HomeMy WebLinkAboutConditions of PermitCONDITIONS OF PERMIT
BLMF-09-19-5954 and SEPT -09-19-5955
John Bellio
New Manufactured Home — Ag Employee Housing
3204 County Road 214 — Silt, Colorado
1) MANUFACTURED HOUSES ARE REGULATED & INSPECTED BY COLORADO DEPT. OF HOUSING
(C.D.O.H.) AND ALL FACTORY -BUILT STRUCTURES INSTALLED IN GARFIELD COUNTY SHALL
COMPLY WITH C.D.O.H. GUIDELINES FOR MANUFACTURE & INSTALLATION AT THE JOB SITE.
2) FOUNDATION, UNFINISHED BASEMENT AND ALL OTHER SITE -BUILT WORK SHALL COMPLY
WITH 2015 I.R.C., 2009 I.E.C.C. AND MANUFACTURER'S INSTALLATION REQUIREMENTS.
3) REFER TO PLAN ATTACHMENTS FOR GARFIELD COUNTY'S BUILDING REQUIREMENTS AND
DETAILED DESCRIPTION OF NUMERIC NOTATIONS AS REDLINED ON DRAWINGS.
4) BUILDING SHALL COMPLY WITH 25 -FOOT MINIMUM SETBACK FROM REAR (SOUTHERN)
PROPERTY LINE. PROVIDE LOT IMPROVEMENT CERTIFICATE AS STAMPED BY A COLORADO
PROFESSIONAL LICENSED SURVEYOR PRIOR TO CERTIFICATE OF OCCUPANCY TO VERIFY
COMPLIANCE WITH THIS REQUIREMENT.
5) ALL PLUMBING AND GAS PIPING CONNECTIONS MUST BE PERFORMED BY A COLORADO
LICENSED PLUMBER, AND ALL ELECTRICAL CONNECTIONS MUST BE PERFORMED BY A
COLORADO LICENSED ELECTRICIAN.
6) ELECTRICAL PERMITTING AND INSPECTIONS BY STATE OF COLORADO ELECTRICAL BOARD.
ELECTRICAL FINAL APPROVAL IS REQUIRED PRIOR TO FINAL BUILDING INSPECTION &
CERTIFICATE OF OCCUPANCY.
7) SEPTIC SYSTEM MUST COMPLY WITH ALL DESIGN CRITERIA - INCLUDING MINIMUM
SETBACK DISTANCES - AS PER GARFIELD COUNTY'S ON-SITE WASTEWATER TREATMENT
SYSTEM (O.W.T.S.) REGULATIONS.
8) GARFIELD COUNTY BUILDING DEPT. INSPECTIONS TO INCLUDE THE FOLLOWING:
A. FOOTINGS
B. FOUNDATION
C. SEPTIC SYSTEM
D. PLUMBING/GAS
E. FINAL INSPECTION & CERTIFICATE OF OCCUPANCY*
* NOTE: GARFIELD COUNTY REQUIRES C.D.O.H. INSTALLATION INSIGNIA TO BE AFFIXED
PRIOR TO FINAL BUILDING INSPECTION & CERTIFICATE OF OCCUPANCY.