HomeMy WebLinkAbout1.18 Kumar Pavement StudyLake Springs Ranch Subdivision Preliminary Plan/PUD Amendment December 2025 Exhibit 18 | Pavement Subsoil Study H-P ~KUMAR Geotechnical Engineering l Engineering Geology Mate ri als Testing I Environmental 5020 County Road 154 Glenwood Springs, CO 81601 Phone: (970) 945-7988 Fax: (970) 945-8454 Email: hpkglenwood@kumarusa.com Office Locations: Parker, Glenwood Springs, and Silverthorne, Colorado December 16, 2016 Mike Berkeley c!o TGMC, Inc Attn: Tim Malloy 402 Park Drive Glenwood Springs, Colorado 81601 tim@tgmalloy.com Subject: Gentlemen: Project No.16-7-318 Subsoil Study for Pavement Section Design, Proposed Lake Springs Ranch Development, County Roads 114 and 115, Garfield County, Colorado As requested, H-P/Kumar performed a subsoil study for pavement section design at the subject site. The study was conducted in accordance with our proposal for geotechnical engineering services to Mike Berkeley dated June 3, 2016. The data obtained and our recommendations based on the proposed construction and subsurface conditions encountered are presented in this report. Proposed Construction: County Road 114 and a short distance of County Road 115 totaling about 1 ½ miles are proposed to be asphalt paved as part of the Lake Springs Ranch development. The roadway alignment and grades will mostly not change significantly from the existing roadway shown on Figure 1. Traffic loadings have not been provided except for current and projected traffic volumes for buildout of the proposed Lake Springs Ranch development. The traffic loading will need to consider temporary construction vehicles including heavy trucks. If proposed conditions or traffic loadings are significantly different from those described above, we should be notified to re-evaluate the recommendations piesented in this report .' Site Conditions: County Roads 114 and 115 are asphalt and chip surface paved, 2 lane roadways. The grades are gentle to moderate and typically shallow cuts and fills were used to construct the roadways. A small pond is located near the middle of the project alignment near Boring 6 shown on Figure 1. Vegetation along the roadway mainly consists of native grass, weeds and sage brush. Basalt rocks are locally exposed on the ground and in road cuts. Subsurface Conditions: The subsurface conditions along the roadway alignment were evaluated by drilling 12 exploratory borings located approximately as shown on Figure 1. The logs of the borings are presented on Figure 2. The subsoils encountered, below existing -2 - pavement materials, typically consist of sandy clay and silty sandy clay with gravel. The section of about¼ mile at Borings 3, 4 and 5 mainly encountered basalt rocks in a silty clayey sand matrix. The soils have low to medium plasticity and Hveem stabilometer testing performed on samples of the clay, presented on Figures 4 and 5, resulted in "R" values of 5 and 9. No free water was encountered in the borings at the time of drilling and the soils were slightly moist to moist. The