HomeMy WebLinkAbout02.10 Binder 1 - Section 11• APPROVED PHASING SCHEDULE • • • SPRING VALLEY RANCH PUD ESTIMATED DEVELOPMENT PHASING SCHEDULE Phase Elements Estimated Start of Construction Estimated Completion of Construction Phase 1 50 Golf Lots April 2007 (see Note 1 on Sheet 5) November 2008 0 Estate Lots 0 Wilderness Cabins 0 Duplex Units Sales Office Lot Clubhouse Lot South Golf Course Parcels Fire station Lot Metro District Lot CR114 Improvements: From the end of the existing asphalt near CMC to the Main Entrance CR115 Improvements: From the intersection of CR114 to the intersection with Black Kettle Court (road to the Metro District Facility) Phase 2 17 Golf lots April 2007 through April 2008 depending on economic and marketing conditions 20 Months after Start of Construction 15 Estate lots 0 Wilderness Cabins 0 Duplex Units Golf Maintenance Facility Lot Driving Range Parcel Phase 3 26 Golf lots April 2007 through April 2009 depending on economic and marketing conditions 20 Months after Start of Construction 32 Estate lots 0 Wilderness Cabins 0 Duplex Units Neighborhood Park #1 CR115 Improvements: From the Intersection with Black Kettle Court to the Landis Creek Entrance Phase 4 19 Golf lots April 2008 through April 2010 depending on economic and marketing conditions 20 Months after Start of Construction 2 Estate lots 33 Wilderness Cabins 0 Duplex Units Parcels for the First 9 Holes of the North Golf Course Phase 5 16 Golf lots April 2008 through April 2011 depending on economic and marketing conditions 20 Months after Start of Construction 0 Estate lots 0 Wilderness Cabins 8 Duplex Units MAY 2005 PAGE 1 OF 5 • SPRING VALLEY RANCH PUD ESTIMATED DEVELOPMENT PHASING SCHEDULE Phase Elements Estimated Start of Construction Estimated Completion of Construction Phase 6 0 Golf lots April 2009 through April 20 Months after Start of Construction 27 Estate lots 2012 7 Wilderness Cabins depending on economic 8 Duplex Units and marketing conditions 1 Meadow Lot Neighborhood Park #2 Phase 7 0 Golf lots April 2009 through April 2013 depending on economic and marketing conditions 20 Months after Start of Construction 14 Estate lots 3 Wilderness Cabins 4 Duplex Units Phase 8 0 Golf lots April 2009 through April 2014 depending on economic and marketing conditions 20 Months after Start of Construction 13 Estate lots 0 Wilderness Cabins 4 Duplex Units CR114 Improvements: From the End of the Phase 1 Improvements near CMC to the Intersection with State Hwy 82 Phase 9 18 Golf lots April 2010 through April 2015 depending on economic and marketing conditions 20 Months after Start of Construction 3 Estate lots 0 Wilderness Cabins 6 Duplex Units Phase 10 0 Golf lots April 2010 through April 2016 depending on economic and marketing conditions 20 Months after Start of Construction 1 Estate lots 17 Wilderness Cabins 0 Duplex Units Phase 11 25 Golf lots April 2010 through April 2017 depending on economic and marketing conditions 20 Months after Start of Construction 0 Estate lots 5 Wilderness Cabins 0 Duplex Units 10 Village Center Single Family Lots 12 Village Center Multi Family Units Phase 12 0 Golf lots April 2011 through April 2018 depending on economic and marketing conditions 20 Months after Start of Construction 7 Estate lots 10 Wilderness Cabins 0 Duplex Units 10 Village Center Single Family Lots 8 Village Center Multi Family Units 2 Village Center Commercial Lot MAY 2005 PAGE 2 OF 5 SPRING VALLEY RANCH PUD ESTIMATED DEVELOPMENT PHASING SCHEDULE Phase Elements Estimated Start of Construction Estimated Completion of Construction Phase 13 0 Golf lots April 2011 through April 2019 depending on economic and marketing conditions 17 Months after Start of Construction 10 Estate lots 0 Wilderness Cabins 0 Duplex Units 5 Village Center Single Family Lots 12 Village Center Multi Family Units 0 Village Center Commercial Lot Phase 14 0 Golf lots April 2011 through April 2020 depending on economic