Loading...
HomeMy WebLinkAboutSite Plan9 Wirkler-Design Calculations OWTS N °�O 16 F j 401111100._ The existing OWTS is being upgraded with a replacement absorption field to / J serve an existing three bed -bedroom residence. The onsite wastewater treatment system (OWTS) is designed based on the design flow for a 3 -bedroom residencial capacity with expansion potential. • From the Regulation 43 usage table : 11 Minimum population based on 3 bedrooms = 6 persons. Additional population based on bedrooms assuming 1 person per bedroom. Gallons per day per person =75 gal/person/day, No peaking factor Max. Design flow (Qd)gallons/day = (# of people) x (avg. flow)gal/person/day. 6® Design flow Qd = 6*75=450 gpd Septic Tank Design: Use a 1,500 gallon, two compartment concrete septic tank with an effluent filter outlet sanitary tee in the second chamber. Tank shall be installed with I/ II •• �...... o ••••.... sealed concrete risers and lids to the finish grade surface. Continue use of existing septic tonk to serve as a raw sewage pump station to lift sewage to the the new septic tank. Sub Surface Conditions and Testing: -� Subsurface soil investigations and USDA soil texture method tests were performed by Sopris Engineering. The soils in the area of the proposed INSTALL CHAMBER absorption field were sampled and characterized by application of the USDA Lu < , o/ END CAP ON ALL END soil texture method analysis. The soils were tested to determine the hydraulic ABSORPTION/TREATMENT FIELD 54 CHAMBERS (TYP)10 loading rate and the appropriate absorptive surface depth in the native soils. 0-4 CHAMBERS W/ END CAPS .� The soils below 6 to 8 inches of topsoil consist of medium dense silt loam ... �S�► - with moderate blocky to granular structure overlying deep cobbles and gravel -GARAGE/BARN Pin a sandy clay loam matrix to the 7 foot depth explored. These soils appear . to consist of outwash materials consisting of sand, silt, clay, co g < ? IX a Pie glacial gravels, __doe' .� UNDERGROUNDs°�cobbles and small boulders. c-1- INSTALLED 4"RISER PIPEINSPECT s\ -s � 'o ®• .•® O. EACH ENION PORTS AT joco TD CHAMBER (TYP) ahe soil tnative ils consisting ed of�omt 1-21nfet X below e withemodeaatece are block characterized to ran aas g >- co w 00 Z } w O V 0 jTRIC10" structure. This soil haan effective loading rate for conventionalsoil vJ��� ..• O. . treatment of 0.60 gal/S.F./day for a level 1 conventional treatment system. . . `. The equivalent percolation rate is approximately 16-25 minutes per inch. ABSORPTION/TREATMENT FIELD, INSTALLED`3 GRAVITY CHAMBER TRENCHES Increased quantities of cobbles and gravel are encountered at depths below 5 ( w p < p _ U ap CO •� 4„ PVC +� . .