boreholes were backfilled with cuttings and patched following drilling completion. Subgrade and Traffic Conditions: The subgrade conditions encountered in the exploratory borings were somewhat variable but typically consist of low to medium plastic clay soils with Hveem "R" values of 5 and 9 on the samples tested. An "R" value of 7 was used for design purposes which correlated to a resilient modulus (Mr) value of 3200 psi. Design traffic loading for flexible (asphalt) pavement was estimated using a current average daily traffic (ADT) of about 200 and a future ADT of about 900 each way with 3% of the traffic single unit trucks and 2% of the traffic combination trucks. This results in an average 20 year design equivalent single axel load (ESAL) of about 176,000. The truck traffic loading would include temporary construction vehicles but these numbers should be reviewed by the project designers. Pavement Section Design: Using the above subgrade condition (Mr=3200 psi) and assumed design traffic information (20 year ESAL=0. l 76xl 06), an initial serviceability of 4.5, a terminal serviceability of 2.5, and a reliability of 95%, we recommend the pavement section consist of 4 inches of asphalt on 6 inches of base course on 10 inches of sub base. The design section assumes structural coefficients of0.44 for asphalt, 0.14 for base course and 0.10 for subbase. Pavement Material Properties: The asphalt should be a batched hot mix approved by the design engineer and placed and compacted to between 92% and 96% of the theoretical maximum density. The base course should meet CDOT Class 6 and the subbase should meet CDOT Class 2 aggregate base course specifications. The base course, subbase and required subgrade fill should be compacted to at least 95% of standard Proctor density within 2% of optimum moisture content. The placement and compaction of base and asphalt materials should be monitored and tested on a regular basis by a representative of the geotechnical engineer. Subgrade Preparation: Required fill to establish design subgrade elevation can consist of the onsite soils or suitable imported soils meeting the project specifications. Prior to fill or pavement placement, the subgrade should be stripped of unsuitable materials, scarified a depth of 8 inches, adjusted to within 2% of optimum moisture content and compacted to at least 95% of standard Proctor density. In soft or wet areas, the subgrade may require drying or stabilization prior to fill placement. A geogrid such as Tensar TX 140 and sub-excavation and replacement with aggregate base soils may be needed for the stabilization. The subgrade should be proof rolled. Areas that deflect excessively should be corrected before placing pavement materials. The subgrade improvements should be monitored and tested on a regular basis by a representative of the geotechnical engineer. Limitations: This study has been conducted in accordance with generally accepted geotechnical engineering principles and practices in this area at the time of this study. We make no