HomeMy WebLinkAboutConditions of PermitCONDITIONS OF PERMIT
BLCO-09-16-4422
Double D Investments, LLC — Dean Dombrowski
Remodel of Existing Mixed -Use Occupancy Building
43 County Road 110 (Cattle Creek Road)
Glenwood Springs, Colorado
1) ALL WORK SHALL COMPLY WITH THE 2015 IBC, IMC, IPC, IFGC AND 2009 IFC & IECC, AND IN
ACCORDANCE WITH MANUFACTURER'S INSTALLATION INSTRUCTIONS & REQUIREMENTS.
2) REFER TO PLAN ATTACHMENTS FOR GARFIELD COUNTY'S BUILDING REQUIREMENTS AND
INSPECTIONS POLICY.
3) WORK SHALL COMPLY WITH "COMMERCIAL LIMITED" ZONE DISTRICT REGULATIONS PER
GARFIELD COUNTY'S LAND USE & DEVELOPMENT CODE.
4) BUILDINGS ARE APPROVED AS TYPE V -B NON-SPRINKLERED CONSTRUCTION WITH MIXED-
USE OCCUPANCIES INCLUDING: OFFICE (GROUP B), LOW -HAZARD STORAGE (GROUP S-2),
PRIVATE GARAGE (GROUP U) AND RESIDENTIAL (GROUP R-3). ALL OCCUPANCIES ARE
INTENDED FOR SINGLE -TENANT USE.
5) PRIOR TO CONSTRUCTION, APPLICANT SHALL CONTACT LOCAL FIRE DISTRICT FOR I.F.C.
REQUIREMENTS INCLUDING FIRE ALARM SYSTEMS & SMOKE ALARMS. PROVIDE COPY OF
BUILDING PERMIT DRAWINGS TO FIRE DISTRICT FOR REVIEW & SIGN -OFF. FINAL APPROVAL
REPORT FROM FIRE DISTRICT IS REQUIRED PRIOR TO FINAL BUILDING INSPECTION &
CERTIFICATE OF OCCUPANCY.
6) EXISTING ON-SITE WASTEWATER TREATMENT SYSTEM (OWTS) TO BE ABANDONED, AND
WASTE LINE CONNECTION TO BE TIED INTO NEW SEPTIC SYSTEM FOR FUTURE BUILDING
(GARFIELD COUNTY BUILDING PERMIT #BLCO-06-16-4269). ENGINEER TO UP-SIZE
PROPOSED SEPTIC SYSTEM AS ORIGINALLY SUBMITTED WITH THE ABOVE -REFERENCED
BUILDING PERMIT, COMPLYING WITH ALL SETBACKS AND OTHER REQUIREMENTS PER
GARFIELD COUNTY OWTS REGULATIONS. PROVIDE UPDATED SEPTIC SYSTEM DESIGN AND
INSTALLATION PRIOR TO FINAL BUILDING INSPECTION & CERTIFICATE OF OCCUPANCY.
7) ACCESSIBILTY REQUIREMENTS PER 2015 IBC, CHAPTER 11, AND ICC A117.1-2009.
(NOTE: ACCESSIBILITY IS NOT REQUIRED AT UPPER LEVEL RESIDENTIAL UNITS PER SECTION
1104.4, EXCEPTION #4).
8) LOCKS, LATCHES & LANDINGS PER 2015 IBC, SECTION 1010.
9) LIGHT AND VENTILATION PER 2015 IBC, CHAPTER 12.
10) BUILDING MECHANICAL SYSTEMS (COMBUSTION AIR, DUCTWORK & VENTING) TO COMPLY
WITH INTERNATIONAL MECHANICAL CODE (IMC) AND IECC, SECTION 503. MECHANICAL
ROUGH -IN INSPECTION REQUIRED PRIOR TO FRAMING INSPECTION.
11) PLUMBING REQUIREMENTS PER INTERNATIONAL PLUMBING CODE (IPC). PLUMBING
ROUGH -IN INSPECTION REQUIRED PRIOR TO FRAME INSPECTION.
12) ELECTRICAL REQUIREMENTS, PERMITTING AND INSPECTIONS BY COLORADO STATE
ELECTRICAL BOARD. ELECTRICAL ROUGH -IN APPROVAL IS REQUIRED AT FRAME INSPECTION.
ELECTRICAL FINAL APPROVAL REQUIRED FOR FINAL BUILDING INSPECTION & CERTIFICATE
OF OCCUPANCY.