HomeMy WebLinkAboutSubsoils Report for Foundation DesignI(+A Xumar & Associatos, lns."
Geotechnical and Matenals Engineers
and Envrronmenlal Scientists
An Employeo Orirnad Contpany
5020 County Road 154
Glenwood Springs, CO 81601
phone: (970) 945-7988
fax: (970) 945-8454
email: kaglenwood@kumarusa.com
www.kumarusa.com
Offiae l,ocations: Denver (HQ), Parker, Colorado Springs, Fort Collins, Glenwood Springs, and Summit County, Colorado
SUBSOIL STUDY
FOR FOTTNDATION DESIGN
PROPOSED GARAGE ADDITION
2074 COANTY ROAD 109
LOT 10, TELLER SPRTNGS
GARFTELD COUNTY' COLORADO
PROJECT NO.23-7-674
DECEMBER 28, 2023
PREPARED FOR:
JACK KENNEDY
2074 COUNTY ROAD 109
CARBO|IDALE, COLORADO 81 623
ik@rof.net
TABLE OF CONTENTS
PURPOSE AND SCOPE OF STUDY
PROPOSED CONSTRUCTION .........
SITE CONDITIONS
SUBSIDENCE POTENTIAL
FIELD EXPLORATION
SUBSTIRFACE CONDITIONS
DESIGN RECOMMENDATIONS ..
FOUNDATIONS
FLOOR SLABS
UNDERDRAIN SYSTEM
SURFACE DRAINAGE....
LIMITATIONS
1
1
I
-1-
-2-
n-L-
a-J-
-3-
-4-
4-
FIGURE 1 - LOCATION OF EXPLORATORY BORING
FIGURE 2 - LOG OF EXPLORATORY BORING
FIGURE 3 _ SWELL-CONSOLIDATION TEST RESULTS
TABLE 1- SUMMARY OF LABORATORY TEST RESULTS
Kumar & Associates, lnc. I Project No. 23-7-674
PURPOSE AND SCOPE OF STUDY
This report presents the results of a subsoil study for a proposed garage addition to the residence
located at2074 County Road 109, Lot 10, Teller Springs, Garfreld County, Colorado. The
project site is shown on Figure 1. The pulpose of the study was to develop recommendations
for the foundation design. The study was conducted in accordance with our agreement for
geotechnical engineering services to Jack Kennedy dated November 24,2023.
An exploratory boring was drilled to obtain information on the subsurface conditions. Samples
of the subsoils obtained during the field exploration were tested in the laboratory to determine
their classification, compressibility and other engineering characteristics. The results of the field
exploration and laboratory testing were analyzedto develop recommendations for foundation
types, depths and allowable pressures for the proposed building foundation. This report
summarizes the data obtained during this study and presents our conclusions, design
recommendations and other geotechnical engineering considerations based on the proposed
construction and the subsurface conditions encountered.
PROPOSED CONSTRUCTION
The proposed garage addition will be a single-story skucture with slab-on-grade floor attached to
the west side of the residence. Grading for the structure is assumed to be relatively minor with
cut depths between about 2 to 3 feet. We assume relatively light foundation loadings, typical of
the proposed type of construction.
If building loadings, location or grading plans change significantly from those described above,
we should be notified to re-evaluate the recommendations contained in this report.
SITE CONDITIONS
The proposed addition area consists of asphalt paved parking on the west side of the existing
residence. The ground surface is relatively flat with a gentle slope down to the northeast.
Nearby vegetation consists of irrigated lawn.
SUBSIDENCE POTENTIAL
Bedrock of the Pennsylvanian age Eagle Valley Evaporite underlies the Teller Springs
subdivision. These rocks are a sequence ofgypsiferous shale, fine-grained sandstone and
siltstone with some massive beds of gypsum and limestone. There is a possibility that massive
gypsum deposits associated with the Eagle Valley Evaporite underlie portions of the property.
Dissolution of the gypsum under certain conditions can cause sinkholes to develop and can
produce areas of localized subsidence. Sinkholes have been observed in the area of the Teller
Springs subdivision which appear similar to others associated with the Eagle Valley Evaporite in
areas of the lower Roaring Fork River valley.
i
I
j
I
I
I
I
Kumar & Associates, lnc. @ Project No. 23-7-674
.,
Sinkholes were not observed in the immediate area of the subject property. No evidence of
cavities was encountered in the subsurface materials; however, the exploratory boring was
relatively shallow, for foundation design only. Based on our present knowledge of the
subsurface conditions at the site, it cannot be said for certain that sinkholes will not develop.