• WITH 18 CHAMBERS PER TRENCH FOR A TOTAL ABSORPTION AREA OF 648 SF� feet. No free water was encountered in excavations on site. Groundwater levels DISTRIBUTION PIPES (525 SF REQUIRED). THE SYSTEM IS PLUMBED FOR EQUAL GRAVITY are expected to be well below 10 feet below the existing surface grades. The .4. �.• ..• EXISTIING LEACH FIELD DISTRIBUTION. THE CHAMBERS ARE INSTALLED ON LEVEL GRADE IN EACH soils appear suitable for a conventional shallow absorption field consisting of ABONDONED IN PLACE • O. TRENCH. THE BOTTOM OF EACH TRENCH WAS EXCAVATED TO A MAX DEPTH gravelless infiltration chamber units. -4... OF 3 FT WITHIN THE NATIVE LOAM. INSTALLED WITH A MIN 12" NATIVE N BACKFILL COVER OVER TOP OF THE CHAMBERS. SEPTIC FIELD FINISH Treatment -Soil Treatment Unit/ Absorption System Design: 'RIS E NGINEERING, LLC. CIVIL CONSULTANTS 502 MAIN STREET CARBONDALE, CO 81623 (970) 704-0311 FAX: (970)-704-0313 LIFT SURFACE APPROX. 3" ABOVE ADJACENT GRADES. INSTALLED ' SCHD-40 SEWAGE PRESSURE PIPE AT The treatment/absorption field is designed based on utilizing the effective 2.5%SLETOINSURE DRAINBACKTOPUMP TANK -_-=- Long Term Acceptance Rate (LTAR) for the native soils and the application of SEWAGE PUMP BASIN. -GARAGE `\ appropriate loading factors for a soil treatment unit (STU) system utilizing INSTALLED SIMPLEX SEWAGE PUMP ASSEMBLY TO " PVC GRAVITY SEWER LINE gravity distribution to gravelless infiltrative chamber units in a trench RAW SEWAGE TO NEW PRIMARY SEPTIC TANK / ' STUBOUT AT 2% SLOPE ± � confirguration, for treatment across the native soil absorptive surface. The new ,•---- / DISTRIBUTION BOX WITH BAFFLE treatment system will consist of sewage collection and conveyance via a ik INSTALLED LEVEL ON COMPACTED BASE. sewage pump station that will transport raw sewage to a new septic tank for INSTALLED 48" DIA. ECCENTRIC CONCRETE INSTALLED RISERS AND LID TO SURFACE detention and gravity distribution to the new STU via a distribution box. MH RISER W/ IRON RING/LID, STEPS . Long Term Acceptance Rate (LTAR) W/HDPE RISERS AND LIDS INSTALLED AT THE FINISHED GRADE litir.--1114 = INSTALLED 2 -COMPARTMENT 1250 -GALLON RIBBED PLASTI SEPTIC TANKConsidering the application of the new state regulation 43: T ,INSTALLED l V ° EXISTING SEPTIC SURFACE. Receiving Wastewater Treatment Level 1; loading rate for silt loam is (0.60 INLET SANITARY TEE AND OUTLET EFFLUENT FILTER SANITARYgal./S.F./day) for soil type 2.; SINGLE COMPARTMENT 1250 GALLON CONCRETE TEE. DEPTH TO TOP OF TANK FROM PROPOSED GRADE IS APPROXIMATLEY Loadingfactors; (Table 10-2, Gravityapplication trenches = 1.0 and TANK WITH LID APPROX. 