warranty either express or implied. The findings and recommendations submitted in this report are based upon the data obtained from the exploratory borings drilled at the locations indicated on Figure 1 H-P~KUMAR Project No. 16-7-318 -3 - and to the depths shown on Figure 2, the proposed construction, and our experience in the area. Our findings include interpolation and extrapolation of the subsurface conditions identified at the exploratory borings and variations in the subsurface conditions may not become evident until excavation is performed. If conditions encountered during construction appear different from those described in this report, we should be notified at once so re-evaluation of the recommendations may be made. This report has been prepared for the exclusive use by our client for design purposes. We are not responsible for technical interpretations by others of our information. As the project evolves, we should provide continued consultation and field services during construction to review and monitor the implementation of our recommendations, and to verify that the recommendations have been appropriately interpreted. Significant design changes may require additional analysis or modifications to the recommendations presented herein. We recommend on-site observation of excavations and testing of structural fill and pavement materials by a representative of the geotechnical engineer. If you have any questions or if we may be of further assistance, please let us know. Respectfully Submitted, H-P~KUMAR Rev. by: DAY SLP/ksw Attachments: Figure 1 -Location of Exploratory Borings Figure 1 -Logs of Exploratory Borings Figure 3 -Legend and Notes Figure 4 -Gradation Test Results Figures 5 and 6 -Hveeni Stabilometer Test Results Table 1 -Summary of Laboratory Test Results cc: High Country Engineering-Dan Dennison (ddennison@hcen g.com) H-P ~KUMAR Project No. 16-7-318 l~ ~i '' -~ i ~-----L ____ _ PROPOSED LAKE SPRINGS RANCH ------400 0 400 800 APPROXIMATE SCALE-FEET ~!1-------.-----------""""T"-----------------"T-----1 :!/ it 16-7-318 H-P~KUMAR LOCATION OF EXPLORATORY BORINGS Fig. 1 ~t ....... ____ .....__ __________ ......_ _________________ ..._ ___ _, BORING 1 BORING 2 BORING 3 BORING 4 12/6,50/5 WC=13.2 73/12 D0=84 0 12/12 (6) 10/12 m -200=53 0 WC=2.4 LL=41 1 WC=11.5 WC=14.2 +4=51 Pl=17 iDD=111 D0=108 -200=27 I A-7-6 (7) I I t-50/6 50/0 t-w w w w i.... i.... I 5 5 I :r: 15/12 42/12 :r: t-t-a. a. w w 0 13/12 20/12 0 WC=13.7 WC=11.9 -200=92 -200=94 LL=39 LL=38 Pl=21 Pl=22 10 A-6 (19) A-6 (21) 10 BORING 5 BORING 6 BORING 7 BORING 8 19/12 WC=9.1 0 ~:l '7 15/6,50/0 (4) D0=109 (3) (3) 13/12 0 -200=77 (4) LL=40 41/12 WC=7.0 WC=17.8 • • WC=11.1 Pl=12 D0=101 -200=38 A-6 (9) +4=17 t-36/1 2 -200=54 t-w w w w i.... i.... I 5 5 I :r: 33/12 48/12 16/12 :r: t-t-a. a. w w 0 5/6, 18/6 16/12 0 WC=15.4 WC=13.7 D0=95 -200=96 -200=88 LL=46 Pl=27 10 A-7-6 (28) 10 BORING 9 BORING 10 BORING 11 BORING 12 28/12 WC=14.2 20/12 15/12 0 (3) D0=103 (4) (2) (1) 0 i (3) • -200=71 WC=11.1 (4) WC=14.0 a LL=48 jDD=111 20/12 