and marketing conditions 17 Months after Start of Construction 10 Estate lots 0 Wilderness Cabins 0 Duplex Units 0 Village Center Single Family Lots 18 Village Center Multi Family Units 2 Village Center Commercial Lot Ranch Phase 1 11 Ranch Lots April 2007 through April 2011 depending on economic and marketing conditions 20 Months after Start of Construction Ranch Phase 2 11 Ranch Lots April 2007 through April 2012 depending on economic and marketing conditions 20 Months after Start of Construction Emergency Access Road through Ranch Phase 3 and down Landis Creek (see Note 2) Ranch Phase 3 10 Ranch Lots April 2007 through April 2013 depending on economic and marketing conditions 20 Months after Start of Construction Ranch Phase 4 15 Ranch Lots April 2008 through April 2014 depending on economic and marketing conditions 20 Months after Start of Construction Ranch Phase 5 16 Ranch Lots April 2009 through April 2014 depending on economic and marketing conditions 17 Months after Start of Construction MAY 2005 PAGE 3 OF 5 • • • SPRING VALLEY RANCH PUD ESTIMATED DEVELOPMENT PHASING SCHEDULE Phase Elements Estimated Start of Construction Estimated Completion of Construction Ranch Phase 6 6 Ranch Lots April 2009 through April 2015 depending on economic and marketing conditions 20 Months after Start of Construction Ranch Phase 7 5 Ranch Lots April 2009 through April 2016 depending on economic and marketing conditions 20 Months after Start of Construction Ranch Phase 8 3 Ranch Lots April 2009 through April 2017 depending on economic and marketing conditions 20 Months after Start of Construction Ranch Phase 9 3 Ranch Lots April 2009 through April 2018 depending on economic and marketing conditions 20 Months after Start of Construction Ranch Phase 10 3 Ranch Lots April 2009 through April 2019 depending on economic and marketing conditions 20 Months after Start of Construction Ranch Phase 11 8 Ranch Lots April 2009 through April 2020 depending on economic and marketing conditions 17 Months after Start of Construction Ranch Open Space Phase 1 Open Space Parcel April 2005 April 2006 MAY 2005 PAGE 4 OF 5 • • • SPRING VALLEY RANCH PUD ESTIMATED DEVELOPMENT PHASING SCHEDULE Note 1 (applies to entire schedule): The estimated start date for Phase 1 of April 2007 is based on the assumption that the Final Plat for Phase 1 will be approved prior to April 2007. In the event that the Final Plat for Phase 1 is approved after April 1, 2007, then the start date for Phase 1 will be the April following the Final Plat approval. In this event, the start dates for each subsequent phase shall be adjusted accordingly to correspond to the difference between the estimated start date for Phase 1 of April 2007 and the actual start date for Phase 1 based on the date of approval of the Final Plat for Phase 1. The reference to "depending on economic and market conditions" refers to the period of time between the start dates. With respect to the time periods set forth in the column entitled "Estimated Completion of Construction," these estimated time periods may be shorter if required in the applicable subdivision improvements agreement. Notwithstanding any dates to the contrary, the Final Plats for all lots in all phases must be approved no later than 15 years after the date of the approval of the Final Plat for Phase 1. Each phase must be developed sequentially in a manner to insure the installation of the appropriate infrastructure and other related improvements for each phase consistent with the requirements of the Garfield County Zoning Resolution and Subdivision Regulations. Note 2: The emergency access road must meet the applicable minimum standards of the International Fire Code and the design must be acceptable to the Glenwood Springs Fire Department H:1012691141Digital Submittal FileslShortcuts to Computer FileslPhasing - updated mapsl[development schedule 20050530.xIs]Develop MAY 2005 PAGE 5 OF 5