HomeMy WebLinkAbout1.14 Pre-Application Conference Summary
Community Development Department
108 8th Street, Suite 401
Glenwood Springs, CO 81601
(970) 945-8212
www.garfield-county.com
PRE-APPLICATION
CONFERENCE SUMMARY
TAX PARCEL NUMBER: 2185-354-23-007 DATE: 1/12/22
APPLICANT: Multi-Family Dwelling
CURRENT OWNER: Blue Heron Properties LLC
CONTACTS: Cal Kendrick, Wes Cole
REPRESENTATIVES: David Mylar (Attorney), Richard Dooley (Builder/Contractor)
PRACTICAL LOCATION: Located at 1007 Westbank Rd., on a portion of the Iron Bridge
Golf Course, within the Westbank Subdivision south of Glenwood Springs off of County
Road 109.
TYPE OF APPLICATION: Limited Impact Review – Multi-family Dwelling
ZONING: Residential Suburban Density
I. GENERAL PROJECT DESCRIPTION
The Property Owner is proposing conversion of a portion of the existing office/maintenance
structure into residential apartments for housing of employees. The second floor of the
5,000 sq.ft. structure would be remodeled into 4 apartments while the lower level would
continue to be utilized for golf course storage and maintenance functions. The facility is
located on the 93.86-acre golf course property and is access off of Westbank Rd. The site
is currently improved with access driveways and off-street parking. Based on Assessor’s
Office records the facility was built in approximately 1965 prior to zoning within the County
and apparently was the club house for the golf course which operated on the property. Golf
course operations have since been incorporated into the larger Iron Bridge Golf Course.
The facility is served by central water (Westbank Water System) and an OWTS.
Confirmation of taps or will serve letters for water and also confirmation of the capacity of
the OWTS to serve the proposed change in use will be required. The pre-application
meeting included extensive input from the County Building Department on building code
requirements including occupancy separation and life safety considerations. The need for
a licensed architect to prepare the plans and a licensed structural engineer to review
structural issues was noted. The Applicant should continue to reach out to the Building
Department for any follow-up questions and the Building Department will be a referral
agency for the Land Use Permit Application.
II. REGULATORY PROVISIONS APPLICANT IS REQUIRED TO ADDRESS
• Garfield County Comprehensive Plan 2030 as amended.
• Garfield County Land Use and Development Code as amended.
• Residential Suburban Zone District - Use Table (Table 3-403).
• Residential Suburban Zone District - Lot/Building Requirements (Table 3-201)
• Review Process (Section 4-104) and Procedures (Section 4-101).
• Table 4-102 Common Review Procedures and Required Notice.
• Application Materials (Table 4-201 and Section 4-203).
• Waivers, Section 4-118 (Standards) and Section 4-202 (Submittal Requirements).
• Article 7, Standards – Division 1, 2 & 3 as applicable.
• Article 15, Definitions – Multi-Family Dwelling
III. REVIEW PROCESS
The Application will follow the Limited Impact Review Process contained in Sections 4-101
and 4-104 and in Table 4-102 (see attached flow chart):
• Pre-application Conference
• Submittal of Application (3 hard copies plus one digital PDF copy on CD or USB Stick)
• Determination of Completeness, if Technically Complete the Applicant will be notified
and the request scheduled for a public hearing before the Board of County
Commissioners. If it is not technically complete the Applicant will be advised of the
deficiencies and has 60 days to complete the application.
• Once determined to be complete, the Application is sent out to referral agencies.
• A public hearing before the Board of County Commissioners is scheduled.
• Four additional hardcopies of the Application are provided for the Board of County
Commissioners review.
• Applicant completes public notice for the public hearing (mailing, posting, and
publication) a minimum of 30 days prior to the hearing.
• Staff prepares a report including public and referral comments
• Review and Action by the Board of County Commissioners at the public hearing.
• The Board of County Commissioners action is formalized by a resolution.
• If approved with conditions the Applicant must meet the conditions prior to issuance of
the Land Use Change Permit.
• The Applicant has one year to meet all conditions of approval.
IV. SUBMITTAL REQUIREMENTS
Application submittal requirements are detailed in Table 4-201, and Section 4-203,
Description of Submittal Requirements. Please use the summary provided below as a
supplemental check list.
