HomeMy WebLinkAboutDeferred Inspection FormCOLORADO
19-01 Department of Local Affairs
Divisionof}lousing JULY 2023
Please confirm if the LAW requires a fire protection system and/or wild fire mititgation for this modular
structure. If so, please indicate if the inspection will be completed by a fire department (identify which
one) or whether it will be completed by the Colorado Division of Fire Prevention Et Control.
Manufacturer Responsibility
The registered manufacturer is responsible for manufacturing a structure that is compliant with our
Administrative Rules (CCR 1302-14). If items in the factory have not been completed, only to be
completed in the field, you are still responsible for ensuring they have been completed for compliance.
Please sign below that you have received this letter and acknowledge the items listed are to complete
compliance of the structure, and items are to be inspected and passed for compliance in order to meet
Rule 1,13.1 and section 24-32-3311(4), Colorado Revised Statutes (C.R.S.).
*ATTENTION`
A DOH issued insignia (silver for residential or blue for nonresidential or pink for tiny homes or black for
multi -family) certifying its construction cannot be affixed to the structure until all "OC" items are
completed on site and pass inspection. The same applies to modular structures manufactured by a
certified manufacturer.
Acknowledge Receipt and Understanding
Normal permits and fees for these site work inspections are to be per the local jurisdiction.
State approved plans for Factory -Built Construction may be obtained from the Builder/Manufacturer.
A copy of this completed form is included with the DOH approved plans and must be included with the
installation instructions and shipped with the unit. If the completed form has been damaged or lost
during shipping, the manufacturer or its representative can obtain a copy from the DOH.
Before any inspection is scheduled at the on -site location or Installation Authorization (required for
modular homes and multi -family structures) is issued by the DOH, this form will be required to be signed
and dated by the Building Official, or Approved Third Party Agent, or Fire Safety Official (if applicable),
and submitted to the DOH.
The DOH approved OC form will be included with the approved spec file, with the DOH Plan Reviewer
signature below and their plan approval stamp on the page(s) with the OC listed items to be completed
at the site location. That approved OC form should be submitted to the appropriate parties described in
this form and submitted back to the DOH before any inspection is scheduled at the onsite location or
Installation Authorization (required for modular homes and multi -family structures) is issued.
DOH Plan Reviewer Name James Trout
DOH Plan Reviewer Signature
Date Approved 116/25 Contact email:
Governor Jared 5 Polis I Rick M. Garcia. Executive Director I Alison George, Division Director nr Vie; r
�S•,
s 1313 iheiman SL., Room 320, Denver, CO 80Z03 P 303.864.7810 r 3U3.864.7857 TDD/TTY 303.864.7758 www.dola.colorado.Qov
Sl engthening Colorado Communities
ROUAL HOUSING
OPPORTUNITY�,,lA7
COLORADO
Department of Local Affairs
Nvision otkousino JULY 2023
"OC" (On -site Construction) Form
Please read below before signing form.
Please See Attached Document at bottom of form for Specific plan and Manufacturer information.
To: The Local Authority Having Jurisdiction (LAHJ) or other DOH approved third party inspection
agency.
By signing this form, you confirm that you have received and reviewed this form, and acknowledge that
the identified components below are required to complete the construction of this modular structure
onsite within your jurisdiction.
Building Official Responsibility
Please check the box labeled "Accept" and initial to confirm that you will take responsibility for
inspections of the "OC" Inspection Items on behalf of the DOH. You also acknowledge that it will be
done to the DOH approved plans.
If you would like to defer inspection of the "OC" Inspection Items back to the DOH, please check the
box labeled "Defer Inspection".
"ATTENTION*
"On -site Construction" or "OC" means on -site construction or modification of the factory -built structure
that directly relates to the durability, quality, and safety; that is completed at the installation "site" as
defined by section 24-32-3302(33), C.R.S.; using components not installed at the manufacturer's
location; and to complete the compliance of that structure as reflected in the Division of Housing
approved plans. These items do not include the component(s) required for setting and securing the
structure for its installation.
Fire Safety Official Responsibility (if applicable)
The DOH defers the requirement of any fire protection system for all modular IBC (Section 901.2) and
IRC (Section R313) structures as follows:
An automatic fire sprinkler system shall be installed in buildings (IBC) OR one and two family dwellings
and townhouses (IRC) OR Tiny homes as required by the local jurisdiction where the structure or home
wilt be set. Final tests required by this Section shall be approved by a certified inspector. The inspector
must be either an employee of the fire department having jurisdiction or another qualified individual
with prior approval of the Colorado Division of Fire Prevention ft Control.
Wild Fire mitigation requirements will be deferred for (IBC) OR one and two family dwellings and
townhouses (IRC) OR Tiny homes as required by the local jurisdiction where the structure or home will
be set. Final inspections required by locals shall be approved by a certified inspector. The inspector .
must be either an employee of the fire department having jurisdiction or another qualified individual
with prior approval of the Colorado Division of Fire Prevention it Control.