The risk of future ground subsidence at the subject site throughout the service life of the
proposed addition, in our opinion, is low; however, the owner should be made aware of the
potential for sinkhole development. If further investigation of possible cavities in the bedrock
below the site is desired, we should be contacted.
FIELD EXPLORATION
The field exploration for the project was conducted on December 6,2023. One exploratory
boring was drilled at the location shown on Figure 1 to evaluate the subsurface conditions. The
boring was advanced with 4-inch diameter continuous flight augers powered by a truck-mounted
CME-458 drill rig. The boring was logged by a representative of Kumar & Associates, Inc.
Samples of the subsoils were taken with I% inch and 2-itch I.D. spoon samplers. The samplers
were driven into the subsoils at various depths with blows from a 140 pound hammer falling 30
inches. This test is similar to the standard penetration test described by ASTM Method D-1586.
The penetration resistance values are an indication of the relative density or consistency of the
subsoils. Depths at which the samples were taken and the penetration resistance values are
shown on the Log of Exploratory Boring, Figure 2. The samples were returned to our laboratory
for review by the project engineer and testing.
SUBSURFACE CONDITIONS
A graphic log of the subsurface conditions encountered at the site is shown on Figure 2. The
subsoils encountered, below the asphalt pavement, consist of about 4%feet of medium stiff,
sandy silty clay overlying dense, silty sandy gravel and cobbles. Drilling in the coarse granular
subsoils with auger equipment was difficult due to the cobbles and probable boulders and drilling
refusal was encountered in the deposit.
Laboratory testing performed on samples obtained from the boring included natural moisture
content and density and finer than sand size gradation analyses. Results of swell-consolidation
testing performed on relatively undisturbed drive sample of the upper clay soil, presented on
Figure 3, indicate low to moderate compressibility under conditions of loading and wetting. The
laboratory testing is summarizedinTable 1.
No free water was encountered in the boring at the time of drilling and the subsoils were very
moist to slightly moist with depth.
t:
!
I
t,
i
I
i
I
I
I
I
I
I
I
i
I
I
t:
I
i
I
i
I
t,
t'
i
l.
Kumar & Associates, lnc. @ Project No. 23-7-674
J
DESIGN RECOMMENDATIONS
FOUNDATIONS
Considering the subsurface conditions encountered in the exploratory boring and the nature of
the proposed construction, we recommend the building addition be founded with spread footings
bearing on the natural soils.
The design and construction criteria presented below should be observed for a spread footing
foundation system.
1) Footings placed on the undisturbed natural granular soils should be designed for
an allowable bearing pressure of 1,500 psf. Based on experience, we expect
settlement of footings designed and constructed as discussed in this section will
be about 1 inch or less. Footings extended down to bear entirely on the dense
gravel can be designed for an allowable bearing pressure of 3,000 psf with minor
settlement potential.
2) The footings should have a minimum width of 18 inches for continuous walls and
2 feet for isolated pads.
3) Exterior footings and footings beneath unheated areas should be provided with
adequate soil cover above their bearing elevation for frost protection. Placement
of foundations at least 36 inches below exterior grade is typically used in this
atea.
4) Continuous foundation walls should be reinforced top and bottom to span local
anomalies such as by assuming an unsupported length of at least 12 feet.
Foundation walls acting as retaining structures (if any) should also be designed to
resist a lateral earth pressure coffesponding to an equivalent fluid unit weight of at
least 55 pcf.
5) All existing fill, topsoil and any loose or disturbed soils should be removed and
the footing bearing level extended down to the firm natural soils. The exposed
soils in footing area should then be moisture adjusted to near optimum and
compacted. The clay soils have relatively high moisture content and care should
be taken to not disturb them such as with wheel traffic or inundation from surface
runoff.
6) A representative of the geotechnical engineer should observe all footing
excavations prior to concrete placement to evaluate bearing conditions.
FLOOR SLABS
The natural on-site soils, exclusive of topsoil, are suitable to support lightly loaded slab-on-grade
construction. To reduce the effects of some differential movement, floor slabs should be
separated from all bearing walls and columns with expansion joints which allow unrestrained
vertical movement. Floor slab control joints should be used to reduce damage due to shrinkage
Kumar E Associates, lnc. o Project No. 23-7-674
-4-
cracking. The requirements for joint spacing and slab reinforcement should be established by the
designer based on experience and the intended slab use. A minimum 4 inch layer of relatively
well graded sand and gravel such as CDOT Class 6 base course should be placed beneath slabs
for support. This material should consist of minus 2-inchaggregate with at least 50% retained
on the No. 4 sieve and less than l2o/o passing the No. 200 sieve. Due to the relatively high
moisture of the natural soils, care should be taken not to disturb the natural clay subgrade such as
with wheel loading.
