and clay soils will have a risk of
excessive settlement and building distress. The amount of settlement will be mainly related to
the depth and extent of subsurface wetting and it will be critical to the long term performance of
H-� KUMAR
Project No. 16-7-577
_4 -
the structure that the recommendations for surface drainage contained in this report be followed.
Extensive wetting of the natural soils could cause 3 inches of settlement and mitigation should be
used to reduce the settlement potential. Recommended forms of settlement mitigation include:
1) deep compaction, 2) a deep foundation such as helical piers bearing on the underlying dense
gravel and cobble soils, or 3) a heavily reinforced structural slab foundation. Presented below
are recommendations for compaction below shallow footings with a settlement risk. If
recommendations for a deep foundation or structural slab are desired, we should be contacted.
DESIGN RECOMMENDATIONS
FOUNDATIONS
Considering the subsurface conditions encountered in the exploratory borings and the nature of
the proposed construction, the building can be founded with spread footings bearing on a
minimum 3 feet of compacted structural fill soils with a risk of settlement mainly if the bearing
soils become wetted and acceptable to the owner.
The design and construction criteria presented below should be observed for a spread footing
foundation system.
1) Footings placed on at least 3 feet of compacted fill soils should be designed for an
allowable bearing pressure of 1,200 psf. Based on experience, we expect initial
settlement of footings designed and constructed as discussed in this section will
be about 1 inch or less. Additional differential settlements of about 1 to 11/2
inches could occur if the underlying natural silt and clay soils become wetted.
2) The footings should have a minimum width of 20 inches for continuous walls and
2 feet for isolated pads.
3) Exterior footings and footings beneath unheated areas should be provided with
adequate soil cover above their bearing elevation for frost protection. Placement
of foundations at Ieast 36 inches below exterior grade is typically used in this
area.
H-> KUMAR
Project No. I6-7-577
-5-
4) Continuous foundation walls should be heavily reinforced top and bottom to span
local anomalies such as by assuming an unsupported length of at least 15 feet.
Foundation walls acting as retaining structures should also be designed to resist
lateral earth pressures corresponding to an equivalent fluid unit weight of at least
50 pcf.
5) Any topsoil and loose disturbed soils should be removed from the building area
and down to at least 3 feet below design bearing level. The exposed soils in
footing area should then be moistened and compacted. Structural fill should
consist of low permeable soil such as the onsite soils or CDOT Class 6 base
course extended at Least 2 feet beyond footing edges and compacted to at least
98% of standard Proctor density at near optimum moisture content.
6) A representative of the geotechnical engineer should observe the building
excavation for bearing conditions and evaluate compaction of the structural fill
during its placement and prior to concrete placement.
FLOOR SLABS
The natural on-site soils, exclusive of topsoil, are suitable to support lightly loaded slab -on -grade
construction with a risk of settlement if the bearing soils are wetted. We recommend at least 2
feet of compacted structural fill similar to that placed below footings be placed below the floor
slab to help mitigate the settlement potential. To reduce the effects of some differential
movement, floor slabs should be separated from all bearing walls and columns with expansion
joints which allow unrestrained vertical movement. Floor slab control joints should be used to
reduce damage due to shrinkage cracking. The requirements for joint spacing and slab
reinforcement should be established by the designer based on experience and the intended slab
use. A minimum 4 -inch layer of relatively well graded sand and gravel such as road base should
be placed beneath interior slabs for support. This material should consist of minus 2 -inch
aggregate with at least 50% retained on the No. 4 sieve and less than 12% passing the No. 200
sieve.
M -I KUMAR
Project No. 16-7-577
-6 -
All fill materials for support of floor slabs should be compacted to at least 95% of maximum
standard Proctor density at a moisture content near optimum. Required fill can consist of the on-
site soils devoid of vegetation and topsoil or a suitable imported material such as road base.
UNDERDRAIN SYSTEM
It is our understanding the ground finished floor elevation of the residence is at or above the
surrounding grade. Therefore, a foundation drain system is not required. It has been our
experience in the area that local perched groundwater can develop during times of heavy
precipitation or seasonal runoff. Frozen ground during spring runoff can create a perched
condition. We recommend below -grade construction, such as retaining walls and basement
areas, if provided, be protected from wetting and hydrostatic pressure buildup by an underdrain
and wall drain system. An underdrain is not recommended around the crawlspace area to help
limit the potential for wetting below the shallow footings.