General Application Materials (application forms,
agreement to pay form, Statement of Authority for Trusts,
corporations or LLC’s, authorization to represent, and
payment of fees).
Evidence of ownership such as a deed for the property
and title work.
Narrative description of the proposal.
List of property owners within 200 feet and any mineral
rights owners on the property. A statement on how
mineral owners were researched is required.
Vicinity Map (including the area generally within 3 miles of
the site).
Site plan with information on proposed use including,
existing structures, parking, access roads/driveways,
topography & significant site features, easements, utilities,
ditches, water lines, existing and proposed wastewater
treatment systems (OWTS). The site plan may be limited
to the area immediately adjacent to the proposed use and
waivers may be requested based on the based the proposal to remodel an existing
building.
Grading and drainage plans. Existing conditions/improvements need to be documented
along with any proposed modifications associated with the change in use.
Landscaping Plan, existing and proposed.
Impact Analysis. This section includes information existing uses, surrounding uses and
potential impacts of the proposal many of which may be addressed by reference to the
existing improvements/condition of the property. A waiver regarding sections on
environmental impacts or wildlife may be requested with supporting justification. Please
contact the staff planner for additional information on potential waiver requests.
Legal access, physical access, and compliance with Roadway Standards Table 7 -107.
Demonstration of adequacy of the roadway and compliance with Roadway standards
must be submitted.
Traffic Study: A waiver from a full traffic study may be requested, however basic traffic
generation information will need to be provided to support the waiver request. Please
contact the staff planner for additional information on potential waiver requests.
Water Supply Plan and supporting documentation including the status of any additional
tap fees and/or will serve letters for the proposed change in use.
The submittals should address any additional fire protection demands and water
requirements should sprinklers be required for the proposed use.
Wastewater treatment plans and supporting documentation. Needs to include
information on the adequacy of the existing OWTS or plans for a new/expanded system.
Information to address applicable sections of Article 7, Divisions 1, 2, and 3, needs to
be provided. Application formatting that addresses each section of Article 7 are
recommended.
Significant Article 7 Standards for this project are anticipated to include: zoning
compliance, comprehensive plan compliance, compatibility, drainage, fire protection
(including potential fire suppression sprinkler requirements), lighting, access, water and
sanitation and parking (demonstration of compliance with the standards in Table 7-
302.A. needs to be provided)
The Application submittal needs to include 3 hard copies of the entire Application and 1
Digital PDF Copy on a CD or USB Stick. Both the paper and digital copies should be split
into individual sections. Please refer to the pre-application summary for submittal
requirements that are appropriate for your application.
Any request for a waiver from standards shall be processed pursuant to Section 4-118 of
the Land Use and Development Code. Submittal waiver requests should be consistent with
the Pre-Application summary, and Section 4-202. Follow-up meetings with Planning Staff
on potential waiver requests is recommended.
V. APPLICATION REVIEW
a. Review by: Staff for completeness recommendation and referral agencies for
additional technical review
b. Public Hearing: ___ Director’s Decision (with notice – not a public hearing)
___ Planning Commission
_X_ Board of County Commissioners
___ Board of Adjustment
c. Referral Agencies: May include but are not limited to County Attorney, County
Building Department, Fire Protection District, County Road &
Bridge, Division of Water Resources or Water Service Provider,
County Vegetation Manager, County Environmental Health, and
County Consulting Engineer.
VI. APPLICATION REVIEW FEES
a. Planning Review Fees: $ 400
b. Referral Agency Fees: $ TBD – consulting engineer/civil engineer fees
c. Total Deposit: $ 400 (additional hours are billed at $40.50 /hour)
VII. GENERAL APPLICATION PROCESSING
The foregoing summary is advisory in nature only and is not binding on the County. The
summary is based on current zoning, which is subject to change in the future, and upon
factual representations that may or may not be accurate. This summary does not create a
legal or vested right. The summary is valid for a six-month period, after which an update
should be requested. The Applicant is advised that the Application submittal once accepted
by the County becomes public information and will be available (including electronically) for
review by the public. Proprietary information can be redacted from documents prior to
submittal.
Pre-application Summary Prepared by:
____________________________________________ _2/16/22__
Glenn Hartmann Date
Principal Planner