6" BELOW SURFACE GRADE t� 1 2" SCHED 40 PVC PIPE 1.5'. PP ) (Table 10-3, gravelless chambers = 0.7) 0.) V /// ,t, �� HIGH POINT TRANSITION 2" TRANSPORT A(sf) = �: A = Area; INSTALLED PUMP SYSTEM CONTROL ( C9 \ PIPE TO 4" GRAVITY TANK INFLUENT PIPE LTAR LTAR = 0.60 Gal/S.F./day for soil type 2, silt loam PANEL ON EXTERIOR WALL LIQ I _ v Qd = flow (gal/day) = 450 gpd v ) L.F.1=1.0 Gravity Distribution \L.F.2=0.7 Chambers 25 '= A(sf) = 450 gpd x 1.0 x 0.7 = 525 S.F. O Lu o 12-5-2011 7N .� 0.60 Gal/S.F./day ■ Number of quick -4 chambers:U 525 S.F = 44 chambers Use 54 chambers m U EXISTING 12 S.F./Chamber 1*111111 Ai 3-BEROOM RESIDENCE 54 chambers x 12 S.F./chamber provides 648 S.F. of absorption/treatment area that equates to a Design Capacity of 555 gpd.suitable for an additional (� 80 bedroom on the the existing residence or to be used as paritial capactiy for a future dwelling up to a 3 bedroom capacity with the addition of 2 additional ' d trenches and tank. MO ° Use 54 Quick -4 chambers in three trenches 74' long by 3' wide with 18 , d chambers units per trench plus two end caps as delineated on the plan. The d ° - .. ° septic tank effluent will be gravity distributed to the head of each chamber . ° as ..° d. a : .. .. - °- . 10° , ° row via individual distribution pipes from a distribution box. Additional soil . evaluation will be performed during construction to verify the soils in the excavations. GRAPHIC SCALE , ° .. .. ° -d ., .: Q 1a 20 40 t.° ° °. o - (, LLJ OWTS SYSTEM AS CONSTRUCTED NOTES EN a d "' ° ° 4 a ° d ° °° (4'I ` ET) d ' "D,inch-=,,. c ft. d " d ° °. ° �-° ° - °° °.d a �° d • ° ' GENERAL NOTES 1. ALL MATERIALS AND INSTALLATION CONFORMS TO STATE AND COUNTY ONSITE WASTEWATER TREATMENT SYSTEM (OWTS) REGULATIONS. ( 2. ALL SEWER LINES INSTALLED WERE SCH 40 PVC PIPE AND INSPECTION PORTS USE WERE SDR -35. 1 3. THE SEPTIC TANK WAS INSTALLED LEVEL ON COMPACTED CLASS 6 BASE MATERIAL OVERLYING NATIVE COMPACTED SOIL. INSTALLED WATERTIGHT RISERS WITH ACCESS LIDS AT THE FINISHED SURFACE GRADE. TANK WAS FLIPPED SITE REVISION: BACKFILLED WITH SUITABLE NATIVE SOIL FREE OF BOULDERS & ROCK IN 1. THE OWTS AS SHOWN ON THE PLAN AND THE DETAILS WERE DESIGNED BY SOPRIS EXCESS OF 3" DIA. ENGINEERING. 2. THE EXISTING CONDITIONS AND PLAT INFORMATION BY THE SEXTON SURVEY 4. SANITARY BAFFLE TEE INSTALLED ON THE SEPTIC TANK INLET AND OUTLET COMPANY. PLUMB IN POSITION TO ALLOW EASY INSPECTION AND MAINTENANCE OF 3. PRIMARY OWNER NAME & ADDRESS: WIRKLER, NORMAN E & MARGARET & CHRIS TANK FROM THE TANK ACCESSES. b Z C PO BOX 1030 CARBONDALE, CO, 81623 5. INSTALLED A 4" EFFLUENT FILTER ON THE 4" BAFFLE OUTLET TEE OF THE NWIRKLER@YAHOO.COM SEPTIC TANK. THE FILTER SHOULD BE INSPECTED EVERY SIX MONTHS. THE OWTS RETROFIT AND UPGRADE AB -SYSTEM PLAN 4. PROPERTY ADDRESS: 9663 STATE HIGHWAY 82, GARFIELD COUNTY, CO EFFLUENT FILTER SHALL BE MAINTAINED AND CLEANED WHEN THE TANK IS EM PLAN PERIODICALLY PUMPED OR AS NECESSARY. 