Loading...
HomeMy WebLinkAboutCorrespondenceDave Argo From: Sent: To: Subject: Dave Argo Monday, December LL,20L7 8:0L AM 'fetzerco@gmail.com' Fetzer Remodel: Permit #BLRE-l-1-l-7-5011 Scott: This email is a follow-up to a phone message left on your voicemail on Tuesday last week regarding proposed alterations to your Aspen Glen residence. I have begun my review of your proposed plans for these alterations but don't have enough information submitted from you to complete my review. More specifically, we need for the following items to be addressed: a. Site Plan - We need to see a site plan clearly illustrating the extent of proposed work and how this relates to the existing building footprint, building envelope and property lines. b. Work Description - lt appears that several items are included in your scope of work, but we need for you to confirm the inclusion of the following list as it's not entirely clear from your submitted application & drawings: ,,á Timber retaining walls (see next item below) ,/ Stairway: L-shaped as shown on plan, but is this stone/concrete or timber? ¡ Stone walkway New door at basement - lndicate location of this new door on your plan o Master Bedroom Deck/Railings - lndicate location of this deck/railing o Anything else? c. Timber Retaining Walls - lt appears as though you are adding timber retaining walls to access the new door you have installed at the basement. lf these timber walls exceed -feet in height (as indicated on your sketches) they need to be designed & wet stamped by a Colorado licensed Professional Engineer. Provide our office with stamped Engineered drawings. d. DRB Approval - Have you already received DRB approval for these changes to your residence? Although not specifically required by our office, I am simply curious if the DRB has approved these alterations to your residence. Please provide us with this additional requested information at your earliest opportunity so that we can complete our plan review. Until I hear back from you, we won't be able to finalize our review and issue a building permit for your project. Thank you for your assistance - Dave Argo Plans Examiner Garfield Counly Community Development Department 708 9th Street, Suite 407 Glenwood Springs, CO 81607 Tel : 970-945-8212 Ext. 1610 E m a i I : d q rg o @ g a rf i e ld -co u nty. com We b : g o rf i e I d-co u n ty. co m CONFTDENTIALITY NOTTCE: This emai! communicotion ond any files transmitted along with it øddressed. tf you hove received this emoil in error, please immediøtely notify the sender by et Hea*e¡¡¿ Wi+h sÒo+l tA lzlúltt...?d;Y Nr¡rø rù¿. wPonx- 10øu hyvl;æ\ 6[u wiq prwlL AVvNgf,^'oV1 ... vwIW a\l løli(ll'liu4t Øas4^ di¿^ æÞ2 1 H o tttcotç ttcrs,Associ ation at,Aspen GIen, Inc. Design Review Committee August 7,2018 Mr. Glenn Hartman Garfield County Building and Planning Department 108 8th Street, Suite 201 Glenwood Springs, CO 81601 viø email Re: Referral for the Proposed Amended Plat for Lot G-1, Aspen Glen, Filing I Dear Glenn, The Aspen Glen Design Review Committee (DRC) reviewed the proposed Seconded Amended Final Plat, prepare by Tuttle Surveying Services dated7ll9l2018 to amend the building envelope for Lot G-l/102 Leonis Lane attheir meeting August 1,2018. The proposed adjustment was considered to accommodate minor exterior improvements proposed by the property owner: an exit stair from the basement and replacement of a dilapidated ground level deck. The single-family home was built in the early 2000's but in2013 the County adopted a policy that limited the type of improvements to property that could project beyond the building envelope and some of these improvements cannot be made. Therefore, the property owner has requested a building envelope adjustment to provide the area within the building envelope to make these improvements. The DRC noticed property owners within the vicinity of the property, no objections were noted. The adjustment does not add more square footage to the original size of the envelope and does not compromise the established setbacks for this property. Therefore, DRC recommends approval to the Garfield County Board of County Commissioners with the following conditions: 1. A copy of the recorded amended plat shall be provided