Loading...
HomeMy WebLinkAboutConditions of PermitCONDITIONS OF PERMIT BLCO-I l-20-6588 a nd S E PT-1 1-20-6589 Aspen Polo Partners, LLP Ganzi Pavilion + Observation Deck L64LL Híghway 82- Carbondale 1) ALL WORK MUST COMPLY W|TH 2015 l.B.C., LF.C., l.P.C., l.M.C., l.F.G.C., AND 2009 LE.C.C. AS WELL AS MANUFACTURER'S REQUIREMENTS. 2l WORK SHALL COMPLY WITH THE FOLLOWING: (A) GARFIELD COUNTY'S B.O.C.C. RESOLUTION No.2018-L0; (B)ASPEN VALLEY POLO CLUB P.U.D. REGULATIONS & P.U.D. GUIDE; AND (C)THE FINAL PLAT. 3) BUtLDtNc tS PERM|TTED AS CONSTRUCTTON TYPE "V-8", W|TH OCCUPANCY GROUP "A2" - ASSEMBLY USE. 4) PROV|DE OPEN-HOLE SOTLS REPORT AT FOOTING INSPECTION TO VERIFY 1,500 P.S.F. 5) A LOT TMPROVEMENT CERTIF|CATE, SEALED BY A COLORADO LICENSED SURVEYOR, lS REQUIRED AT FOUNDATION INSPECTION TO VERIFY STRUCTURE - INCLUDING ROOF OVERHANGS, DECKS AND OTHER PROJECTIONS - IS IN COMPLIANCE WITH IO-FOOT MINIMUM CLEARANCE/SETBACK TO ADJACENT BUILDINGS. 6) A FtRE ALARM SYSTEM tS REQUTRED tN THIS STRUCTURE. VERIFY SYSTEM DESIGN WITH LOCAL FIRE DISTRICT. 7l VERtFy COMPLTANCE W|TH EGRESS REQUTREMENTS AS PER 2015 l.B.C., CHAPTER 10. VERIFY EXIT DIRECTIONAL SIGNS & EMERGENCY LIGHTING LOCATIONS PRIOR TO ELECTRICAL ROUGH-IN INSPECTION. 8) LOCKS, LATCHES & LANDINGS AS PER 2015 l.B.C., SECTION L0L0. 9) ACCESS|BTLTy REQUTREMENTS AS PER 201s r.B.C., CHAPTER 11 &tCC/Arr7.1-2009 STANDARDS. 10) LIGHI VENTTLATTON & TEMPERATURE CONTROLS AS PER 2015 LB.C., CHAPTER 12. 11) COMMERCTAL KTTCHEN pERMtTS, TNSPECTTONS & FTNAL APPROVALS SHALL BE ADMTNTSTERED BY GARFIELD COUNTY PUBLIC HEALTH DEPT. PRIOR TO FINAL INSPECTION & CERTIFICATE OF occupANcy pRovrDE FrNAL APPROVALS/SIGN-OFF FROM PUBLTC HEALTH DEPT. 12) ENGTNEERED SEPTTC SYSTEM (O.W.T.S.)SHALL BE TNSPECTED BY A COLORADO LTCENSED PROFESSIONAL ENGINEER. PROVIDE FINAL REPORT AND APPROVAL FROM GARFIELD COUNW PUBLIC HEALTH DEPT. PRIOR TO FINAL BUILDING INSPECTION & CERTIFICATE OF OCCUPANCY. 13) BUILDING MECHANICAL SYSTEMS INCLUDING: COMBUSTION AlR, DUCTWORK & VENTING REQUTREMENTS AS pER TNTERNATTONAL MECHANICAL CODE (l.M.C.)AND l.E.C.C., SECTTON s03. MECHANICAL ROUGH-IN INSPECTION IS REQUIRED PRIOR TO FRAME INSPECTION. 14) PLUMBtNc REQUTREMENTS AS pER TNTERNATTONAL PLUMBTNG CODE (r.P.C.) & TNTERNATIONAL FUEL GAS CODE (t.F.c.C.) PLUMBTNG ROUGH-rN TNSPECTTON rS REQUTRED PRIOR TO FRAME INSPECTION. 15) ELECTRICAL REQUIREMENTS, PERMITTING AND INSPECTIONS BY COLORADO STATE ELECTRICAL BOARD. ELECTRICAL ROUGH-IN APPROVAL IS REQUIRED AT FRAME INSPECTION. ELECTRICAL FINAL APPROVAL REQUIRED FOR FINAL BUILDING INSPECTION & CERTIFICATE OF OCCUPANCY. Dave Arqo Sent: From: Subject: Attachments: Dave Argo Monday, January 4,2021 3:10 PM 'Max Filiss'; 'Mark Ward'; Jon Fredericks Glenn Hartmann; Andy Schwaller (aschwaller@gar-field-county.com); lkrol@garfield- county.com Aspen Polo Partners - Ganzi Barn + Pavilion Permits Ganzi Pavilion Plan Review Corrections.pdf To: Cc: Max: I wanted to update you on our review of Building Permits for the 2 buildings to be located on Lot 5 of the Aspen Polo Partners project located aLL64LL Highway 82 in Carbondale. Last week I met with both Glenn Hartmann and Andy Schwaller in our office to discuss these projects in an effort to insure that both the Planning & Building divisions were on the same page and being consistent with prior reviews and interpretations with regard to the ongoing project approvals from Garfield County's Community Development Dept. As a result of our internal coordination meeting, we are now ready to issue a building permit for the Ganzi Barn project. However, the drawings submitted for the Pavilion are incomplete and require additional information be submitted to our office before we can finalize our plan review and issue permits for that structure. ln addition to missing information, lack of coordination between Architect/Consultant plans and other issues which simply do not meet the Building Code, the placement of the Pavilion on the site is inconsistent with our department's policy and definition of the term "Building Envelope" as set forth in Garfield County's Land Use & Development Code. For a more detailed description of the many issues that must be addressed before we can proceed further wíth our review of the Pavilion, please refer to the attached "Plan Review Correction Notice". Because of the site placement issues related to the platted "Building Envelope" and distance between buildings, we strongly urge you and your design consultants to address these issues "post-haste" and perhaps prior to initiating excavation and grading work for the Ganzi Barn, because of certain dimensional "ripple effect" if the Pavilion needs to be relocated on the site. I will be dropping off the approved plans for the Ganzi Barn project at the office in the morn¡ng, and you should be receiving a call from Lindsay sometime tomorrow with final balances dues and permit pick-up instructions. Until we receive an updated and more completed set of drawings for the Pavilion project we will place those drawings in our "Pending" files. Please contact our offíce with any questions. Dave Argo Plans Examiner Caunty Community Development Department 708 8th Street, Suite 40L Glenwood Springs, CO 8160L Tel: 970-945-8212 Ext. L670 Emo il : do rg o @ go rfield-cou nty.com Web : ga rfield-cou nty. co m 1