February 28, 2024
AS-BUILT CERTIFICATE OF INSPECTION & ACCEPTANCE
Onsite Wastewater Treatment System
3-BR Single-Family Dwelling
3093 CR 237 Harvey Gap Road
Silt, CO 81652
The referenced onsite wastewater treatment system (OWTS) was inspected February 21, 2024.
At the time of inspection, the OWTS was installed in conformance with the October 2023 OWTS
design plans. Please contact WestWater Engineering for any additional information regarding
engineered-design OWTS for referenced address.