to the Aspen Glen DRC. 2. The DRC has only approved the plat amendment. Any further improvements to property shall be submitted for DRC review and approval. If you have any questions, please do not hesitate to contact me. Sincerely, bt/r). l¿*r.t¿nr Leslie Lamont, Administrator Aspen Glen Design Review Committee Cc: Scott Fetzer 0080 Bald Eagle Way Carbondale, CO 81623 Tel: (970) 963-3362 Email : leslielamont@aspenglenltoa.c om 1 Dave Argo From: Sent: To: Cc: Attachments: Subject: Leslie Lamont < leslielamont@aspenglenhoa.com> Tuesday, August 07,20L8 L0:1-9 AM Glenn Hartmann 'Scott Fetzer'; Dave Argo Aspen Glen BEA Recommendation Lot G-L/\O2 Leonis Lane Garco Rec BEA 8-7-18.pdf Good morning. Please find attached a letter from the DRC recommending approval of a proposed Building Envelope Adjustment/Plat Amendment for Lot G-1 in Aspen Glen. Please do not hesitate to contact me with any questions. Thank you, Leslie Leslie Lamont, Administrator Design Review Committee Homeowners Association at Aspen Glen, lnc 80 Bald Eagle Way Carbondale CO 81623 970-963-8434 www.aspenglenhoa.com 1 Dave Argo From: Sent: To: Cc: Dave Argo Thursday, August 09, 201-8 8:26 AM 'Scott Fetzer' Leslie Lamont; Glenn Hartmann RE: 102 Leonis Lane Aspen Glen Lot G-LSubject: Scott: Thanks for your call yesterday inquiring about the status of Garfield County approvals related to proposed improvements at your Aspen Glen property. As we discussed, Glenn Hartmann here in our office will need to weigh in on the plat amendment for adjustment of the Building Envelope because this is a Planning Dept. issue - not a Building Dept. issue. Glenn is currently on vacation but will return to the office on Monday, August 13. ln addition, you mentioned that you are interested in modifying the deck plans you have previously submitted to the Building Dept. More specifically, you described an enclosed roof and/or expanded interior area which are not presently illustrated on the plans prepared by Bob Oddo. My suggestion is to have Bob's office update these plans to reflect your current thinking, so that they properly revise their plans while you are finalizing approval of the amended final plat with our planning Dept. Otherwise, you will run the risk of additional delays with the plan review of your submitted plans and subsequent building inspections at the job site. Following this course of action will provide you with the easiest path to a smooth approval process and will allow you to finish up your project in the quickest manner. Thanks again for your inquiry, and l'm sure that Glenn will be in touch with you early next week after he returns to the office. Dave Argo Plans Examiner Garfield Couttty Community Development Department L08 gth Street, Suite 401 Glenwood Springs, CO 81601 Tel: 970-945-8212 Ext. 1670 E mo il : d o rgo @ ga rfi eld -cou nty.com We b : ga rfield-cou nty. com CONF)DENT)ALIT| NOTTCE: This emoil commun¡cotion ond øny files tronsmitted along with it are intended only for the person or ent¡ty to which it is addressed. tf you have received this emoil in error, pleose immediotely notify the sender by emoil and delete it from your fíles' From: Leslie Lamont Imailto:leslielamont@aspenglenhoa.com] Sent: Tuesday, August 07,2OI8 10:L9 AM To: Glenn Ha rtmann <ghartman n@garfield-county'com> Cc:'Scott Fetzer'<fetzerco@gmail.com>; Dave Argo <dargo@garfield-county.com> Subject: Aspen Glen BEA Recommendation Lot G-t/I02 Leonis Lane Good morning. please find attached a letterfrom the DRC recommending approvalof a proposed Building Envelope Adjustment/Plat Amendment for Lot G-1 in Aspen Glen. Please do not hesitate to contact me with any questions. Thank you, Leslie I Leslie Lamont, Administrator Design Review Committee Homeowners Association at Aspen Glen, lnc. 80 Bald Eagle Way Carbondale CO 8L623 970-963-8434 www.