FIELD OBSERVATION REPORT #2
Date: February 3,2027
To Julio Moreno
Lot 38 County Road 331
Silt, Colorado
A site visit to review the existing structure and construction progress was completed for the above referenced project. At the time
of the site visit, the following observations were made:
L The structural framing systems for the house were essentially complete.
a. Roof framing was installed, roof sheathing was in place for most of the roof, with garage roof sheathing in
progress,
At the time of the site visit, construction appears to be in general conformance with the Structural Contract Documents. Please
contact our office if you have any questions or concerns in relation to the information noted above.
Evolve Structural Design
Steven R, Edm ., S,E.
Senior Engineer
Project:Griselda's Project - Lot 38 County Road 331
ESD Project #:19.r20C
Observation Date:December L8,2O2O
Contractor:Owner
Present at Site:Julio Moreno (Owner), Steve Edmiston (ESD)