All fill materials for support of floor slabs should be compacted to at least 95o/o of maximum
standard Proctor density at a moisture content near optimum. Subgrade fill can consist of the
onsite soils devoid of vegetation, topsoil and debris when moisture conditioned to near optimum
moisture content. Imported granular soil such as CDOT Class 6 base course could also be used.
UNDERDRAIN SYSTEM
We understand the proposed finished floor elevation of the addition at the lowest level is at or
above the surrounding grade. Therefore, a foundation drain system is not required. It has been
our experience in the area that local perched gtoundwater can develop during times of heavy
precipitation or seasonal runoff. Frozen ground during spring runoff and the clay soils can create
a perched condition. We recommend below-grade construction, such as retaining walls,
crawlspace and basement areas, be protected from wetting and hydrostatic pressure buildup by
an underdrain and wall drain system.
If the finished floor elevation of the proposed addition is revised to have a floor level below the
surrounding grade, we should be contacted to provide recommendations for an underdrain
system. All earth retaining structures should be properly drained.
SURFACE DRAINAGE
The following drainage precautions should be observed during construction and maintained at all
times after the addition has been completed:
1) Inundation ofthe foundation excavations andunderslab areas shouldbe avoided
during construction.
2) Exterior backfill should be adjusted to near optimum moisture and compacted to
at least 95Yo of the maximum standard Proctor density in pavement and slab areas
and to at least 90% of the maximum standard Proctor density in landscape areas.
3) The ground surface surrounding the exterior of the building should be sloped to
drain away from the foundation in all directions. We recommend a minimum
slope of 6 inches in the hrst l0 feet in unpaved areas and a minimum slope of
3 inches in the first 10 feet in paved areas.
4) Roof downspouts and drains should discharge well beyond the limits of all
backfill.
,il
iii
ii
:ll
rii
it
:IIjit
,t!
iiiiIiil
;ii
ril
rii
rli
itl
,li
iii
ill
iii
.I
,ltr;l,t'
;i
'
,ll,l;
iii
iii
:li
iii'il
,ii
ii
iti
,ii
:ll
jil
;ii
,il
ili
iil
ilt
:ll
ill
ili
iti
ili
ii I
,ii
:I I
:ll
:i
iti,i,
iit
rll
iii
ii
iI
iii
;ii
;ii
;li
iti
:ii
Ii
ii!
iir
iii
iil
iii'tl
.lr
iil
iil
Kumar & Associates, lnc. @ Project No. 23.7.674
-5-
5) Landscaping which requires regular heavy irrigation should be Iocated at least
5 feet frorn foundation walls.
LIMITATIONS
This study has been conducted in accordance with generally accepted geotecturical engineering
principles and practices in this area at this time. We rnake no warranty either express or implied.
The conclusions and recommendations subrnitted in this report are based upon the data obtained
frorn the exploratory boring drilled at the location indicated on Figure 1, the proposed type of
construction and our experience in the area. Our services do not include determining the
presence, prevention or possibility of mold or other biological contaminants (MOBC) developing
in the future. if the client is concerned about MOBC. then a professional in this special field of
practice should be consulted. Our lindings include interpolation and extrapolaticln of the
subsurface conditions identified at the exploratory boring and variations in tire subsurface
conditions may not become evident untii excavation is perfonned. If curditions encountered
during construction appear dilferent frorn those described in this repofi, we should be notified so
that re-erraluation of the recommendations may be rnade.
This report has been prepared fbr the exclusive use by our client fbr design purposes. We are not
responsible for technical inte4rretations by others of our infonnation. As the project evolves, we
should provide continued consultation and field services during construction to review and
monitor the implementation of our recomrnendatiotrs, and to veritl, that the recornmendations
have been appropriately interpreted. Significant clesign changes may requile additional arialysis
or rnodifications to the recommendations presented herein. We recommend on-site observation
of excavations and foundation bearing strata and testing of structural fill by a representative of
the geotechnical engineer.
Respectfully Submitted,
(f,
Steveu L. Pawlak, P.
Revierved by:
I I i..*
-:' ,:r' ''
b
Daniel E. Hardirr, P.E.
SLP,&ac
cc: Palomino Desigri-Build - Jack Palomiuo (;;lr. ii1;;iii:r'rrliir;''i"i1'r ;:ijillti , ,ri,)
if. 1^1i1i ;;1 |t. jr,::l:qrL iiiit'l.l, I ltt:,r tr,] :r i,r:'r .'.1' l:,1,i
,i
il
il
BORING 1o
PROPOSED
ADDITION
EXISTING
EXISTING
1()E 6 0
APPROXIMATE SCALE-FEET
2rJ74.