âsoe oa.com 2 Dave Argo From: Sent: To: Subject: Andy Schwaller Wednesday, April 10, 2019 3:08 PM Wade Patton; Dave Argo; Brooke Winschell; Lindsay Krol RE: Fetzer 102 Leonis Ln Aspen Glen Iøupw o( Þ.P, Sounds good. The new owner inherits the violations. From: Wade Patton Sent: Wednesday, April 10, 2079 2:54 PM To: Andy Schwaller <aschwaller@garfield-county.com>; Dave Argo <dargo@garfield-county.com>; Brooke Winschell <bwinschell@garfield-county.com>; Lindsay Krolclkrol@garfield-county.com> Subject: Fetzer 102 Leonis Ln Aspen Glen ljust got a call and this house is under contract with an open NOV violation and Open building permits. Deborah with Aspen Glen was going to try to contact the real estate agent that is selling the home to make them aware of the issues. Just a heads up in case you get a call from anyone asking about this property. Wade Patton Garfield County Code Enforcement 108 8th Street, Suite 401 Glenwood Springs, CO 81601 Telephone: 97 0-945-1377, ext 1530 Email: wpatton @qarfield-cou ntv.com \r'uùivu¡awwl 6ltnnb 4 fru*l plat ... ù+lwwix v,ç¿7 tD qo Ovl ll,Lc )þov,* al<o varl$T AÞt^ virþfi¡¡ w[u¿L Dave Argo From: Sent: To: Cc: Subject: Attachments: Dave Argo Wedrresday, Marclr 27,2019 9:58 AM Wade Patton G lenn Ha rtmann; Andy Schwal ler (aschwal ler@ garfield -county.com) Fetzer - Aspen Glen Aspen Glen Scott Fetzer.docx Wade: Just wanted to let you know that Scott Fetzer's building permit for adding a basement egress door, associated retaining walls and rebuild of wood deck are now finished up on my end, but Glenn is still awaiting final mylars from Tuttle for the Amended Final Plat with new building envelope. FYI: I have attached a copy of my "Conditions for Permit" including item #6 specifically addressing the ADU issue in the basement. Have you already sent out an N.O.V.? Given the status of his situation with regard to this item, just thought it would be appropriate to include it and make you aware. Døve Argo Plans Examiner Gnrfield Coutrty Community Development Department 708 9th Street, Suite 407 Glenwood Springs, CO 81607 Tel: 970-945-8212 Ext. 7670 Emoil : do rgo @ g o rfi eld-cou nty.com Web : go rfield-cou nty. com 1 CONDITIONS OF PERMIT B LRE-1_1-t7 -5011 Scott Fetzer Alterations to Existing Single-Family Residence 1,02 Leonis Lane, Carbondale Aspen Glen PUD - Filing l-, Lot G-L 1) ALL NEW WORK SHALL COMPLY W|TH THE 2015 TNTERNATTONAL RESIDENTIAL CODE (r.R.c.)AND 2009 TNTERNATIONAL ENERGY CONSERVATION CODE (l.E.C.C.) 2',) TMPROVEMENTS ARE SUBJECT TO ALL APPLICABLE ITEMS CONTAINED lN THE ATTACHED "GARFIELD COUNTY BUILDING REQUIREMENTS". NUMBERED REFERENCES AS NOTED ON PLANS REFER TO SPECIFIC ITEMS ON THIS LIST. 3) THIS BUtLDtNG PERMtT lS TSSUED FOR ALTERATTONS TNCLUDING A NEW ON-GRADE EGRESS DOOR FROM BASEMENT WITH ASSOCIATED RETAINING WALLS AND REBUILD OF AN EXISTING WOOD DECK. 4) ALL PROPOSED WORK UNDER THtS PERMIT SHALL BE FULLY CONTAINED WITHIN LIMITS OF REVISED BUILDING ENVELOPE PER AMENDED FINAL PLAT DATED MARCH t,2OT9. PROVIDE IMPROVEMENT SURVEY VERIFYING COMPLIANCE PRIOR TO FINAL INSPECTION & CERTIFICATE OF OCCUPANCY. 5) STRUCTURAL ENGTNEER TO PROVTDE TNSPECTTON REPORT FOR CONSTRUCTION OF VERSA-LOK RETAINING WALLS PRIOR TO FRAME INSPECTION. 6) AN ACCESSORY DWELLTNG UNtT (A.D.U.)AT BASEMENT OF RESTDENCE lS SPECIFICALLY NOT AN APPROVED USE UNDER THIS BUILDING PERMIT, AND ANY SUCH USE MAY REQUIRE A LAND USE CHANGE PERMIT UNDER PROVISIONS OF GARFIELD COUNTY,S LAND USE & DEVELOPMENT CODE. ADU,s MAY ALSO NOT BE ALLOWED WITHIN THE ASPEN GLEN P.U.D. - HOMEOWNER TO VERIFY WITH DESIGN REVIEW ADMINISTRATOR. 7l pRovtDE GUARDRAIL AT PERTMETER OF DECK PER ITEM #38 OF PLAN ATTACHMENTS 8) VER|Fy CARBON MONOXTDE & SMOKE ALARMS AT ALL BEDROOMS WITHIN EXISTING DWELLTNG (REFERENCE IrEMS #32,#33 OF PLAN ATTACHMENTS). 9) ELECTRTCAL PERMtTTtNG AND TNSPECTTONS BY COLORADO STATE ELECTRICAL BOARD. ELECTRICAL ROUGH-IN APPROVAL IS REQUIRED AT FRAME INSPECTION. ELECTRICAL FINAL APPROVAL IS REQUIRED FOR FINAL INSPECTION & CERTIFICATE OF OCCUPANCY. Dave Argo From: Sent: To: Cc: Subject: Dave Argo Friday, March 22,2019 8:48 AM Wade Patton Andy Schwaller RE: lllegal ADU at Aspen Glen - Lot G1, 102 Leonis Lane Wade: The permit for the egress door at basement is still in my "pending" file (for over L2 months now) and includes a deck replacement/addition that encroached outside of the platted building envelope. Scott Fetzer did work together with Glenn to get an amended building envelope, but I don't think that has been totally signed offyet. What l've been told by Deborah isthat he'salso mired in a potentialbankruptcyon the property-which issomewhat ironic because as he explained to me, he