HomeMy WebLinkAboutConditions of PermitCONDITIONS OF PERMIT
BLMF-01-21-6647 and SEPT-01-21-6648
Mario Tarin
New Manufactured Home
405 County Road 104 — Carbondale, Colorado
Jean & Dee Blue Amended Exception, Tract 2
1) MANUFACTURED HOUSES ARE REGULATED & INSPECTED BY COLORADO DEPT. OF HOUSING
(C.D.O.H.) AND ALL FACTORY -BUILT RESIDENTIAL STRUCTURES INSTALLED IN GARFIELD
COUNTY MUST MEET C.D.O.H. GUIDELINES FOR MANUFACTURE AND INSTALLATION AT THE
JOB SITE.
2) FOUNDATION, CRAWL SPACE & SITE WORK SHALL COMPLY WITH 2015 I.R.C., 2009 I.E.C.C.
AND MANUFACTURER'S INSTALLATION REQUIREMENTS.
3) REFER TO PLAN ATTACHMENTS FOR GARFIELD COUNTY'S BUILDING REQUIREMENTS AND
DETAILED DESCRIPTION OF NUMERIC NOTATIONS AS REDLINED ON DRAWINGS.
4) MANUFACTURED RESIDENCE IS APPROVED AS REPLACEMENT OF AN EXISTING RESIDENCE
ON THIS PROPERTY.
5) LOCATION/PLACEMENT OF NEW MANUFACTURED RESIDENCE SHALL NOT ENCROACH INTO
THE 25-FOOT FRONT YARD SETBACK. A LOT IMPROVEMENT CERTIFICATE, SEALED BY A
COLORADO LICENSED SURVEYOR, IS REQUIRED AT FOUNDATION INSPECTION TO VERIFY
THAT STRUCTURE IS IN COMPLIANCE WITH BUILDING SETBACK REQUIREMENTS.
6) ALL PLUMBING AND GAS PIPING CONNECTIONS MUST BE PERFORMED BY A COLORADO
LICENSED PLUMBER, AND ALL ELECTRICAL CONNECTIONS MUST BE PERFORMED BY A
COLORADO LICENSED ELECTRICIAN.
7) PRIOR TO FINAL BUILDING INSPECTION & CERTIFICATE OF OCCUPANCY, PROVIDE
BUILDING INSPECTOR WITH FINAL APPROVAL/SIGN-OFF FROM GARFIELD COUNTY'S
PUBLIC HEALTH DEPARTMENT FOR INSTALLATION OF THE ON -SITE WASTEWATER
TREATMENT SYSTEM.
8) ELECTRICAL PERMITTING AND INSPECTIONS BY STATE OF COLORADO ELECTRICAL BOARD.
ELECTRICAL FINAL APPROVAL IS REQUIRED PRIOR TO FINAL BUILDING INSPECTION &
CERTIFICATE OF OCCUPANCY.
9) GARFIELD COUNTY BUILDING DEPT. INSPECTIONS TO INCLUDE THE FOLLOWING:
A. FOOTINGS
B. FOUNDATION
C. SEPTIC SYSTEM
D. PLUMBING/GAS
E. FINAL INSPECTION & CERTIFICATE OF OCCUPANCY*
* NOTE: GARFIELD COUNTY REQUIRES C.D.O.H. INSTALLATION INSIGNIA TO BE AFFIXED
PRIOR TO FINAL BUILDING INSPECTION & CERTIFICATE OF OCCUPANCY.