D0=111 V Pl=22 1-200=94 -200=95 . I 0 A-7-6 (15) I 29/12 ' I m t-154/12 t-~ WC=10.3 :;; w w l w D0=114 w i.... i.... I 5 5 I e :r: 36/12 ]63/12 60/12 35/12 :r: ~ t-t-a. WC=12.6 a. w w ~ 0 24/12 WC=17.5 36/12 -200=90 0 J WC=16.8 -200=84 WC=12.1 LL=37 l DD=94 LL=47 -200=79 Pl=21 -200=53 Pl=11 LL=39 A-6 (18) ~~ LL=46 A-7-5 (12) Pl=21 z~ 10 Pl=6 A-6 (16) 10 0 1 A-7-5 (2) ~ '' -~ ~! .;~ a,:; ii 16-7-318 H-P~KUMAR LOGS OF EXPLORATORY BORINGS Fig. 2 E f ... ~,<.' a> ij i~ o,!. I I ~:e ~~ LEGEND (5) I ASPHALT, THICKNESS IN INCHES SHOWN IN PARENTHESES TO LEFT OF THE LOG. (5) I ~~~~COURSE, THICKNESS IN INCHES SHOWN IN PARENTHESES TO LEFT OF THE [71 CLAY (CL); SLIGHTLY SANDY TO SANDY, SCATTERED GRAVEL, STIFF TO VERY L_j STIFF, SLIGHTLY MOIST TO MOIST, MIXED BROWN, MEDIUM TO HIGH PLASTICITY. [71 SAND AND CLAY (SC-CL); SILTY, GRAVEL AND COBBLES , MEDIUM DENSE/VERY Lj STIFF, LIGHT BROWN, CALCAREOUS, LOW PLASTICITY. ~ GRAVEL (GM-GC); SILTY, CLAYEY, SANDY, COBBLES, PROBABLE BOULDERS, Ed MEDIUM DENSE, GRAY-BROWN, CALCAREOUS, BASALT ROCK. p ~ RELATIVELY UNDISTURBED DRIVE SAMPLE; 2-INCH 1.0. CALIFORNIA LINER SAMPLE. DRIVE SAMPLE; STANDARD PENETRATION TEST (SPT), 1 3/8 INCH 1.0. SPLIT SPOON SAMPLE, ASTM D-1586. ~] DISTURBED BULK SAMPLE. / DRIVE SAMPLE BLOW COUNT. INDICATES THAT 10 BLOWS OF A 140-POUND HAMMER 1 O 12 FALLING 30 INCHES WERE REQUIRED TO DRIVE THE CALIFORNIA OR SPT SAMPLER 12 INCHES. t PRACTICAL AUGER REFUSAL. NOTES 1. THE EXPLORATORY BORINGS WERE DRILLED ON OCTOBER 20, 2016 WITH A 4-INCH DIAMETER CONTINUOUS FLIGHT POWER AUGER. 2. THE LOCATIONS OF THE EXPLORATORY BORINGS WERE MEASURED APPROXIMATELY BY PACING FROM FEATURES SHOWN ON THE SITE PLAN PROVIDED. 3. THE ELEVATIONS OF THE EXPLORATORY BORINGS WERE NOT MEASURED AND THE LOGS OF THE EXPLORATORY BORINGS ARE PLOTTED TO DEPTH. 4. THE EXPLORATORY BORING LOCATIONS SHOULD BE CONSIDERED ACCURATE ONLY TO THE DEGREE IMPLIED BY THE METHOD USED. 5. THE LINES BETWEEN MATERIALS SHOWN ON THE EXPLORATORY BORING LOGS REPRESENT THE APPROXIMATE BOUNDARIES BETWEEN MATERIAL TYPES AND THE TRANSITIONS MAY BE GRADUAL. 6. GROUNDWATER WAS NOT ENCOUNTERED IN THE BORINGS AT THE TIME OF DRILLING. 7. LABORATORY TEST RESULTS: WC = WATER CONTENT (%) (ASTM D 2216); DD = DRY DENSITY (pcf) (ASTM D 2216); +4 = PERCENTAGE RETAINED ON NO. 4 SIEVE (ASTM D 422); -200= PERCENTAGE PASSING NO. 200 SIEVE (ASTM D 1140); LL = LIQUID LIMIT (ASTM D 4318); Pl = PLASTICITY INDEX (ASTM D 4318); A-6 {19) = AASHTO CLASSIFICATION (GROUP INDEX) (AASHTO M 145). ~~-----------------....... -----------------------ii 16-7-318 I H-P~KUMAR I LEGEND AND NOTES I Fig. 3 o>,__ _____ ...._ _________ _.,_ __________________ _.,_ ___ __, E -g ¾~ !7 ,', ·= I I HYDROMETER ANALYSIS SIEVE ANALYSIS TIME READINGS U.S. STANDARD SERIES CLEAR SQUARE OPENINGS J 24 HRS 7 HRS 100 45 MIN 15 MIN 60MIN 19MIN .4MIN IMIN .:aa 1100 •so ,..,a 130 .,. ,10 ,a • 3/8'" 3 1 ,· 1 112" 3 " 5"6" ' ! ' i a ' --i I I i ! 90 ' 10 V I i I I I ea '' 20 ! :-! I I 70 I 30 : : I I I ! --+-60 f---,a so I l so ! i I I I •o i -+-----r+ --60 I ! I I I ! 