purchased this existing residence out of bankruptcy himself. Dave From: Wade Patton Sent: Thursday, March 21,,2OL9 t2:44 PM To: Dave Argo Cc: Andy Schwaller Subject: FW: lllegal ADU at Aspen Glen - Lot Gl", 102 Leonis Lane Just a quick bit of research on this one. lt looks like to basement was permitted to be finished and they also got a permit to add an egress to the basement. I will tell Deborah if I hear from her. Thanks Wade From: Dave Argo Sent: Thursday, March 2t,2OL9 t2:O7 PM To: Deborah Prince <dprince@aspenglenhoa.com> Cc: Wade Patton <wpatton@garfield-countv.com> Subject: lllegal ADU at Aspen Glen - Lot Gl, 102 Leonis Lane Deborah Based on your recent observations of an illegal basement ADU at Scott Fetzer's residence, you may want to file a formal code compliance violation with our code enforcement officer, Wade Patton. The violation form is located on our website and you can download via this web-link: https://www.garfield- countv.com/comm unitv-develo nme nt/code-e nfo rcement.esox lf you'd like to speak with Wade about this issue, you can reach him at 97O-945-821"2, extension 1-530 or wpatton@sarfi eld-countv.com and I have copied Wade on this email correspondence I will be sending you an email response about Exline's project later this afternoon. Døve Argo Plans Examiner 1 Dave Argo Dave, Thank you so much for this info. lt appears Scott may be waiting to see how things go with the foreclose before spending any more funds. I shared with Lance Luckett just in case Scott loses the property. Best, Deborah From: Dave Argo [ma i lto :da rgo @ga rfie ld-cou nty.com] Sent: Friday, February 8,zOLg 9:50 AM To: Deborah Prince <dprince@aspenglenhoa.com> Cc: Glenn Hartmann <ghartmann@garfield-county.com>; Becky Wheelersburg <bwheelersburg@garfield-county.com> Subject: RE: Fetzer Lot G-l Deborah: I checked with both Becky Wheelersburg & Glenn Hartmann here at our office and here's a summary of where we are with Scott Fetzer's project: From: Sent: lo: Cc: Subject: a a Deborah Prince <dprince@aspenglenhoa.com> Friday, February 8,2019 1 1:28 AM Dave Argo Glenn Hartmann; Becky Wheelersburg RE: Fetzer Lot G-1 Plannins Approvals for Bldg. Envelope Adiustment - He has not followed through with payment of S100 fee for Plat Review (over 60 days past due). His open file for the Amended Final Plat will expire at the end of February, unless he requests and receives an extension. Glenn Hartmann has made Fetzer aware of this, and supposedly he will be scheduling a time to review any final requirements for getting this Amended Final Plat completed before expiration of his planning approval. Building Permit Approvals - Final review & approval is pending the Bldg. Envelope Adjustment described above. Once the FinalAmended Plat is finalized, we require submission of accurate plans from an Engineer reflecting actual scope of work to be completed - including site plan indicating placement of new construction within confines of the new Building Envelope. During my last conversation with Fetzer, he indicated that he wanted to place a roof over the proposed deck and this is not illustrated on the plans we now have. Hope that information is helpfulto you. Dave Argo Plans Examiner Garfield Coanty Community Development Department 708 9th Street, Suite 401 Glenwood Springs, CO 81601 Tel: 970-945-82L2 Ext. 1610 Ema il : do rg o @ g o rfield-county.com Web : garfleld-county.com From: Deborah Prince lmailto:dprince@aspenglenhoa.com] Sent: Thursday, Februa ry 7, 20L9 5:57 PM To: Davc Argo Subject: Fetzer Lot G-l Hello Dave, I understand the Fetzer house is in foreclosure and that Scott Fetzer must come up with the money by Feb 26th for a court date Feb 27th. Would you be able to send me an update on his file at Garfield County? ls he up to date with you financially? I would like to be prepared either way. Many thanks, Deborah Deborah Prince Administrator Design Review Committee Homeowners Association at Aspen Glen, lnc. 80 Bald Eagle Way Carbondale CO 81623 970-366-286L www.aspenglenhoa.com 2 Dave Arqo From: Sent: To: Cc: Subject: a a a a O Dave Argo Wednesday, June 06, 2018 4:4O PM 'fetzerco@gmail.com' Leslie Lamont Fetzer Aspen Glen - Building Permit #BLRE-1-1-17 -50LL Scott After preliminary review of updated/amended