23-7 -67 4 Kumar & Associates LOCATION OF EXPLORATORY BORING 1
I
IFig
BORING 1
(4)ASPHALT, THICKNESS IN INCHES SHOWN IN PARENTHESES TO
LEFT OF THE LOG.0 (4)
5/12
CLAY (CL); Sllfi, SANDY, MEDIUM STIFF, VERY MOIST, BROWN.
FlrJ
u.l
LL
I-F(L
LJo
5
10/12
WC=21.9 W
GRAVEL AND CoBBtrS (GM); STLTY, SANDY, PRoBABLE
BOULDERS, DENSE, MOIST, BROWN, ROUNDED ROCK.
I oo=gg
I
F
i
I
_t
DRIVE SAMPLE, z-INCH I.D. CALIFORNIA LINER SAMPLE.
10 DRTVE SAMPLE, 1 5/8-|NCH t.D. SpLtT Sp00N STANDARD
PENETRATION TEST,
-l otsrunneo BUr.x sAMPt.e.
I_t
<rt.lDR|VE SAMPLE BL0W C0UNT. INDICATES THAT 5 BL0WS 0F"/ ''A 140-pouND HAMMER FALLINc 30 tNcHEs wERE REQUIRED
TO DRIVE THE SAMPLER 12 INCHES.
f enlcrrclr AUGER REFusAL.
NOTES
THE EXPLORATORY BORING WAS DRILLED ON DECEMBER 6, 2023
WITH A 4-INCH DIAMETER CONTINUOUS FLIGHT POWER AUGER.
2, THE LOCATION OF THE EXPLORATORY BORING WAS MEASURED
APPROXIMATELY BY PACING FROM FEATURES SHOWN ON THE
SITE PLAN PROVIDED.
3. THE ELEVATION OF THE EXPLORATORY BORING WAS NOT
MEASURED AND THE LOG OF THE EXPLORATORY BORING IS
PLOTTED TO DEPTH.
4. THE EXPLORATORY BORING LOCATION SHOULD BE CONSIDERED
ACCURAIE ONLY TO THE DEGREE IMPLIED BY THE METHOD USED.
5. THE LINES BETWEEN MATERIALS SHOWN ON THE EXPLORATORY
BORING LOG REPRESENT THE APPROXIMATE BOUNDARIES BETWEEN
MATERIAL TYPES AND THE TRANSITIONS MAY BE GRADUAL.
6. GROUNDWATER WAS NOT ENCOUNTERED IN THE BORING AT THE
TIME OF DRILLING.
7. LABORATORY TEST RESULTS:
WC = WATER CONTENT (X) (ASTM D 2216):
DD = DRY DENSITY (pcf) (ASTM D 2216);
-2OO = PERCENTAGE PASSING NO. 2OO SIEVE (ASTM D 1 1 40).
WC=7,1
-200=26
Fis. 223-7-674 Kumar & Associates LOG OF EXPLORATORY BORING
,1
jj
;i
1l
!
I
rl
:]
{'
,li
SAMPLE OF: Sondy Silty Cloy
FROM:Boringl@4'
\ttC = 21 .9 %, DD = 99 pcf
ln
ot
NO MOVEMENT UPON
WETTING
0x
J4J -llr,l
=vt
t_2
zotr
(f
oazoo_4
-5
-6
1.0 APPLIED PRESSURE - KSF t0
Fig. 3SWELL_CONSOLIDATION TEST RESULTS23-7-674 Kumar & Associates
rli
K+n Kumar & Arstriates, lnn" ',lcrltrnl c 1r tr:1 I\4el?r,,1rs 1".:s:.r"+.:,
an{ fifi rirrcrrilgr]lgt SCr{ifrti$t$
TABLE 1
SUMMARY OF LABORATORY TEST RESULTS
SOIL TYPE
Sandy Silty Clay
Silty Sandy Gravel
(psfl
UNCONFINED
COMPRESSIVE
STRENGTH
(%\
PLASTIC
INDEX
ATTERBERG LIMITS
t%l
LIQUID LIM]T
PERCENT
PASSING NO.
200 stEvE
26
SAND
(%l
GRADATION
(%)
GRAVEL
{ocfl
I'IATURAL
DRY
DENSITY
992t.9
7.1
NATURAL
MOISTURE
CONTENTDEPTHBORING
4
5-8
I
No. 23-7-674