30 I 70 i I i I 20 f-80 I I ! I 10 ; I i ! 90 i I ! l 0 I I I I I I I I I i I i 100 .001 .002 .005 .009 .019 .037 .075 ,150 .300 .600 ... 1.18 1 2.36 4.75 •. s 19 38.1 76.2 127 , 200 CLAY TO SILT GRAVEL 3 " LIQUID LIMIT 31 SAMPLE OF: Sandy Clay HYDROMETER ANALYSIS TIME READINCS 24 HRS 7 HRS .425 2.0 152 DIAMETER OF PARTICLES IN MILLIMETERS SAND GRAVEL 1-------.--------,.----t------,.--------1COBBLES SAND FINE MEDIUM COARSE FINE COARSE 12 % PLASTICITY INDEX U.S. STANDARD SERIES SILT AND CLAY 16 85 % FROM: Boring I O I' -4' SIEVE ANALYSIS CLEAR SQUARE OPENINGS I 100 .... MIN , .. MIN 6OMIN 19MIN .tMIN 1MIN •~oo •100 •so •40 •30 •~5 •10 ~B ·--._I __ --+---+---+ 1 , __ --,' ----<----+ l I ~~ l l 3• s1"s_" e" 0 i l ' -: i 1 ·:~_ ~ --==---,.----t·--+----r---r ·7· ---+-----+---+---+---------1---...-"'~'--4--..;-+-'--+--...;:_ t----+---+---+---+I----+! ---+!--ii 90 80 JO 20 I J i I I ! ! I . I : V ,, ,,, 10 ---+-----~--1------+1---+---! 1 I 7--~+-30 ____ L_ -, . --+----: +---+--+--+----+--~i_J___ ___ --~--~-__ l ____ l __ ~--40 BO j I I i ] ! j i • ! t ; 1 i I so 1---~---1---+----+.--~----· r·----r·--+--<---+--+---i'---+---"'-----+---· 1 j ! I j l l I so ea ,a ----r----------+---1------:------t----------+ ----t-··+--l----.---,:-r-----~,,-----~------~ -----+----r - ___ : -! ti_j !----: :_ -___ J __ _,_ ____ t---!-----H-70 30 i i 20 1---,-----e---+----+---"-· I 1 ! : l j I I I l I l ' l 1 1 l ! [ ~ , ---+---, ea l i ; ; : I 10 I I ! l l I I I i I •a -j-i -r-----r--;, !·---;-!--i 7 Jj .0·~0'"1 --_-;;a-::-02:;--''-'-1 .""o~;::5;"' ... ''--':.'o"'o~~--:.0~11"•--'-:;·oca'37!:--''--'--:! 1 .0:':~'a-, 'w''---:. 1°"s""o ... ,_..,_3°'00,,-J'--''-,.•"'~0""1-''-'1-''1:-_,-;: e:;---,2,.,t . .:!l"'s'-1 -'',:-_!a~s;-'-'.J...J. ''-:!-~ :.,,, ,---,1-=~---'-,"'•="'. 1,-.1.....J 1 '--1:!:s"=.2='-'-1 -:-1 "'~1="' 1 '-::-!2001 00 CLAY TO SILT GRAVEL 4 " LIQUID LIMIT 43 .425 2.0 152 DIAMETER OF PARTICLES IN MILLIMETERS GRAVEL SAND t-------,-------.-----1r-----.-------tCOBBLES FINE MEDIUM SAND 24 % PLASTICITY INDEX COARSE FINE SILT AND CLAY 13 COARSE 72 " SAMPLE OF: Calcareous Sandy Silty Clay FROM: Boring 10 0 1'-4' i ~ l,! It These test results apply only to the samples which were tested . The testing report shall not be rtproduced, except In full, without the written approval of Kumar & A:1:sociotes, Inc. Sieve analysis testing is performed in occordance with ASTM 0422, ASTM C136 and/or ASTM 01140. ~"§" .gt---------.-------------------.------------------------------,.-------1 H 16-7-31a H-P~KUMAR GRADATION TEST RESULTS Fig. 4 !~._ ________ .._ __________________ .._ ____________________________ ...., ______ .., R-VALUE TEST SPECIMEN 1 2 3 4 R-VALUE (300 psi) MOISTURE CONTENT(%) X DENSITY (pct) X EXPANSION PRESSURE (psi) X EXUDATION PRESSURE (psi) X R-VALUE X <5 100 90 80 70 60 C1> :I ca 50 >, ~ 40 30 20 10 0 0 100 200 300 400 500 600 700 800 EXUDATION PRESSURE (psi) SOIL TYPE : Sandy Clay (CL) A-6 (12) LOCATION : CR114 Garco, Boring 1@ 1-4' DATE SAMPLED: DATE RECEIVED : DATE TESTED : 11/17/16 GRAVEL: 3 SAND: 12 SILT AND CLAY: 85 These