information you recently submitted for remodel of your Aspen Glen residence, we cannot proceed with approval of your building permit, because you have not addressed the site plan requirement which was stipulated in my December L1-,2OL7 email sent to you following review of your initial building permit application. Prior to our approval of your revised building permit application we require submittal of an "lmprovement Location Certificate" (l.L.C.) as prepared by a Professional Licensed Surveyor in Colorado which clearly illustrates the following items: Property Boundary Lines Building Envelope Any other Easements or Encumbrances Extents of Existing Building Footprint including decks, porches, walkways, etc. All New Proposed construction including decks, patios, retaining walls, etc. One other quest¡on I have is how high above finish grade will the new deck be? The Engineer's drawings don't address this issue. Please provide us with additional information. Once we receive the requested Surveyor's site plan as described above, and assuming that placement of all existing/new improvements comply with Garfield County requirements, we should be able to quickly finalize our review & issue a building permit. Thank you for your assistance. Dave Argo Plans Examiner Garficld County Communíty Development Department 708 'th Street, Suite 407 Glenwood Springs, CO 81607 Tel: 970-945-8272 Ext. 1670 E mø i I : d q rg o @ g o rf i e ld -co u nty. com Web : g a rfield -county. com CONFIDENTTALITY NOTICE: This email communicat¡on ønd any files transmítted olong with it are intended only for the person or ent¡ty to wh¡ch ¡t is oddressed. lf you hove received this email in error, pleøse immediately notify the sender by email ond delete it from your files. Dave Arqo From: Sent: To: Leslie Lamont <leslielamont@aspenglenhoa.com> Wednesday, June 06, 20LB 5:00 PM Dave Argo RE: Fetzer Revised Scope of WorkSubject: We did approve what he proposed but subject to submitting to us what he gets approved by you and I required copies of what he submits to you to gain a building permit. He cannot start until he gets his bldg. permit obviously.....and I have a gatel Leslie Lamont, Administrator Design Review Committee Homeowners Association at Aspen Glen, lnc 80 Bald Eagle Way Carbondale CO 81623 970-963-8434 www.aspenglenhoa.com From: Dave Argo <da rgo@ga rfield-county.com> Sent: Wednesday, June 6, 2018 4:40 PM To: Leslie Lamont <leslielamont@aspenglenhoa.com> Subject: Fetzer Revised Scope of Work Leslie: Thanks for sharing your time & insights earlier today . . . I have sent a follow-up email to Scott and copied you on that correspondence. FYI: Attached is Scott Fetzer's "new" scope of work. lt sounds as though he may have perhaps overstated his status with the DRC? Dave Argo Plans Examiner Gurfield County Community Development Department 708 8th Street, Suite 407 Glenwood Springs, CO 81607 Tel: 970-945-8272 Ext. 1610 Emq il : d o roo@ qo rfie ld-cou ntv.com Web : gø rfi eld-cou nty. com CONFtDENTtALtTy NOTTCE: This emoil communicotion and any files tronsmitted olong with it ore intended only for the person or ent¡ty to which it is oddressed. If you have received this emoil in error, pleose immediately notify the sender by emøil ond delete it from your files' 1 Dave Argo From: Sent: To: Cc: Subject: a Dave Argo Friday, February 8,2019 9:50 AM 'Deborah Prince' Glenn Hartmann; Becky Wheelersburg RE: Fetzer Lot G-1 Deborah I checked with both Becky Wheelersburg & Glenn Hartmann here at our office and here's a summary of where we are with Scott Fetzer's project: planning Approvals for Bldg. Envelope Adiustment - He has not followed through with payment of SL00 fee for plat Review (over 60 days past due). His open file for the Amended Final Plat will expire at the end of February, unless he requests and receives an extension. Glenn Hartmann has made Fetzer aware of this, and supposedly he will be scheduling a time to review any final requirements for getting this Amended Final Plat completed before expiration of his planning approval. o Buildins Aoorovals -Final review & approval is pending the Bldg. Envelope Adjustment described above. Once the Final Amended plat is finalized, we require submission of accurate