5. LEGAL DESCRIPTION: LOTS 4 & 5 OF THE MARTIN PARCEL IN SECTION: 20 TOWNSHIP: 7 RANGE: 88 OF THE 6TH P.M., GARFIELD COUNTY, CO 6. THE CONTRACTOR INSTALLED SEWER LINES, SEPTIC TANK AND RISERS 6. PARCEL ID #:2393-202-00-111 WATERTIGHT. ALL PLUMBING FIXTURES AND OWTS COMPONENTS SHALL BE Pump Selection fora Non-PressurizedSystem- singleramllyhesldenceProiect ��� 7. GARFIELD COUNTY OWTS CONSTRUCTION PERMIT #: SEPT -04-18-5184 MAINTAINED TO AVOID SURFACE OR GROUNDWATER FROM ENTERING THE 18020-WIRKLER1 SEWAGE PUMP 1250 TANK TO FIELD aik��� 8. SIZE OF LOT: 7.1 ACRES SYSTEM AND TO PREVENT LEAKAGE FROM THE SYSTEM. IN-HOUSE ,e 9. CONTRACTOR: GREAT LAKES CONSTRUCTION. PLUMBING FIXTURES SHALL BE MAINTAINED TO PREVENT EXCESS WATER Cr) N o Parameters -1 �sw.�a� CONTACT: CHRIS LAKE00 FROM ENTERING THE SEPTIC SYSTEM. O Discharge Assembly Size 2.00 inches ADDRESS: POB 313, NEW CASTLE 81647 Transport Length 100 feet Transport Pipe Class 40 CELL: 970 618 2813 Orenco Systems' 7. THE DIMENSIONS AND NOTES SHOWN ON THE PLAN INDICATE GENERAL O Q Transport Line Size 2.00 inches Incorporated EM: GLCCHRIS@YAHOO.COM AND DIMENSIONS OF OWTS COMPONENTS. Q DistrbutngValveModel None Max Lift 12 feet aangthg the Way the " , n 6080 Elevation 00 Design Flow Rate 10 gpm _LOCATION Meld Darr Wastewater' 8. THE ABSORPTION TRENCHES WERE EXCAVATED TO LEVEL GRADE IN NATIVE RESIDENCE .ARBONDALE )UNTY, COLOI TREATMENT ZECORD DRAWINC Flow Meter None inches •Add-on•FridionLosses CROWN FIELD TRENCH TO 4" PVC INLET PORT EARTH. THE TRENCH BOTTOM AND SIDEWALLS WERE SCARIFIED. INSTALLED 24" IRON RING & COVER 0 feet DIVERT SURFACE WATER IN END CAP REVEGATATION 4' DIA MH ACCESS KISER USE Calculations 9. THE LEACHING CHAMBERS WERE INSTALLED LEVEL WITH A MINIMUM COVER MAIN LEVEL FLOOR 4' CONCRETE BARREL SECTION Transport velocity os fps TOPSOIL LAYER rux �� �' OF 12 TO 36 INCHES. so & 2' ECCENTRIC CONIC SECTION Frictional Head Losses BACKFILL WITH SCREENED ' 10. END CAPS WITH INSPECTION PORTS WERE INSTALLED ON THE END Loss through Discharge 0.2 `'/\y/\y/\y/\/� 6070 feet ONSITE SOILS FREE OF ROCKS IN / / \\\\\ \\ \\ \\ \ CHAMBERS IN EACH TRENCH. Loss in Transport o.2 feet Loss -,,.!. < - EXCESS OF 3" DIAMETER OR USE =' 4= :`_ ,:n2.'-;'_:=: /// , 2' HDPE DR 9 OR SCHED-40 PVC through Valve 0.0 feet . _ __ L. ` a' PRESSURE TRANSPORT PIPE Loss through Flowmeter 0.0 feet •Add onFrdonLosses 0.0 feet x 3/4" TO 1.5' SCREENED ROCK _` �`t �,;.'-:\//� 11. VERTICAL INSPECTION PORTS WERE INSTALLED FROM THE PRE MARKED HOLE ° fo 6.67 -'<-M.:-. s':~.':<'< ' ,-...