If the finished floor elevation of the proposed structure has a floor level below the surrounding
grade, we should be contacted to provide recommendations for an underdrain system. AlI earth
retaining structures should be properly drained.
SURFACE DRAINAGE
It will be critical to the building performance to keep the bearing soils dry. The following
drainage precautions should be observed during construction and maintained at all times after the
residence has been completed:
1) Inundation of the foundation excavations and underslab areas should be avoided
during construction.
2) Exterior backfill should be adjusted to near optimum moisture and compacted to
at least 95% of the maximum standard Proctor density in pavement and slab areas
and to at least 90% of the maximum standard Proctor density in landscape areas.
3) The ground surface surrounding the exterior of the building should be sloped to
drain away from the foundation in all directions. We recommend a minimum
H-� KUMAR
Project No, 16-7-577
-7 -
slope of 12 inches in the first 10 feet in unpaved areas and a minimum slope of 3
inches in the first 10 feet in paved areas. Graded swales should have a minimum
slope of 3%.
4) Roof downspouts and drains should discharge well beyond the limits of all
backfill.
5) Landscaping which requires regular heavy irrigation should be located at Ieast 10
feet from foundation walls. Consideration should be given to use of xeriscape to
reduce the potential for wetting of soils below the building caused by irrigation.
LIMITATIONS
This study has been conducted in accordance with generally accepted geotechnical engineering
principles and practices in this area at the time of this study. We make no warranty either
express or implied. The conclusions and recommendations submitted in this report are based
upon the data obtained from the exploratory borings drilled at the locations indicated on Figure
1, the proposed type of construction and our experience in the area. Our services do not include
determining the presence, prevention or possibility of mold or other biological contaminants
(MOBC) developing in the future. If the client is concerned about MOBC, then a professional in
this special field of practice should be consulted. Our findings include interpolation of the
subsurface conditions identified at the exploratory borings and variations in the subsurface
conditions may not become evident until excavation is performed. If conditions encountered
during construction appear different from those described in this report, we should be notified so
that re-evaluation of the recommendations may be made.
This report has been prepared for the exclusive use by our client for design purposes. We are not
responsible for technical interpretations by others of our information. As the project evolves, we
should provide continued consultation and field services during construction to review and
monitor the implementation of our recommendations, and to verify that the recommendations
have been appropriately interpreted. Significant design changes may require additional analysis
or modifications to the recommendations presented herein. We recommend on-site observation
H -I KUMAR
Project No. 16-7.577
-8 -
of excavations and foundation bearing strata and testing of structural fill by a representative of
the geotechnical engineer.
Respectfully Submitted,
H -P `KUMAR
Steven L. Pawlak, P
Reviewed by:
Daniel E. Hardin, P.E.
SLPtksw
Q!
`4,11
!x el'J'i.m,E'h�'.��j���
H-� KUMAR
Pmjcct No. 16-7.577
LOT 52
B' UE HERRON DRIVE
LOT 53
LOT 54
10 0 s0 20
APPROXIMATE SCALE—FEET
16-7-577
H-P44KUMAR
LOCATION OF EXPLORATORY BORINGS
Fig. 1
5
d
- 0
--5
— 10
•--- 15
BORING 1 BORING 2
19/12
WC=5.4
DD=99
-200=83
17/12
WC=5.9
DD=95
17/12
14/12
13/12
WC=5.3
DD=101
-200=68
18/12
WC=6.3
DD=93
52/6
10
15
--- 20 20
16-7-577
H-Pk-KUMAR
LOGS OF EXPLORATORY BORINGS
DEPTH -FEET
Fig. 2
LEGEND
7
li
19/12
f
NOTES
SILT AND CLAY (ML—CL); SANDY, STIFF, SLIGHTLY MOIST, LIGHT BROWN, SLIGHTLY
POROUS.
GRAVEL AND COBBLES (GM—GP); SLIGHTLY SILTY, SANDY, PROBABLE BOULDERS, DENSE,
SLIGHTLY MOIST, BROWN. ROUNDED ROCK.
RELATIVELY UNDISTURBED DRIVE SAMPLE; 2—INCH I.D. CALIFORNIA LINER SAMPLE.
DRIVE SAMPLE; STANDARD PENETRATION TEST (SPT), 1 3/8 INCH I.D. SPLIT SPOON
SAMPLE, ASTM D-1586.