test results apply lo the samples which were tested. The testing report shall not be reproduced , except tn full. without the written approval of Kumar & LIQUID LIMIT: 31 PLASTICITY INDEX : 16 Associates , Inc, R~value performed in accordance with ASTM 02844. Atterberg limits performed in accordance with ASTM 04318. Sieve analyses performed In accordave wrth ASTM D422, 01140 16-7-3181 HP/KUMAR HVEEM STABILOMETER TEST RESULTS Fig 5 R-VALUE TEST SPECIMEN 1 2 3 4 R-VALUE (300 osil MOISTURE CONTENT(%) 41.7 40.3 38.5 DENSITY (pct) 97.7 96.2 102.7 EXPANSION PRESSURE (psi) 0.000 0.000 0.000 EXUDATION PRESSURE (psi) 268 327 502 R-VALUE 6 10 12 9 100 90 80 70 60 Cl) ::I ni ~ 50 0::: 40 30 20 10 ✓r 0 0 100 200 300 400 500 600 700 800 EXUDATION PRESSURE (psi) SOIL TYPE : Calcareous Sandy Silty Clay LOCATION: CR114 Garco, Boring 10@ 1-4' DATE SAMPLED: DATE RECEIVED : DATE TESTED: 11/17/16 GRAVEL: 4 SAND: 24 SILT AND CLAY: 72 These test results apply to the samples which were tested. The tl!!sting report shall not be reproduced, except in full . without the written approval of Kumar & Associates, Inc. R-value performed in accordance with LIQUID LIMIT: 43 PLASTICITY INDEX: 13 ASTM D2844. Atterberg limits performed in accordance with ASTM 04318. Sieve analyses performed in accordave with ASTM 0422, 01140 16-7-3181 HP/KUMAR HVEEM STABILOMETER TEST RESULTS Fig 6 H-P~l<UMAR TABLE 1 SUMMARY OF LABORATORY TEST RESULTS Project No. 16-7-318 . Page 1 of 2 SAMPLE LOCATION NATURAL NATURAL GRADATION ATTERBERG LIMITS AASHTO PERCENT HVEEM"R" MOISTURE DRY GRAVEL SAND PASSING LIQUID PLASTIC VALUE CLASS-SOIL OR BORING DEPTH CONTENT DENSITY NO. 200 LIMIT INDEX IFICATION BEDROCK TYPE (%) (%) SIEVE (ft) (%) (pcf) (%) (%) 1 1 11.5 111 Sandy Clay 1-4 3 12 85 31 16 5 A-6 (12) Sandy Clay 3 13.7 92 39 21 A-6 (19) Slightly Sandy Clay 2 1 14.2 108 Sandy Clay 3 11.9 - ' 94 38 22 A-6 (21) Slightly Sandy Clay 3 1 2.4 51 22 27 Silty Clayey Sandy Gravel 4 1 13.2 84 53 41 17 A-7-6 (7) Calcareous Silty Clay and Sand with Gravel 5 1 11.1 38 Silty Clayey Sandy Gravel 6 1 9.1 109 77 40 12 A-6 (9) Silty Sandy Clay with Gravel 3 15.4 95 88 Silty Sandy Clay with Gravel 7 1 and 3 7.0 17 29 54 Silty Sand and Clay with (combined) Gravel SAMPLE LOCATION NATURAL NATURAL MOISTURE DRY BORING DEPTH CONTENT DENSITY (ft) (%) (pcf) 8 1 17.8 101 3 13.7 9 1 14.2 103 3 16.8 94 10 1 11.1 111 1-4 3 and 5 17.5 (combined) 11 3 12.1 - 12 1 14.0 111 3 10.3 114 5 12.6 H-P~l<UMAR TABLE 1 SUMMARY OF LABORATORY TEST RESULTS GRADATION ATTERBERG LIMITS PERCENT HVEEM"R" GRAVEL SAND PASSING LIQUID PLASTIC VALUE NO. 200 LIMIT INDEX (%) (%) SIEVE (%) (%) 96 46 27 71 48 22 53 46 6 94 4 24 72 43 13 9 84 47 11 79 39 21 95 90 37 21 . AASHTO CLASS- IFICATION A-7-6 (28) A-7-6 (15) A-7-5 (2) A-7-5 (10) A-7-5 (12) A-6 (16) A-6 (18) Project No.16-7-318 Page 2 of 2 , SOIL OR BEDROCK TYPE Silty Sandy Clay Slightly Sandy Clay Sandy Clay Clayey Silt and Sand Slightly Sandy Clay Calcareous Sandy Silty Clay Calcareous Sandy Silty Clay Sandy Clay with Gravel Slightly Sandy Clay Sandy Clay Sandy Clay