- <-_\\N ON THE TOP OF EACH END CHAMBER END CAP. (TYP. BOTH ENDS OF BASEMENT LEVEL FLOOR r A/' LEACHING '� LJ CC Pipe Volumes c / EACH ROW)THE PORTS HAVE PIPE CAPS INSTALLED ABOVE GRADE. ,+ • //� CHAMBER �-�--I " U m - SIMPLEX 2 SOLIDS HANDLING Volt7ranspotune 17.4 gals m X A/` N w ■ LEACHING / L CO Q SEWAGE PUMP HP E , FILTER FABRIC 12. THE CHAMBERS WERE BACKFILLED WITH EXCAVATED MATERIAL VOID OF 3" Y a 6060 Minimum Pum Requirements p q "c CHAMBER /// PLUS ROCKS TO AT LEAST 12 INCHES ABOVE THE TOP OF THE CHAMBERS. Q CO EL= Design Flow Rate 10.0 1 1 \\\ 1 1 J WfNcr�j "1 gpm ao�PFswv:oI BACKFILL LAYER NATURAL OFF FLOAT EL= - coN Total Dynamic Head 12.4 feet//\ /\///\//�//�//�/ < 5 ONSITE SOILS FREE OF ROCKS �jAA�j VAS ,, 13. INSTALLATION OF LEACHING CHAMBERS IS IN CONFORMANCE WITH THE DATUM ELEVLL e. /AA�Av MANUFACTURES INSTALLATION INSTRUCTIONS. �j� LJJ o 8055.00 EXISTING CONCRETE /\\//, //,///�/�/�\/,\%'\\'' _ Ct I - 00 SEPTIC TANK N SELECTtSOIL REPLACEMENT 14 ARE R D THE FOUR 06 06 ao `� FIELDS MUSTALLY CORNERS WITHE TH NSPECTIONSPORTS. THE BET PROTECTED FROM SCARIFY/TILL BOTTOM SURFACE TO AS NEEDED IF EXCESSIVE _� C Q LID L.D N. VEHICULAR AND LIVESTOCK TRAFFIC. A DEPTH OF 3" AND RAKE LEVEL COBBLES OR BOULDERS ARE _ lel l.0 ENCOUNTERED. USE 4" FILTER e 15. THE ABSORPTION FIELD SURFACES WERE SLIGHTLY MOUNDED TO DIVERT NOTE: ALL CHAMBERS IN EACH TRENCH MUST BE INSTALLED co w SAND LEVELLING COURSE. SURFACE DRAINAGE AWAY FROM THE FIELD. C 5 uemc°we: - ON LEVEL GRADE. MAINTAIN 6' OF UNDISTURBED SOIL is,r,,,,f C 10 UNDISTURBED EARTH SILT ',•, BETWEEN TRENCHES. THE ELEVATION OF ADJACENT TRENCHES ����� RE 16. THE ENTIRE ABSORPTION FIELD SURFACES HAVE BEEN SEEDED AND 0) _ V) 1+00 P pcwra: LOAM SOIL. t .e"'•, MAY VARY. MAXIMUM DEPTH OF TRENCHES NOT TO EXCEED T '; MULCHED TO RE ESTABLISH VEGETATED COVER. Z Pump Optimal Rarge:- 30" BELOW PROPOSED SURFACE GRADES. INLET AND END .%� GX Ni' ' '`_ OWTS PROFILE Op .vvgPont o CAPS ARE TO BE INSTALLED ON EACH END CHAMBER ROW. e -ti�..,'. 4 f 17. THE ABSORPTION FIELD WERE INSTALLED PER THE REQUIRED SETBACK 0 0 e 40 Net Discharge 80 20 100 ��n,: • DISTANCES: 10 FEET FROM ANY PROPERTY LINE. 28377 ;tr ` 25 FEET FROM ANY POTABLE WATER SUPPLY LINE. IF EXCESSIVE LARGE COBBLES OR BOULDERS ARE ENCOUNTERED "PIP.//84.4• IN ANY PART OF THE EXCAVATION, OVER EXCVATE AND BACKFILL , 20 FEET FROM ANY OCCUPIED DWELLING. 100 FEET FROM ANY WELL, SPRING OR CISTERN. DATE: 10-18-2018 WITH SAND OR SUITABLE SCREENED NATIVE SOILS. (�' S'SiONAI. E����•'50 FEET FROM ANY STREAM OR WATER COURSE. SEWAGE PUMP CURVE ' r'1 ' JOB NO. 18020.01 CHAMBER TRENCH CROSS SECTION DETAIL n " N.T.S. M:\3800dwgs\18020\18020-AB-OWTS-Record2.dwg SHEET Cl