plans from an Engineer reflecting actual scope of work to be completed - including site plan indicating placement of new construction within confinesof the new Building Envelope. During my lastconversation with Fetzer, he indicatedthat hewanted to place a roof over the proposed deck and this is not illustrated on the plans we now have. Hope that information is helpful to you Dave Argo Plans Examiner Garfielú Couttly Community Development Department 1.08 gth Street, Suite 407 Glenwood Springs, CO 8160L Tel: 970-945-8212 Ext. 1-670 Em o i I : da rgo @ g a rfi e ld-cou nty. com Web : ga rfi eld -cou nty.com From: Debora h Prince Imailto:dprince@aspenglenhoa.com] Sent: Thursday, FebruaryT,2Ot9 5:57 PM To: Dave Argo Subject: Fetzer Lot G-l Hello Dave, I understand the Fetzer house is in foreclosure and that Scott Fetzer must come up with the money by Feb 26th for a court date Feb 27th. Would you be able to send me an update on his file at Garfield County? ls he up to date with you financially? I would like to be prepared either way. Many thanks, Deborah 1 Deborah Prince Administrator Design Review Committee Homeowners Association at Aspen Glen, lnc. 80 Bald Eagle Way Carbondale CO 81623 970-366-286L www.âsDen enhoa.com 2 Dave Argo From: Sent: lo: Subject: Becky Wheelersburg Tuesday, February 5,2019 12:15 PM Andy Schwaller; Becky Wheelersburg; Brooke Winschell; Claire Dalby; Dave Argo; Glenn Hartmann; Jim Wilson; Kirby Wynn; Lindsay Krol; Matt Provost; Patrick Waller; Sheryl Bower; Tricia Parish; Wade Patton Scott Fetzer applications Good Afternoon! lf any of you have applications in progress for Scott Fetzer, please place them on hold. He has an unpaid invoice that is 2 months old ($100) and he will not answer my e-mails or phone calls. I left a message again today. As soon as I hear from him and receive payment, I will let you know so that his application(s) may proceed. Sincerely, Becky Wheelersburg Adm i n istrative Assistant Garfield County Community Development 970-945-1377 Extension 1550 bwheelersbu rq@garfield-county.qqm 108 8th Street Suite 401 Glenwood Springs CO 81601 1 Dave Argo From: Sent: To: Cc: Subiect: Dave Argo Thursday, November 29, 2018 9:19 AM 'Scott Fetzer' Leslie Lamont; Glenn Hartmann; Brooke Winschell RE: 102 Leonis Lane Aspen Glen Lot G-1 Scott I wanted to reach back out to you regarding status of your Building Permit for your planned deck improvement project at Aspen Glen just to make sure that you are aware that your pending approval of the Land Use Permit reconfiguring the platted Building Envelope - with whom you have been working together with Glenn Hartmann in our office - is a completely separate permit from the Building Permit' Items previously discussed with you regarding changes to the prior plans submitted to our office (and described more fully in my August 9 email to you as highlighted in RED TEXT below) have not yet been addressed per our records. lf your intent is to vary from the original plans prepared by Bob Oddo, please submit these plans to our office so that we can issue you a Building Permit at our earliest opportunity once the Land Use Change Permit has been finalized. ln addition, plans for the deck improvement project needs to clearly illustrate that proposed improvements will be located within the new Buitdíng Envelope. This can be easily shown by including a copy of the Surveyor's Site Plan which you had prepared for the Land Use Change Permit. Thank you for your attention to this matter Døve Argo Plans Examiner G*rfield CottntTt Community Development Department 708 9th Street, Suite 407 Glenwood Springs, CO 87607 Tel: 970-945-8212 Ext. 1610 Emo il : d o rgo @ g o rfie ld-cou nty. com Web : go rfie ld-cou nty.com From: Dave Argo Sent: Thursday, August 9,2Ot8 8:26 AM To:'Scott Fetzer' Cc: Leslie Lamont; Glenn Hartmann Subject: RE: 102 Leonis Lane Aspen Glen Lot G-1 Scott: Thanks for your call yesterday inquiring about the status of Garfield County approvals related to proposed improvements at your Aspen Glen property. As we discussed, Glenn Hartmann here in our office will need to weigh in on the plat amendment for adjustment of the Building Envelope because this is a Planning Dept. issue - not a Building Dept. issue. Glenn is currently on vacation but will return to the office on Monday, August L3. 