HomeMy WebLinkAboutEngineer's Report of Site Observations 08.20.2019EVOLVE REPORT OF SITE OBSERVATIONS Date: August 20, 2019 To: Sweeney Development Attn: Kurt Backofen Report No: 01 Project: Buffalo Valley Apartments ESD Project No.: 19.082C Date: August 20, 2019 Weather: Cool Contractor: Sweeney Present at Site: Kurt Backofen (Sweeney), Steve Edmiston (ESD) A site visit to observe construction progress for Building 1 was completed for the above referenced project. At the time of the site visit, the following observations were made: 1. The section of corridor foundation footing slated for reconstruction had been formed up and most of the reinforcing was in place. The following items were noted and/or discussed with the Contractor while on site: 1. Footing reinforcing was still in the process of being chaired up to the specified clear distance to bottom of footing With the completion of the above noted items, construction appears to be progressing in general conformance with the Contract Documents. Steven R. Edmiston, P.E. Senior Engineer