Governor Jared S. Pops I Rick M. Garcia. Executive Director i Alison George, Division Director
!� 1313 Sherman St., Room 320, Denver, CO 80203 P 303.864.7810 F 303.864.7857 TDD/Try.103.864.7758 www_dola.colorado.gov r0
Strengthenfna, Colorado Canmunitles 1
EQUAL HOUSING k4C�,
OROSfUN11'Y "" ,
ar'
COLORADO
Department of Local Affairs
Dlvtsion nl Wousing JULY 2023
Building Department Representitive Printed Name
Building Department Representitive Signatlre
Title G�SlGa1t-�G b G�AcL.-
Date 10 -Z4-z5
❑r1*RF o.
Accept Defer Inspection Contact email:���I•J. C►t¢+..pCa4+,qY[
GOV
If applicable:
Fire Safety Official Printed Name__..
Fire Safety Official Signature.. .:_ _ —Date__
Contact email:
Is a fire protection system required? (check one) Required Not Required
If required, the inspection is to be performed by (check one):
Fire Department: WA✓ T
OR
Colorado Division of Fire Prevention Ft Control
Manufacturer's Authorized Quality Assurance Representative
Printed Name kRls W6,6Y Al.5 0 W
Manufacturer's Aut XTI-
y ssuranre Representative
Signature -- Date
Contact ail:�ro visors S-kALAu=t.c.orn
If the inspection has been deferred and the manufacturer elects to utilize an Approved Third Party
Agency to inspect the "OC" items on behalf of DOH, please sign and date below.
Approved Third Party Agent Printed Name
Approved Third Party Agent Signature Date
Contact email:_
Governoi Jared S. POWs I Rick M Garcia. Executive Director i Alison George. Division Director of i q
>r 1373 Shr_nnan St., Room 320. Denver, CD 80Z03 P 303.864.7810 F 303.864.7357 TDD/TTY 303.864.T758 www.dola.colorado.gov yS •,;,..-V
Strengthening Colorado Communities
j*
oOPPORrillr UNITY
COLORADO
A9.01 Department of Local Affairs
Mvision OF) frusinq JULY 2023
Verify Inspection(s) Completed
Once you have completed all of your assigned inspections identified in this form and they have passed
for compliance, please sign and date below.
Building Department Representitive Printed Name
Building Department Representitive Signature
Date
Contact email:
Or
Approved Third Party Agent Printed Name,_
Approved Third Party Agent Signature _ _ �. _._Date
Contact email:
Fire Protection Systems (if applicable)
Fire Safety Official Printed Name_
Fire Safety Official Signature Date
Contact
Please direct questions to manufactured. alansstate.co.us
Governor hired S Polls I Rick ,A Garcia, Executive Director I Alison George. Division Director "co
1313 Sherman St.. Room 320, Denver CO 80203 P 303.864 7810 F 303.864.7857 TDD/TTY 303.864,7758 www.dota.colorado.gov� ,
Strrngtheninj, Colorado CommunitiP;
COUAL HOUSR40
OPPORTUNITY } Igy6 ;'
COLORADO
Department of Local Affairs
Dlvlsion of Housing
JULY 2023
The following is based on information provided to the Division of Housing (DOH) and may be modified
based on the actual findings of the field inspection.
DATE: 12-5-24
MANUFACTURER: Kit HomeBuilders West ID NO.: 000175
CONTACT: Matt Duree
MODEL NO.: 2512-M Laidlaw CO
INSPECTION REQUIREMENTS: Check on site:
"OC" Inspection Items
PHONE No.: 208-454-5012
DOH P/A NO.: R-00065130C
i], .:[riir .ti_ie r+_n1L inn rrticif sRr�llr__ nnA flnr�r nnnnnrtinn&
r i
- Insulation basement walls per ResCheck.
- All landings, complete siding and trim.
- Complete stairway construction.
- Complete installation of drain lines and service hook-up.
- Installation of furnace and ducting.
- Complete water heater pop -off and drain pan drain to exterior of home.
- Complete furnace condensation drain line to exterior of home.
- Waterline marriage line connections and service hook-up.
Complete installation of gas lines and service hook-up.
- Electrical connections to furnace.
- Electrical marriage line connections.
- Electrical service hook-up.
Complete thermal envelope
1313 Sherman St.
EOUAL HOWMNG
OPPOITUNITY
Governs, Jared S. PoLs I RickM. Garcia, Executive Director I Alison George, Division Director ci.�_nE '.
Room 320, Denver, CO S02.03 P 303 864.7810 F 303.864.7857 TDDiM 303.864.7798 www.dota.coforado.guy
,
SUengthening Colorado Communities k
x r878 "