DRIVE SAMPLE BLOW COUNT. INDICATES THAT 19 BLOWS OF A 140—POUND HAMMER
FALLING 30 INCHES WERE REQUIRED TO DRIVE THE CALIFORNIA OR SPT SAMPLER 12 INCHES.
PRACTICAL AUGER REFUSAL.
1. THE EXPLORATORY BORINGS WERE DRILLED ON NOVEMBER 15, 2016 WITH A 4—INCH DIAMETER
CONTINUOUS FLIGHT POWER AUGER.
2. THE LOCATIONS OF THE EXPLORATORY BORINGS WERE MEASURED APPROXIMATELY BY PACING
FROM FEATURES SHOWN ON THE SITE PLAN PROVIDED.
3. THE ELEVATIONS OF THE EXPLORATORY BORINGS WERE NOT MEASURED AND THE LOGS OF THE
EXPLORATORY BORINGS ARE PLOTTED TO DEPTH.
4. THE EXPLORATORY BORING LOCATIONS SHOULD BE CONSIDERED ACCURATE ONLY TO THE
DEGREE IMPLIED BY THE METHOD USED.
5. THE LINES BETWEEN MATERIALS SHOWN ON THE EXPLORATORY BORING LOGS REPRESENT THE
APPROXIMATE BOUNDARIES BETWEEN MATERIAL TYPES AND THE TRANSITIONS MAY BE GRADUAL.
6. GROUNDWATER WAS NOT ENCOUNTERED IN THE BORINGS AT THE TIME OF DRILLING.
7. LABORATORY TEST RESULTS:
WC = WATER CONTENT (%) (ASTM D 2216);
DD = DRY DENSITY (pef) (ASTM 0 2216);
—200= PERCENTAGE PASSING NO. 200 SIEVE (ASTM 0 1140).
16-7-577
H-P�KUMAR
LEGEND AND NOTES
Fig. 3
CONSOLIDATION - SWELL
2
0
— 2
_4
— 6
— 8
— 10
— 12
.1
16-7-577
1.0 APPi1E0 PRESS4. K5F
H -P- KUMAR
I0
SWELL -CONSOLIDATION TEST RESULT
100
Fig. 4
SAMPLE OF: Sandy Slit and Clay
FROM: Boring 1 0 5'
WC = 5.9 X, DD = 95 pcf
I
1
ADDITIONAL COMPRESSION
UNDER CONSTANT PRESSURE
DUE TO WETTING
Thu, SMI .RK/ Awl/ M4' W ti
,rryl,. 14•L- Rr WIYf, Iprl
MIM Lf b
IM ivork.+d. l./post
AAL mtleul Ifth MAIM qp.M I
INf AMNIA* f,Y .. NI
111 Ail G -76r6.
.1
16-7-577
1.0 APPi1E0 PRESS4. K5F
H -P- KUMAR
I0
SWELL -CONSOLIDATION TEST RESULT
100
Fig. 4
n...• rr ln.A.Vr p 1N
rw .. I.. . r'46914.
M u.s 1 -
— .11.1 Y. nprNro.L ..aol In
Mom" 4,'4 r �w�sww, i
SAMPLE OF: Sandy Silf and Clay
FROM: Baring 2 0 10'
WC = 6.3 X. DD = 93 pcf
ADDITIONAL COMPRESSION
UNDER CONSTANT PRESSURE
DUE TO WETTING
.1
16-7-577
1.0 APPLIED PRESSURE - I Si ID I00
H -PKU MAR
SWELL -CONSOLIDATION TEST RESULT
Fig. 5
5
3
1
1
1
H-PKUMAR
TABLE 1
SUMMARY OF LABORATORY TEST RESULTS
Project No. 16-7-577
SAMPLE LOCATION
NATURAL
MOISTURE
CONTENT
(%)
NATURAL
DRY
DENSITY
(pct)
GRADATION
PERCENTCOMPRESSIVE
PASSING
NO. 20(1
SIEVE
ATTERBERG LIMITS
UNCONFINED
STRENGTH
(PSF)
SOIL OR
BEDROCK TYPE
BORING
_
DEPTH
(ft)
GRAVEL
(%)
SAND
(%)
LIQUID
LIMIT
(°lo!
PLASTIC
INDEX
(%)
1
2%
5.4
99
83
Sandy Silt and Clay
5
5.9
95
Sandy Silt and Clay
2
5
5.3
101
68
Sandy Silt and Clay
10
6.3
93
Sandy Silt and Clay