1 ln addition, you mentioned that you are interested in modifying the deck plans you have previously submitted to the Building Dept. More specifically, you described an enclosed roof and/or expanded interior area which are not presently illustrated on the plans prepared by Bob Oddo. My suggestion is to have Bob's office update these plans to reflect your current thinking, so that they properly revise their plans while you are finalizing approval of the amended final plat with our Planning Dept. Otherwise, vou will run the risk of additional delavs with the plan review of vour submitted plans and subsequent building inspections at the iob site. Following this course of action will provide you with the easiest path to a smooth approval process and will allow you to finish up your project in the quickest manner. Thanks again for your inquiry, and l'm sure that Glenn will be in touch with you early next week after he returns to the office. Dave Argo Plans Examiner Garfield Count¡, Community Development Department 1-08 8th Street, Su¡te 401. Glenwood Springs, CO 8760L Tel: 970-945-8272 Ext. 7610 E mo i I : d o rq o @ q o rf i e ld -co u ntv. co m Web : ga rfi el d-cou nty.com CONFIDENTIALITY NOTICE: This emoil commun¡cot¡on ønd øny files tronsmitted olong with it are intended only for the person or ent¡ty to which ¡t is addressed. lf you hove received this emoil in error, pleose immediately notify the sender by email and delete it from your files. From: Leslie Lamont [mailto:leslielamont@aspenelenhoa.com] Sent: Tuesday, August 07,2OL8 10:19 AM To: G len n Ha rtma nn <gha rtma n n @ga rfield-co u ntv.com> Cc: 'Scott Fetzer'<fetzerco@gmail.com>; Dave Argo <dargo@garfield-countv.com> Subject: Aspen Glen BEA Recommendation Lot G-1,/1O2 Ler¡nis Lane Good morning. Please find attached a letter from the DRC recommending approval of a proposed Building Envelope Adjustment/Plat Amendment for Lot G-l in Aspen Glen. Please do not hesitate to contact me with any questions. Thank you, Leslie Leslie Lamont, Administrator Design Review Committee Homeowners Association at Aspen Glen, lnc 80 Bald Eagle Way Carbondale CO 81623 970-963-8434 www.aspenglenhoa.com 2 Dave Argo From: Sent: To: Subject: Attachments: Dave Argo Wednesday, June 06, 20L8 4:4O PM Leslie Lamont Fetzer Revised Scope of Work Fetzer Revised Scope of Work.pdf Leslie Thanks for sharing your time & insights earlier today . . . I have sent a follow-up email to Scott and copied you on that correspondence. FYI: Attached is Scott Fetzer's "rìew" scope of work. lt sounds as though he may have perhaps overstated his status with the DRC? Dave Argo Plans Examiner Garfæld Couaty Community Development Department 708 gth Street, Suite 407 Glenwood Springs, CO 87601 Tel: 970-945-8272 Ext. 7670 Em a i I : d a rg o @ g ø rf i etd -cou nty, com W eb : g o rf i e I d -co u nty. co m CONflDENIiAilTY NOTICE: This email communicot¡on and ony files trønsmitted along with it ore intended only for the person or ent¡ty to wh¡ch it ¡s oddressed. tf you have received this email in error, please immediately notify the sender by emoil and delete it from your files. 1 Fetrefs Residence 10? Leonb Lane Carhndale,Colorado 81623 Scope sf work ïV timeline A. Otg dirt sut fEr &e constnr€tiûn of thr rutaining wall 8. Fot¡r coficr*t€ pad for ååsÊtrlÊnt of basernent- l.dig a*d in#fl drf drain C" Contra*ed Ttøo retrdnirg waB¡ 5e* $pecs. *ttached D. S¡ch ml nctðintng Watb es Psr S*ccs. t. S€t 12* sotno tub€s for exterlcr ded( see $pecs attached F. Forrn *n deck for csr¡sete See specr. G. Po*¡r concrete deËk ar*d deen, landscapr and d*an up. this ås a verr low impa€t job. Þoesn't require ¡ lot traffc and can be dsne, ln a short period of tirne. Ihenk You Scott V Fetrer 7 ?r* I Arpen Glen tñc has gven prnri*rion to begin *rprft trO¡ Lßoni¡ Lene Carbondde, tobrado 83613 Csntact LEslie [ammt RECEIVED MAY 21 20t8 GARFIELD COUNTY COMMUNITY DEVELOPMENTFetzefs ßesidence 102 Leonis Lane Carbondale,Colorado 916?3 Scope of work W tirneline Aspen Glen tRt has given perrnirsíon to begin work 1ûl Le$ní* Lane Carbor¡dale, Colorado 81621 Contact Leslie Larnont A. üig dirt ot¡t for the construction af the retaining wall 8. Pour co;ìcretÊ pad for easement of basement. l.dig and install dry drain C. Çontracted Two r*training u¡alls See Sp*cs. Attached S. Eack fill Retaining ltfalls as pe¡ Specs, t. set 1?- sorno tubes for exterisr deck $ee specs attached F" torrn in decl¡ for conçrets 5e* specr_G. Pcur concrete deck and clean, landscape and clean uB" This is ä very low impact job. toesn't require a iot traffic and san be dsn*, ln a short period ôf time, Thank Yr¡u $cott V Frt¡er 7 -'l tf¿f Dave Argo From: Sent: To: Subject: Attachments: Lindsay Krol Tuesday, May 29,2018 4:27 PM Andy Schwaller; Dave Argo FW: Garfield County - project description Fetzer's Work of Scope .pdf This is for permit # BLRE-11--1-7-5OIL.The review of this permit was pending regarding more information from the homeowner. He has now provided an updated description of work as wellas engineered plans forthe foundation. ltold Scott that we would contact if we had any questions or needed more information. Otherwise will contact him when the permit is ready to be picked up. From: Scott Fetzer [mailto :fetzerco @gma il.com] Sent: Tuesday, May 29,2OL8 2:56 PM To: Li ndsay Krol <l krol @ga rfield-cou nty.com> Subject: Re: Garfield County - project description Scott Fetzer 102 Leonis Lane Carbondale, Colorado 81 623 P.O. Box 7588 Carmel.Ca 93921 970710t192 fetzerco@email.com On May 29,2018, at2:52 PM, Scott Fetzer <fetzerco@gmail.co wrote (Fetzer's Residence 102 Leonis Lane.docx> Scott Fetzer 102 Leonis Lane Carbondale, Colorado 81 623 P.O. Box 7588 Carmel.Ca 93921 9707101t92 fetzerco@gmail.com On May 29,2018, at 10:37 AM, Lindsay Krol <lkrol@garfield-county.com> 1 wrote: Good Morning Scott Please submit to our office in writing a detailed description of the scope of work for the project for IO2 Leonis Ln. Because the scope of work has changed since the permit was originally submitted, we need an amended description so that we may update our records for revlew. You can sènd the dêscrlptlon to our plans exâmlner, Dâvê Argo äs well as our Chief Building Official, Andy Schwaller. I have copied them on this correspondence so that you have their contact information. We cannot and will not review your application untll thls letter has been recelved. lf you have any questlons, please contact the office. Thank you. Lind,søy Krol Ad,ntin. Asst.II Ga,rfield County - Canntnu,níty Deaelopnùent 708 &h St.o Suite 407 Glenwood Spríngso CO 87607 970-945-8272 2 CONDITIONS OF PERMIT BLRE-1L.L7.5OTL Scott Fetzer Alterations to Existing Single-Family Residence l-02 Leonis Lane, Carbondale Aspen Glen PUD - Filing l-, Lot G-l- 1) ALL NEW WORK SHALL COMpLY W|TH THE 2015 TNTERNATIONAL RESIDENTIAL CODE (r.R.c.)AND 2009 INTERNATIONAL ENERGY CONSERVATION CODE (l.E.C.C.) 2l tMpRovEMENTS ARE SUBJECT TO ALL APPLICABLE |TEMS CONTAINED lN THE ATTACHED "GARFIELD COUNTY BUILDING REQU¡REMENTS,,. NUMBERED REFERENCES AS NOTED ON PLANS REFER TO SPECIFIC ITEMS ON THIS LIST. 3) THIS BUtLD|NG PERMtT rS TSSUED FOR ALTERATIONS INCLUDING A NEW ON-GRADE EGRESS DOOR FROM BASEMENT WITH ASSOCIATED RETAINING WALLS AND REBUILD OF AN EXISTING WOOD DECK. 4) ALL PROPOSED WORK UNDER THtS PERMIT SHALL BE FULLY CONTAINED IVITHlN LIMITS OF REVISED BUILDING ENVELOPE PER AMENDED FINAL PLAT DATED MARCH T,20T9. PROVIDE IMPROVEMENT SURVEY VERIFYING COMPLIANCE PRIOR TO FINAL INSPECTION & CERTIFICATE OF OCCUPANCY. 5) STRUCTURAL ENctNEER TO pROVtDE TNSPECTION REPORT FOR CONSTRUCTION OF VERSA-LOK RETAINING WALLS PRIOR TO FRAME INSPECTION. 6) AN ACCESSORY DWELLTNG UNrT (A.D.U.)AT BASEMENT OF RESIDENCE lS SPECIFICALLY NOT AN APPROVED USE UNDER THIS BUILDING PERMIT, AND ANY SUCH USE MAY REQUIRE A LAND USE CHANGE PERMIT UNDER PROVISIONS OF GARFIELD COUNTY,S LAND USE & DEVELOPMENT CODE. ADU,s MAY ALSO NOT BE ALLOWED WITHIN THE ASPEN GLEN P.U.D. - HOMEOWNER TO VERIFY WITH DESIGN REVIEW ADMINISTRATOR. 7l pRovtDE GUARDRATL AT PERTMETER OF DECK PER ITEM #38 OF PLAN ATTACHMENTS 8) VER|Fy CARBON MONOXTDE & SMOKE ALARMS AT ALL BEDROOMS WITHIN EXISTING DWELLTNG (REFERENCE ITEMS #32,#33 OF PLAN ATTACHMENTS). 9) ELECTRTCAL PERMITT|NG AND TNSPECTIONS BY COLORADO STATE ELECTRICAL BOARD. ELECTRICAL ROUGH-IN APPROVAL IS REQUIRED AT FRAME INSPECTION. ELECTRICAL FINAL APPROVAL IS REQUIRED FOR FINAL INSPECTION & CERTIFICATE OF OCCUPANCY